Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
GASTECH 2OO2
Mario Dogliani
RINA SPA
Italy
PROGRAMME
1. Introduction
Within the AZURE R&D project, a complete feasibility analysis of a FULL FLOATING LNG chain was
carried out covering design aspects of the LNG FPSO (Floating Production Storage Offloading), the LNG
shuttle tanker fleet, the LNG FSRU (Floating Storage Re-gasification Unit) as well as the BTT (Boom To
Tanker) LNG transfer system.
Outlines of the overall project results as well as of a few specific design aspects were presented in a series
of papers at GASTECH 2000 /1/, /2/, /3/, /4/; the aim of this paper is to complete this overview by
providing insight into the specific safety aspects of the FSRU and the related gas transfer system.
More specifically the key issues of an FSRU’s safety can be identified as follows:
ß risk acceptance criteria: the FSRU is an hybrid installation which presents features (and risks)
typical of both offshore oil storage units and of oceangoing LNG ships; hence, ad hoc risk
acceptance criteria are needed;
ß results of the risk assessment – FSRU topside: from a design standpoint, the topside is of
particular interest since, contrary to LNG oceangoing ships, the process equipment located there is
normally operating thus introducing risks neither normally considered nor regulated onboard
ships;
ß results of the risk assessment – BTT LNG transfer system: the LNG transfer system is clearly the
most critical issue from both safety and operational standpoint, detailed re-design based on risk
assessment was a must in the project;
ß applicability of the IGC Code: several safety issues can be approached based on the International
Code of Safety of Gas Carriers (IGC Code), particularly as far as LNG storage, floater’s stability,
power generation & distribution and crew accommodation are concerned.
After providing an outline of the safety assessment procedure adopted in the study, on purposely
developed for this type of unit, the above safety issues are presented in the following paragraphs,
providing details on the initial design, safety assessment, risk quantification and identified risk mitigation
measures.
As a result of the study, it was proved that present technology allows the construction and operation of
FSRU units which are at least as safe as presently operating offshore oil storage floating installations: the
basis of this statement are illustrated and documented in the present paper.
The considered FSRU, whose main characteristics are provided in table 1, is a monohull floating terminal
(see figure 1) where the LNG is received, stored, vaporised and exported to the onshore gas distribution
network.
Loa (m) - length overall 285.0
Lbp (m) - length between perpendiculars 240.0
B (m) - breadth 50.0
Dfl (t) - displacement at full load 141,600
Dbl (t) - displacement in ballast conditions 98,000
Tfl (m) - maximum draught (full load) 12.6
Tbl (m) - ballast draught 8.95
Table 1: FSRU’s main characteristics
The unit was conceived with 200,000 m3 LNG storage capacity, 10,000 m3/h transhipment flow rate and
450,000 m3/h re-gasification rate. LNG storage is achieved by means of four LNG storage tanks, through
the GTT membrane containment technique, with a boil-off rate lower than 0.15% per day. Further details
on the FSRU and its ancillary systems can be found in /2/.
Dogliani page. 2
PROGRAMME
LNG is loaded into the FSRU via tandem connection; in this situation the fundamental requirements for
the BTT system are to work in cryogenic operative conditions and to compensate the relative motions
between the FSRU stern and the LNG shuttle tanker's bow.
The BTT main components, are:
ß the boom, able to slew around the kingpost to compensate for relative angular motions ("fish tailing")
in the horizontal plane (± 70°) of the two floaters
ß the double pantograph system, which compensates for relative wave frequency motions
ß the automatic control system which monitors the relative position of the two vessels and controls the
emergency procedures.
3. Safety assessment procedure
3.1 General
The objective of the FSRU safety assessment was to review potential internal accident scenarios
associated with its operation and to identify design modifications to reduce the associated risks. This was
achieved by means of a preliminary hazard analysis of the FSRU which involved the assessment of
potential hazards, their screening and the incorporation into the design of remedial measures.
The BTT is essential for the overall safety of the combined FSRU-LNG carrier system, therefore the
objective of its risk assessment was to estimate its safety level in all the operating phases of LNG transfer.
