Sei sulla pagina 1di 16

FRONT END ENGINEERING DESIGN (FEED)

PEMBANGUNAN PIPA GAS GRISSIK-PUSRI

PIPELINE BUOYANCY AND STABILITY CALCULATION


DOCUMENT NO. PTGGP-00-PL-CAL-004

0 28-Mar-16 Issued for Bid BYN GAM SPR

A 29-Jan-16 Issued for Approval BYN GAM SPR


DISUSUN DIPERIKSA DISETUJUI

REV TANGGAL KETERANGAN MENGETAHUI

NO part of this document may be reproduced, in any form or by any means, except as permitted by
PT. PERTAMINA GAS
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 2 of 13
Stability Calculation

Lembar Revisi

Page Revision Page Revision Page Revision


A B 0 1 A B 0 1 A B 0 1
1 X 26 52
2 X 27 53
3 X 28 54
4 X 29 55
5 X X 30 56
6 X 31 57
7 X X 32 58
8 X 33 59
9 X 34 60
10 X X 35 61
11 X 36 62
12 X X 37 63
13 X 38 64
14 39 65
15 40 66
16 41 67
17 42 68
18 43 69
19 44 70
20 45 71
21 46 72
22 47 73
23 48 74
24 49 75
25 50 76
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 3 of 13
Stability Calculation

COMMENT SHEET

Komentar
No. Referensi / Paragraf / Kalimat Catatan
PT. Pertamina Gas
1 3.2 Definition Revise Definition Revised

2 1. Project Overview Revised

3 Attachment Revised

4 Design Pressure and Temperature Revised


FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 4 of 13
Stability Calculation

DAFTAR ISI
1. PROJECT OVERVIEW .................................................................................................... 5
2. OBJECTIVES ................................................................................................................... 6
3. MEASUREMENT UNITS, DEFINITIONS AND ABBREVIATIONS .................................... 6
3.1. Measurement Units................................................................................................ 6

3.2. Definitions .............................................................................................................. 7

3.3. Abbreviations ......................................................................................................... 7

4. APPLICABLE CODES AND SPECIFICATIONS ............................................................... 8


4.1. Indonesian Act and Regulations ............................................................................ 8

4.2. Project Documents ................................................................................................ 8

4.3. Codes and Standards ............................................................................................ 9

4.4. Order of Precedence ............................................................................................. 9

5. DESIGN DATA PARAMETER .......................................................................................... 9


5.1. Pipeline Design Life ............................................................................................... 9

5.2. Design Pressure and Temperature ...................................................................... 10

5.3. Onshore Pipeline Properties ................................................................................ 10

5.4. Pipeline Coating System ...................................................................................... 10

5.5. Longitudinal Weld Joint Factor ............................................................................. 10

6. METHODOLOGY ........................................................................................................... 10
6.1. Minimum SG ........................................................................................................ 10

6.2. Load Case ........................................................................................................... 11

6.3. Assumptions ........................................................................................................ 11

7. RESULT, ANALYSIS, AND RECOMMENDATION ......................................................... 12


7.1. Result .................................................................................................................. 12

7.2. Analysis and Recommendation............................................................................ 12

ATTACHMENT ...................................................................................................................... 13
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 5 of 13
Stability Calculation

1. PROJECT OVERVIEW
PT Pertamina Gas (Pertagas) plans to build new pipelines to support the plan of
distribution of gas for fertilizer, where the pipeline will deliver gas sourced from Grissik
Processing Plant heading to PUSRI Plant at Palembang.
A pig launcher will install in ConocoPhillips area and power source will provide via solar-
cell. This pig launcher will design for intelligent pig. Liquid drain from pig launcher will be
collected using dedicated portable drum. Nitrogen system will provided to operate SDV
and fusible plug for fire detection. Venting will be directed to Jambi-Merang facilities,
which will be EPCI scope of work. Drains will be disposed periodically by vacuum truck.
The project location is the construction site of the new gas pipeline. Pictures of these
locations can be seen on the following map. Pipeline planned through 3 (three) route, i.e.
Right of Way (ROW) ConocoPhillips, ROW PERTAGAS and ROW Jalan Raya
Palembang-Jambi. About 70 MMSCFD gas will transfered 171 km via 20” pipeline and
LBCV will be installed along this pipeline. Nitrogen from bottle also used for SDV and
fusible plug at this area. Pipeline will protected from corrosion with cathodic protection.
Outside the fence of Pusri area there will constructed receiving facilities that consist of
Pig Receiever, Slug Catcher and Gas Metering (ultrasonic type) and Instrument Air
System. Drain from the receiving facility will be disposed periodically by vacuum truck.
Venting from this facility will be routed to safe area. The required of electrical power will
be supplied from PT PUSRI fertilizer plant.

