Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1. Rated utility source voltage is available to the transfer switch terminal lugs N1, N2,
N3 (N4 if so equipped), through the closed main contacts to the load terminals T1,
approximately a 10 to 1 ratio. From the secondary side of TR3, wire 264 goes to the
In Phase Monitor as a reference for an in phase transfer when going from generator
back to utility.
2. Rated utility source voltage is available to the transfer switch terminals A1 (wire 126
from position 7 on the Transfer Relay (TR), which is the other side of the normally
closed contact wire 125 on position 1 of TR. Wire 125 is on the Maintenance
position) and A2 (wire N2). However, the limit switches (LS1 and LS2) are open at
this point and are closed to B1 (wire 107) and B2 (wire E2), which are waiting for the
3. From the load terminals T1 and T2, rated utility source voltage is delivered to the
primary winding of the load transformer (TR2). This voltage is then stepped down to
exerciser via wires 185 and 0. Wires 185 and 0 are used to operate the timing circuit
(clock) of the exerciser that runs whenever programmed to do so. A nine-volt battery
is used to power the 7-day exerciser when these terminals do not have power (loss of
Interface Board (USI). Transformers then step down this voltage to approximately
18 to 50 VAC, depending on where the voltage is read. This voltage is sent to the
Utility Voltage Sensing Printed Circuit Board (UVS) via wires 224, 225, 226 and
227.
5. If voltage is present on wires 224, 225, 226 and 227, the system takes no action,
1. The Voltage Dropout Sensor constantly monitors the reduced utility voltage. If this
voltage drops below the set value, the Line Interrupt Delay Timer starts timing. If
utility voltage DOES NOT return before this timer times out, the UVS closes the two
wire start (wires 177 and 178). At the same time, wires 199 and 202 open, delivering
used to inform the IMPCB that utility is below the preset value.
2. When the two wire start circuit is closed, that signal is sent to the generator’s panel
(wires 178 and 183) to initiate an automatic start. The generator then starts to crank
IF the generator is set to AUTO and there is no break in 178 and 183 (SW1 is set to
the manual position, the lower harness in the generator is disconnected, 178 or 183 is
3. Once the generator starts, rated standby voltage is delivered to transfer switch
terminal lugs E1, E2, E3 (E4 if so equipped). Rated standby voltage is also sent to
TR1, which then is then stepped down to an approximate 10 to 1 ratio. This reduced
voltage is sent to the Standby Operating lamp (wire 191), which illuminates the light
and to the IMPCB (wires 191 and 266), which turns on the IMPCB.
4. The Engine Minimum Run starts to time, the Engine Warm Up timer begins, if not
bypassed, and both Standby Voltage and Standby Frequency setting percentages are
looked at.
5. A 12 VDC signal is delivered to wire 194 on the TR Coil. Once the timers are met
(see above), the IMPCB will then pull wire 23 low (to ground), powering the TR
coil.
6. If the Time Delay Neutral is selected, there is a Time Delay (TD) Relay that also
uses wire 194. Wire 193 acts like wire 23 in the sense that when the transfer
mechanism goes to neutral, it will activate the TD and actuate the normally open
contacts to the closed position and bypass LS 3 and go to a resistor via wires 187 and
189. The main solenoid coil (C) will be electrically held for the duration that is
selected on the IMPCB. Once this timer expires, wire 193 goes high again (about 10
7. Once the TR coil is energized from wire 23 going low, voltage from wire 108 (9 on
TR) can now go through via wire 107 (6 on TR) to B1 on the transfer mechanism.
E2 has a direct path to B2 on the transfer mechanism. This voltage can now go
through the limit switches and energize the coil to actuate the mechanism for transfer
A2, so that when utility is restored, utility can power the coil to go back to the normal
load.
9. The utility auxiliary contact moves to the normally open side and powers the
Utility Return
1. When Utility returns, voltage is on N1, N2, N3 (N4 if so equipped) and delivered to
the UVS via wires 224, 225, 226 and 227. If this reduced voltage is above the
Voltage Pick Up Sensor percentage, wire 199 is then closed by wire 202, which is the
signal to the IMPCB that utility has returned. The IMPCB then takes over for the
two-wire start and the Return to Utility Timer starts. Once this timer times out, the
2. When all timers have been met, the IMPCB then opens wire 23, de-energizing the
TR coil, allowing utility voltage to actuate the coil via wire 125 (1 on TR) to wire
126 (7 on TR) on A1 and N2 on A2. This allows voltage to go through the limit
switches to energize C (LS 3 opens in the neutral position) and switch the main
contacts back to utility powering the load. Once the coil de-energizes, the limit
switches close to B1 and B2 to wait for the next action (loss of utility).
3. The auxiliary contact on the utility side then goes back to its normally closed
position, which de-energizes the Emergency light and illuminates the Utility light via
wire 148.
4. The Engine Cool down timer is active now for the duration that has been selected.
Once this timer times out, 178 opens from ground and shuts down the generator.