3.2 Assessment procedure
When the AZURE project started, an established safety assessment process for either a LNG floating
chain or each single item of the chain was not available, moreover, no specific codes, standards and
regulations addressing the full chain existed. Therefore, based on the review of applicable regulations and
on the identified gaps, the following tailor-made safety assessment framework was established:
Risk assessment technique Applied to
HAZard IDentification (HAZID) FSRU topside, FSRU, BTT
Failure Mode Effect & Criticality Analysis (FMECA) BTT
Zone Analysis (ZA) FSRU topside;
3.2.1 Preliminary steps
Before starting the safety assessment, the two following preliminary steps are required:
Dogliani page. 3
PROGRAMME
ß definition of the system under analysis, of its interfaces with other systems in the LNG chain and
identification of the mission profile;
ß execution of a functional analysis, consisting in the identification of all the functions needed for the
correct completion of the mission; this typically involves a classification of functions as follows:
- main functions which are necessarily active for the completion of the mission; depending on each
mission phase, not all the functions need to be simultaneously active.
- auxiliary functions aimed at supporting main functions
- constraint functions required to fulfil external constraints (environmental, legal, etc.)
- safety functions aimed at preventing or mitigating accidents or downgraded conditions.
3.2.2 HAZID
The HAZID is generally a structured brainstorming process which identifies potential accidents in each
mission phase. Possible causes of accidents, hazards, their consequences and any safeguards, which may
be in place to prevent them, are reviewed during the HAZID, which is broken down into three sequential
stages: hazard identification (i.e. what can go wrong), frequency assessment (i.e. how likely), and
consequence assessment (i.e. how bad).
The primary aim of the exercise is to identify as many failure conditions (or Hazards) as possible for each
mission phase. The exercise is also intended to provide relevant details of the failure effects, failure
causes, failure detection and regulations and to provide an estimate of probability and severity.
It carrying out the HAZID, the following process be followed:
1. consider each mission phase individually and identify as many relevant hazards as possible;
2. identify the causes, consequences and other relevant information for each hazard;
3. record all the generated information on HAZID worksheets.
3.2.3 FMECA
FMECA is an hazard identification technique based on a single failure concept under which each
individual failure is considered as an independent occurrence with no relation to other failures in the
system, except for the subsequent effect that it might produce. Through this technique, the ways
equipment can fail, the possible causes, the effects these failures on the system performance and their
ranking according to the combination of severity and probability of occurrence are documented.
The FMECA is carried out on a series of worksheets, where the results are listed in a tabular format,
equipment item by equipment item, following a systematic bottom up approach. Two different levels of
detail were considered in the analysis:
1st level: the analysis is carried out on the overall system, and each function of each main sub-system is
analysed;
2nd level: the analysis is carried for the components of sub-systems. Each conceivable mode in which a
component or unit can fail with respect to its intended function is analysed.
The 2nd level FMECA is performed for the sub-systems which failed the 1st level analysis; i.e.:
ß whose individual failure can cause major or more serious effects, and
ß where a redundant system is not provided, and
ß the probability of occurrence of acceptance criteria are not met.
3.2.4 ZA
The aim of Zone Analysis is to provide a detailed knowledge of the risk of occurrence of hazardous
failure in a given area and the risk of propagation of a local effect to the whole area and possibly beyond.
The basic scheme of a ZA is as follows:
ß define the objective of the study (e.g. a type of hazard)
ß for each zone, carry out an inventory of hazardous materials in the zone
Dogliani page. 4
PROGRAMME
ß collect data relative to process, segregation / separation criteria, detection / alarms, emergency
response etc.
ß assume occurrence of failure and assess local and end effect as well as likelihood
ß deduce risk picture for each zone.
3.3 Risk acceptance criteria
The consequences can be evaluated using the in-house physical modelling software tools available to the
companies. Likewise frequency calculations can be undertaken using reliability data. A point to note
however is that acceptability criteria only requires evaluation of the nearest order of magnitude. For this
reason judgmental ranking may be an acceptable replacement for quantitative analysis during the
preliminary design stage.
The selected acceptance criteria for the AZURE project are provided in the following tables.