Figure 1-1: Project Route Grissik - PUSRI


FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 6 of 13
Stability Calculation

2. OBJECTIVES
The objectives of this document is to calculate pipeline stability and buoyancy for 20”
Onshore Gas Pipeline API 5L – X65 from Grissik to Pusri, to ensure negative buoyancy
in swampy areas.

3. MEASUREMENT UNITS, DEFINITIONS AND ABBREVIATIONS


3.1. Measurement Units
US Customary Unit is used to all design, figure, and specifications in general. Units
and abbreviations applied are:

Table 3.1 Measurement Units


Parameter Units Abbreviation
Area Square Feet ft2
Density Pounds per Cubic Feet lb/ft3
Flow Rate Mass Pounds per Hour lb/hr
Gas Million Standard Cubic Feet per Day MMSCFD
Liquid Barrels per Day BPD
Barrels per Liquid per Day (Well or Mixed BLPD
Fluid)
Barrel Oil per Day (oil) BOPD
Barrel Water per Day (water) BWPD
Gallon per Minute GPM
Gas Oil Ratio (GOR) Standard Cubic Feet per Standard Barrel Scf/stb
Head Feet ft
Heat British Thermal Unit BTU
Elevation Feet ft
Length Inch In
Feet ft
Mass Pound lb
Power Watt W
Kilowatt kW
Megawatt MW
Horse Power hp
Pressure Pound per Square Inch absolute or gauge psia or psig
Radiation British Thermal Unit per hour Btu/ft/hr
o
Temperature Degrees Fahrenheit F
Time Seconds s
Minute min
Hour hr
Velocity Feet per second fps
Volume Barrels (Petroleum) bbls
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 7 of 13
Stability Calculation

Parameter Units Abbreviation


Cubic Feet ft3
Gallons (US) gal
Dynamic Viscosity Centipoises cP
Kinematic Viscosity CentiStoke cSt

3.2. Definitions

The following parties are mentioned in this document:

COMPANY PT. Pertamina Gas (PERTAGAS) as the owner.


CONSULTANT (PTC, PT SINGGAR MULIA), the party that carries out
all or part of the Front End Engineering Design
CONTRACTOR The party that carries out all or part of the detail
engineering, procurement, construction, installation
and commissioning
VENDOR/SUPPLIER Party which supplies equipment/materials or services
specified and ordered by CONTRACTOR (or
COMPANY)
MANUFACTURER Party which manufactures equipment/materials
specified and ordered by CONTRACTOR (or
COMPANY)
SUBCONTRACTOR The party(s) that carry out all or part of the design,
procurement, installation and testing of the systems
as specified by CONTRACTOR

3.3. Abbreviations
AFC Approved For Construction
API American Petroleum Institute
BOPD Barrels of Oil Per Day
BPD Barrels Per Day
BWPD Barrels Water Per Day
CV Curriculum Vitae
°C Celcius degree
EPC Engineering, Procurement and Construction
DSS Design Submission Schedule
°F Fahrenheit degree
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 8 of 13
Stability Calculation

FEED Front End Engineering and Design


HDPE High Density Polyethylene
HSE Health and Safety Environment
ITP Inspection and Test Plan
LBCV Line Break Control Valve
MMSCFD Million Standard Cubic Feet per Day
NACE National Association of Corrosion Engineers
PP Peraturan Pemerintah
ROW Right of Way
RP Recommended Practice
SDV Shut Down Valve
SMTS Specified Minimum Tensile Strength
SMYS Specified Minimum Yield Strength
SNI Standar Nasional Indonesia

4. APPLICABLE CODES AND SPECIFICATIONS


The current edition, at the date of contract award, of the following codes, standards, and
specifications form an integral part of this specification.

4.1. Indonesian Act and Regulations

1. 300.K/38/M.PE/1997 Decree of the Minister of Mining and Energy Regarding


The Work Safety of Oil and Natural Gas Distribution
Pipeline.

2. 84.K/38/DJM/1998 Inspection Guidelines for Safety On Facilities,


Equipment and Technology Used In Oil and Gas And
Geothermal Activities.

4.2. Project Documents


PTGGP-00-PRO-DB-001 Project Design Basis
PTGGP-00-PL-CAL-001 Pipeline Wall Thickness Calculation
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 9 of 13
Stability Calculation

4.3. Codes and Standards


API Spec. 5L Specification of Linepipe
ASME B31.8 Gas Transmission and Distribution Piping System

4.4. Order of Precedence

Wherever conflicts or omissions between codes, specifications, and contract occur,


the most onerous condition shall apply. CONTRACTOR is responsible for reviewing
the list below and informing the COMPANY of any omissions. All conflicts shall be
formally brought to the attention of the COMPANY.