NOTES:
• When the unit is exercising (177 is closed to ground via 178), wire 198 on the 7-Day
Exerciser opens from 202 and delivers 10 to 12 VDC to the IMPCB. This tells the
• Placing the Operating Mode switch in the Normal Test mode will run the system as
if a Utility loss has occurred, even though Utility is available. This test goes through
the normal timers and runs for that duration of time. The IMPCB knows it is in a
• If a Fast Test is selected, the switch must be held down, as this part of the switch is
spring loaded. This will start the generator and transfer to standby within five
seconds, bypassing all timers. Once the switch is released, the unit will shut down
after the transfer back to Utility has occurred. The IMPCB knows it is in a Fast Test
1. Rated utility source voltage is available to the transfer switch terminal lugs N1, N2,
N3 (N4 if so equipped), through the closed main contacts to the load terminals T1,
approximately a 10 to 1 ratio. From the secondary side of TR3, wire 264 goes to the
In Phase Monitor as a reference for an in phase transfer when going from generator
back to utility.
2. Rated utility source voltage is available to the transfer switch terminals A1 (wire 126
from position 7 on the Transfer Relay (TR), which is the other side of the normally
closed contact wire 125 on position 1 of TR. Wire 125 is on the Maintenance
position) and A2 (wire N2). However, the limit switches (M1 and M2) are open at
this point and are closed to B1 (wire 107) and B2 (wire E2), which are waiting for the
3. From the load terminals T1 and T2, rated utility source voltage is delivered to the
primary winding of the load transformer (TR2). This voltage is then stepped down to
exerciser via wires 185 and 0. Wires 185 and 0 are used to operate the timing circuit
(clock) of the exerciser that runs whenever programmed to do so. A nine-volt battery
is used to power the 7-day exerciser when these terminals do not have power (loss of
Interface Board (USI). Transformers then step down this voltage to approximately 18
to 50 VAC, depending on where the voltage is read. This voltage is sent to the Utility
Voltage Sensing Printed Circuit Board (UVS) via wires 224, 225, 226 and 227.
5. If voltage is present on wires 224, 225, 226 and 227, the system takes no action,
1. The Voltage Dropout Sensor constantly monitors the reduced utility voltage. If this
voltage drops below the set value, the Line Interrupt Delay Timer starts timing. If
utility voltage DOES NOT return before this timer times out, the UVS closes the two
wire start (wires 177 and 178). At the same time, wires 199 and 202 open, delivering
10 to 12 VDC to the In Phase Monitor Printed Circuit Board (IMPCB), which is used
2. When the two wire start circuit is closed, that signal is sent to the generator’s panel
(wires 178 and 183) to initiate an automatic start. The generator then starts to crank
IF the generator is set to AUTO and there is no break in 178 and 183 (SW1 is set to
the manual position, the lower harness in the generator is disconnected, 178 or 183 is
3. Once the generator starts, rated standby voltage is delivered to transfer switch
terminal lugs E1, E2, E3 (E4 if so equipped). Rated standby voltage is also sent to
TR1, which then is then stepped down to an approximate 10 to 1 ratio. This reduced
voltage is sent to the “Standby Operating” lamp (wire 191), which illuminates the
light and to the IMPCB (wires 191 and 266), which turns on the IMPCB.
4. The “Engine Minimum Run” starts to time, the “Engine Warm Up” timer begins, if
not bypassed and both “Standby Voltage” and “Standby Frequency” setting
5. A 12 VDC signal is delivered to wire 194 on the TR Coil. Once the timers are met
(see above), the IMPCB will then pull wire 23 low (to ground), powering the TR coil.
6. If the Time Delay Neutral is selected, there is a Time Delay (TD) Relay that also uses
wire 194. Wire 193 acts like wire 23 in the sense that when the transfer mechanism
goes to neutral, it will activate the TD and actuates the normally open contacts to the
closed position and bypasses TD1 and TD2 and go to a resistor via wires 187 and
189. The main solenoid coil (C) will be electrically held for the duration that is
selected on the IMPCB. Once this timer expires, wire 193 goes high again (about 10
7. Once the TR coil is energized from wire 23 going low, voltage from wire 108 (9 on
TR) can now go through via wire 107 (6 on TR) to B1 on the transfer mechanism. E2
has a direct path to B2 on the transfer mechanism. This voltage can now go through
the limit switches and energize the coil to actuate the mechanism for transfer to
Standby power. When the mechanism is in the neutral position, TD1 and TD2 open
8. Once the Load is being powered by Standby, M1 and M2 are now closed to A1 and
A2, so that when Utility is restored, Utility can power the coil to go back to the
Normal load.