F Annual Frequency Return Period / Annual Frequency
1 <10-5 Extremely improbable
2 10 - 10-4
-5
Extremely remote
3 10-4 - 10-3 Remote
4 10-3 - 10-2 Reasonably probable
5 > 10-2 Frequent
Dogliani page. 5
PROGRAMME
Dogliani page. 6
PROGRAMME
Dogliani page. 7
PROGRAMME
Dogliani page. 8
PROGRAMME
Dogliani page. 9
PROGRAMME
Concerning the applicability of the IGC Code, summary table 5.1 was developed and adopted in the
project; in this list only those items which resulted non completely applicable are shown.
IGC code requirement Application / remarks
Chapter 1 general
1.5 survey and certification Applicable. Arrangement to be provided for survey at sea.
Chapter 2 ship survival capability
2.2 freeboard and intact stability Applicable in principle. Towing to site to be considered.
2.5 damage assumptions. Applicable. Extent of side damage may need to be adapted. Bottom damage
not relevant as the FSRU is in a fixed site.
Chapter 3 ship arrangement
3.3 cargo pump room and cargo Applicable. Can be extended to process machinery and equipment. However
compressor room prime mover of hydrocarbon processing machinery need not to be located in
safe area if they are suitable for the zone class.
3.5 access to spaces in cargo area Applicable. Provisions to be taken for inspection at sea in operation.
3.6 airlocks Can be modified by MODU code para 6.3
3.8 bow/stern loading/unloading Applicable. Consideration to be given to permanent gas loading
Chapter 4 cargo containment
4.3 design loads Applicable. Criteria could be adapted to site specific dynamic loads and
probability of occurrence. Ditto for thermal loads.
4.7 secondary barrier Applicable. The containment period of 15 days designed for a standard
voyage to be adapted to the FSRU always at sea.
4.12 acceleration To be adapted to site, based on seakeeping analysis/model test
Chapter 5 process pressure vessels
5.2 cargo and process piping Applicable. The ANSI piping codes could also be used bearing in mind that
in general materials are not valid below – 29 deg. C
5.3 type tests Applicable. Number of cycles to be adapted to site
5.9 vapour return May be not necessary with the shuttle
Chapter 7 cargo press./temp. control
7.1 general Applicable. Flaring can be allowed. Site specific temperatures
Chapter 8 cargo tanks vent system
8.2 pressure relief systems Applicable. Flaring can be allowed
Chapter 10 electrical installations
10.1 general Applicable. Neutral regime, segregated in marine practice and connected to
the earth in offshore process practice, is to be clarified
10.2 types of equipment Applicable. Electric motors (safe type) could be allowed in hazardous areas.
Hazardous areas extent & class according to recognised standard (API 500,
IP code)
Chapter 11 fire protection and extinction
11.1 fire safety requirements Applicable. The presence of a process plant is to be taken into account.
Recognised standards such as NFPA can also be used.
Chapter 13 instrumentation
13.6 gas detection requirements Applicable. Individual detectors may be used instead of sampling.
Table 5.1 – summary of IGC Code non completely applicable requirements
5.2 Specific issues
5.2.1 Hazardous areas
The definition of hazardous areas should be in compliance with one of the following codes:
1. API 505
2. MODU Code
3. IP 15 "Area Classification Code for Petroleum Installations".
The latter is the most conservative and commonly used in the offshore industry and therefore suggested for this
specific application.
Dogliani page. 10
PROGRAMME
According to IP 15 Code, « a hazardous area is a three dimensional space in which a flammable atmosphere may be
expected to be present at such frequencies a to require special precautions for the construction and use of electrical
apparatus. All the other areas are referred to as non-hazardous …».
« The hazardous areas are subdivided in three zones as follow.
Zone 0. That part of the hazardous area in which a flammable atmosphere is continuously present or present for long
periods.
Zone 1. That part of the hazardous area in which a flammable atmosphere is likely to occur in normal operation.
Zone 2. That part of the hazardous area in which a flammable atmosphere is not likely to occur in normal operation
and, if occurs, will exist only for a short period ».