All Work shall be performed in accordance with the following order of precedence of
the following codes and standards:

1. Indonesian Act and Regulations

2. Project Scope of Work and Design Basis Memorandum

3. Project Specification and Datasheet

4. Internationally Recognized Codes and Standards

5. Good Engineering Practice

It is the CONTRACTOR responsibility to present the issues and/or differences


among the codes and standards above to the COMPANY for resolution. The more
stringent requirement shall prevail unless otherwise approved by the COMPANY.

Any latest amendments / new additions to the standard and regulation shall be
incorporated.

If the CONTRACTOR proposes to employ an alternative standard this shall be


approved by the COMPANY before Work can proceed.

5. DESIGN DATA PARAMETER


5.1. Pipeline Design Life
The design life for the pipeline system is 20 years.
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 10 of 13
Stability Calculation

5.2. Design Pressure and Temperature


Design pressure and design temperature are summarized in table below.
Table 5.1. Functional Parameter
Parameter Unit Values
Design Pressure psig 1120
o
Design Temperature F 200
Service - Gas

5.3. Onshore Pipeline Properties


The following tables are present pipeline mechanical properties.
Table 5.2. Pipeline Properties
Parameter Unit Values
Outside Diameter in 20
Material - Carbon Steel, API 5L Grade X65
Seam - SAWL, HFERW
Specified Minimum Yield Strength psig 65000
Specified Minimum Tensile Strength psig 77000
Steel Density kg/m3 7850
5
Young Modulus MPa 2.07 x 10
-5
Thermal Expansion Coefficient 1/°C 1.1x10
Poisson Ratio - 0.3
Corrosion Allowance mm 3

5.4. Pipeline Coating System


Pipeline external coating system summarized in Table below:
Table 5.3. Pipeline Coating System
Parameter Unit Values
3LPE Thickness mm / in 3 / 0.118
3 3
3LPE Density kg/m / lb/ft 900 / 56

5.5. Longitudinal Weld Joint Factor


The weld joint factor for HFERW pipe is 1.0, refer to ASME B 31.8 table 841.115A.

6. METHODOLOGY
6.1. Minimum SG
A pipeline located in submerged or swampy areas shall have a specific gravity
(SG) that is higher than that of the surrounding water or fluidic soil (mud). The
submerged pipe SG is calculated by the following equation.
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 11 of 13
Stability Calculation

𝑊𝑝
𝑆𝐺 =
𝐹𝑠

where:

SG = submerged pipe specific gravity

Wp = total weight pipeline in air including coating (N/m)

Fb = buoyancy (N/m)

A minimum SG of 1.1 is adopted for the onshore pipeline section.

6.2. Load Case


Load cases that will be analyzed in this calculation are summarized in table below.

Table 6.1. Load Case Description


Content Concrete Coating Buoyant Media
Load
Condition Density Density Density
Case 3 3 3
(kg/m ) (kg/m ) (kg/m )
1 Installation 0 3043.5 1000
2 Operation 29.17 3043.5 1000

6.3. Assumptions
The assumptions made during calculation are:
1. Pipeline sinking settlement is considered unlikely.
2. Field joint coating for corrosion coating is to be the same as the mill coating itself.
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 12 of 13
Stability Calculation

7. RESULT, ANALYSIS, AND RECOMMENDATION


7.1. Result
Table 7.1. Calculation Result
Concrete Concrete Recommended
Buoyant
Load OD WT Coating Thickness Concrete
Condition Density
Case Density Requirement Thickness
3 3
(in) (mm) (kg/m ) (kg/m ) (mm) (mm)
1 20 15.09 3043.5 Empty 1000 10.55
40
2 20 15.09 3043.5 Operational 1000 8.82

7.2. Analysis and Recommendation


The pipeline buoyancy and stability calculation using MathCAD inhouse software for
empty/installation and operating cases for Pertagas Grissik-Pusri Project has been
performed.
The minimum required concrete thickness for 20” onshore gas pipeline from Grissik to
Pusri has been analyzed for possibility of floatation in submerged areas.
From the table above, whether the pipe is in installation condition (empty) or in operation
condition (gas filled), it requires concrete weight coating to overcome buoyancy and keep
the pipeline sinking. The selected concrete thickness is 40mm to satisfy all condition and
common concrete manufacturing practice.
The majority of the area that potentially need concrete coating area are swampy area
and rice paddy field where these two area tend to be floody when rain is pouring down.
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI

JUDUL NOMOR DOKUMEN REV PAGE

Pipeline Buoyancy and


PTGGP-00-PL-CAL-004 0 13 of 13
Stability Calculation

ATTACHMENT

Calculation Result
CLIENT : PT Pertagas BY: BYN

PROJECT : FEED Pembangunan Pipa Gas Grissik CHK: GAM

DOC. TITLE : PIPELINE BUOYANCY AND STABILITY CALCULATION REV: 0

DOC. NO. : PTGGP-00-PL-CAL-004


______________________________________________________________________________________________
CASE : 1 to 2

i := 0 .. 1

1.0 Pipeline Parameters

Pipe OD OD := 20in Outer jacket layer thickness tout := 0mm


(PE)
Pipe wall thickness twall := 15.88mm
−3
Outer jacket layer density ρout := 800⋅ kg⋅ m
−3
Steel density ρst := 7850⋅ kg⋅ m
Concrete coating thickness tcon := 0mm
Anti-Corrosion coating thickness tcor := 3 ⋅ mm (initial)
(3LPE)
−3 Concrete coating density ρcon :=
Anti-Corrosion coating density ρcor := 900⋅ kg⋅ m i

Insulation layer thickness tins := 0mm −3


3043.5kg⋅ m
(PUF)
−3
−3 3043.5kg⋅ m
Insulation layer density ρins := 960⋅ kg⋅ m

ρg :=
i Length per Joint Lp := 12.2m
Pipe content density
(CASE 1 Empty) −3
0kg⋅ m Concrete Cut-back Lcb := 300mm
Pipe content density −3
29.17kg⋅ m
(CASE 2 Gas)

Specific Gravity Required SG := 1.1

2.0 Environment Parameters


ρf :=
Bouyant media condition i

−3
1000kg⋅ m
−3
1000kg⋅ m

3.0 Calculation

Total Outer Diameter ( ) (


ODtotal tcon := OD + 2 ⋅ tcor + tins + tout + tcon ) ( )
ODtotal tcon = 0.514 m

Internal Diameter ID := OD − 2 ⋅ twall ID = 0.476 m


3 N
Steel weight ( ) ( )
wst := π OD − twall ⋅ twall⋅ ρst⋅ g wst = 1.89 × 10 ⋅
m
N
Anti-corrosion coating weight wcor := π⋅ tcor⋅ ( OD + tcor) ⋅ ( ρcor ⋅ g) wcor = 42.506⋅
m
N
Insulation layer weight ( )( )
wins := π⋅ tins⋅ OD + 2.tcor + tins ⋅ ρins⋅ g wins = 0 ⋅
m
Outer jacket weight wout := π⋅ tout⋅ ( OD + 2.tcor + 2⋅ tins + tout) ⋅ ( ρout⋅ g)

1 of 2
Lp − 2 ⋅ Lcb
wcon tcon , i := ⋅ ODtotal tcon ... 
π 2
Concrete coating weight ( 4
) ( )  ⋅  ρconi⋅ g ⋅ Lp
+ − OD + 2 ⋅ t + t 2 
  cor ins  ( ) 

Total Pipe Weight ( )


wp tcon , i := wst + wcor + wins + wcon tcon , i ( ) (
wp tcon , i = )
N
1.933·103 ⋅
m
1.933·103

π 2
Weight of content wg := ⋅ ID ⋅ ρg ⋅ g wg =
i 4 i i
N
0 ⋅
m
50.956

 π ⋅ ρ ⋅ g⋅  OD 2
Buoyancy (
FL tcon , i := )  4 f i ( total( tcon) )  (
FL tcon , i = )
  N
2.035·103 ⋅
m
2.035·103

Download weight total ( )


wdown tcon , i := wp tcon , i + wg
i
( ) wdown tcon , i =( )
N
1.933·103 ⋅
m
1.983·103

Required weight ( ) (
wreq tcon , i := SG⋅ FL tcon , i − wdown tcon , i ) ( ) (
wreq tcon , i = )
N
305.852 ⋅
m
254.895

−1
Weight required check wchk :=
i
(
"YES" if wreq tcon , i > 0N⋅ m )
"NO" otherwise
Given

(
wdown tcon , i )
SG = tcn( i) := Find tcon ( )
(
FL tcon , i )
−1
tc :=
i
(
"NO" if wreq tcon , i < 0N⋅ m )
tcn( i) otherwise
Total Download Weight Total Buoyancy with
with Concrete Concrete (Uplift)
(
wp tcn( i) , i + wg )
SGfinal( i) :=
i ( )
wp tcn( i) , i + wg =
i (
FL tcn( i) , i = )
(
FL tcn( i) , i ) N N
2.426·103 ⋅ 2.205·103 ⋅
m m
2.395·103 2.177·103
4.0 Result
Additional weight required: Concrete coating thickness required: SG using concrete thickness :
SGfinal( i) =
 "YES"   10.55  1.1
wchk =   tc =   ⋅ mm
 "YES"   8.82  1.1

2 of 2

Potrebbero piacerti anche