5.2.2 Internal combustion engines on the deck
As far as the location of the internal combustion engines on the deck is concerned, MODU Code was
considered according to which the cargo area (i.e., the portion of deck above the LNG tanks) is defined as
hazardous zone of type 2. Therefore it was concluded that internal combustion engines in Zone 2 can be
accepted if they are constructed to reduce the risk of ignition from sparking or high temperature in
compliance with a recognised standard (e.g. IP 15).
Additionally, engines situated on the roof of the cargo tanks are not normally accepted, therefore the
solution of a raised deck becomes the only way ahead. In this respect, the following rules can also fit the
design:
ß IGC Code establishes (indirectly) that, to be acceptable, this deck should be higher than 2.4 m;
ß IGC Code sets forth a minimum distance of 10 m between vent exits and the nearest intake or
opening to accommodation spaces, service spaces and control stations, etc.: this provides further
inputs as to how to build the raised deck, since a possible interpretation is that any potential gas
leak source must be at least 10 m away from any source of ignition.
So far, emphasis has been put on the gas leak as an initiating event, with the presence of sources of
ignition as possible causes of escalation. Assuming the generation modules are someway enclosed, care
should be taken to tackle the following issues:
ß spark control (possible solutions: raised exhaust stack, anti-spark equipment, etc.);
ß control of hot surfaces (e.g. by providing insulation to the exhaust stack );
ß discharge of gas e.g. through vents not free, but conveyed to the flare or to a safe position;
ß examination of the possibility of combustion of soot along the stack (soot formation is probably
unlikely if only methane is burnt).
Now, also the reverse should be analysed: that is, a generation module can be itself an initiating event,
possibly impacting on the tanks, for the following reasons:
ß fire
ß structural collapse (maybe as a consequence of a fire or helicopter crash)
ß missiles (the rotor disintegration of gas turbines)
The reliability of fire-fighting equipment and all the safety systems involved (detection, shutdown, etc.)
must be then demonstrated when the design is at a sufficient detail level. If the module is enclosed, the
walls should be capable of withstanding the missiles from gas turbines. The raised structure may require
structural and thermal calculations to verify the resistance to incidents, whose likelihood is to be properly
assessed.
6. Overall safety of the FSRU
The risk levels associated with the FSRU concept compared with current, accepted industry practices has
led to the conclusion that the FSRU risk profile is likely to at least equivalent to the risk profile of a
"normal" turret-moored FPSO. The rationale leading to this conclusion was a comparison of the primary
features of the FSRU with those of an FPSO, as outlined below:
• Process equipment – the FSRU has a very open, uncongested process area with a limited amount
of equipment that is thus well spaced out with no stacking required. Compared to an FPSO, this will
lead to:
Dogliani page. 11
PROGRAMME
Dogliani page. 12
PROGRAMME
unloading buoy, but with the use of dedicated LNG carriers and appropriate precautions during
manoeuvring, such hazards can be controlled.
7. Conclusions
The studies and analyses undertaken within the AZURE project in support of the FSRU design have
shown that the floating alternative for a LNG receiving terminal is a viable solution.
In particular, as discussed in this paper, based on a comprehensive risk assessment, it is judged that in
most instances the FSRU has a risk profile lower than the accepted risk of Crude oil FPSO and that the
reduced fire and explosion risks on the FSRU relative to the FPSO outweigh the few potential higher risks
identified in the analysis.
Moreover, these issues are considered to present risks that can be controlled during the engineering design
phase using existing LNG industry experience.
8. References
/1/ Mayer M., Sheffield J., Robertson A., Courtay R., "Safe Production of LNG on an FPSO”,
Proceedings GASTECH 2000, Houston, November 2000.
/2/ Scarpa G., Dogliani M., Ducert A., "A Floating LNG Receiving Terminal: a Possible Solution for
Italy”, Proceedings GASTECH 2000, Houston, November 2000.
/3/ Spittael L., Zalar M., Laspalles P., Brosset L., "Membrane LNG FPSO and FSRU - Methodology for
Sloshing Phenomenon", Proceedings GASTECH 2000, Houston, November 2000.
/4/ Marchand D., Prat C., Besse P., "Floating LNG: Cost and Safety Benefits of a Concrete Hull",
Proceedings GASTECH 2000, Houston, November 2000.
Dogliani page. 13