9. The utility auxiliary contact moves to the normally open side and powers the
1. When Utility returns, voltage is on N1, N2, N3 (N4 if so equipped) and delivered to
the UVS via wires 224, 225, 226 and 227. If this reduced voltage is above the
Voltage Pick Up Sensor percentage, wire 199 is then closed by wire 202, which is the
signal to the IMPCB that utility has returned. The IMPCB then takes over for the
two-wire start and the Return to Utility Timer starts. Once this timer times out, the
2. When all timers have been met, the IMPCB then opens wire 23, de-energizing the TR
coil, allowing utility voltage to actuate the coil via wire 125 (1 on TR) to wire 126 (7
on TR) on A1 and N2 on A2. This allows voltage to go through the limit switches to
energize the coil (TD1 and TD2 open in the neutral position) and switch the main
contacts back to utility powering the load. Once the coil de-energizes, the limit
switches close to B1 and B2 to wait for the next action (loss of utility).
3. The auxiliary contact on the utility side then goes back to its normally closed
position, which de-energizes the “Emergency” light and illuminates the “Utility” light
4. The Engine Cool down timer is active now for the duration that has been selected.
Once this timer times out, 178 opens from ground and shuts down the generator.
NOTES:
• When the unit is exercising (177 is closed to ground via 178), wire 198 on the 7-Day
Exerciser opens from 202 and delivers 10 to 12 VDC to the IMPCB. This tells the
a Utility loss has occurred, even though Utility is available. This test goes through
the normal timers and runs for that duration of time. The IMPCB knows it is in a
• If a Fast Test is selected, the switch must be held down, as this part of the switch is
spring loaded. This will start the generator and transfer to standby within five
seconds, bypassing all timers. Once the switch is released, the unit will shut down
after the transfer back to Utility has occurred. The IMPCB knows it is in a Fast Test
UTILITY PRESENT
1. Rated utility source voltage is available to the transfer switch terminal lugs N1, N2,
N3 (N4 if so equipped), through the closed main contacts to the load terminals T1,
approximately a 10 to 1 ratio. From the secondary side of TR3, wire 264 goes to the
In Phase Monitor as a reference for an in phase transfer when going from generator
back to utility.
2. Rated utility source voltage is available to the transfer switch terminals A1 (wires 233
from position 3 on the Time Delay Neutral Relay (TD) and 126 from position 7 on
the Transfer Relay (TR) to position 9 on TD. Wire 125 (position 1 on TR) is
SW1) and A2 (wire N2), but cannot get to the Closing Coil (C) due to AX being
open. Rated utility source voltage is also present on BT1 (wire 126) and BT2 (wire
N2), but cannot get to the Trip Coil (TC) due to BTS1 and BTS2 being open.
3. From the load terminals T1 and T2, rated utility source voltage is delivered to the
primary winding of the load transformer (TR2). This voltage is then stepped down to
via wires 185 and 0. Wires 185 and 0 are used to operate the timing circuit (clock) of
the exerciser that runs whenever programmed to do so. A nine-volt battery is used to
power the 7-day exerciser when these terminals do not have power (loss of utility or
Interface Board (USI). Transformers then step down this voltage to approximately 18
to 50 VAC, depending on where the voltage is read. This reduced voltage is then sent
to the Utility Voltage Sensing Printed Circuit Board (UVS), via wires 224, 225, 226
and 227.
5. If voltage is present on wires 224, 225, 226 and 227, the system takes no action,
1. The Voltage Dropout Sensor constantly monitors the reduced utility voltage. If this
voltage drops below the set value, the Line Interrupt Delay Timer starts timing. If
utility voltage DOES NOT return before this timer times out, the UVS closes the two
wire start (wires 177 and 178). At the same time, wires 199 and 202 open, delivering
10 to 12 VDC to the In Phase Monitor Printed Circuit Board (IMPCB), which is used
2. When the two wire start circuit is closed, that signal is sent to the generator’s panel
(wires 178 and 183) to initiate an automatic start. The generator then starts to crank
IF the generator is set to AUTO and there is no break in 178 and 183 (if SW1 is set to
the manual position, the lower harness in the generator is disconnected, 178 or 183 is
3. Once the generator starts, rated standby voltage is delivered to the transfer switch
terminal lugs E1, E2, E3 (E4 if so equipped). Rated standby voltage is also sent to
the IMPCB (wires 191 and 266), which turns on the IMPCB.
4. The “Engine Minimum Run” starts to time, the “Engine Warm Up” timer begins, if
not bypassed and both “Standby Voltage” and “Standby Frequency” setting
5. A 12 VDC signal is delivered to wire 194 on the TR coil. Once the timers are met
(see above), the IMPCB will pull wire 23 low (to ground), powering the TR coil.
6. If the Time Delay Neutral is selected, the TD relay also uses wire 194 for 12 VDC.
Wire 193 acts like wire 23 in the sense that when the transfer mechanism goes to
neutral, it will activate the TD and actuate the normally closed contacts to the open
position. This in turn, doesn’t allow standby voltage to the Select Coil (SC) for a
predetermined amount of time, adjustable on the IMPCB. Once the timer expires,
wire 193 then goes to its normal state, allowing standby voltage to move to the SC.
7. Once the TR coil is energized from wire 23 going low, standby voltage from wire 108
(9 on TR) can now go through via wire 107 (6 on TR) to AT1 on the transfer
mechanism. E2 has a direct path to AT2 on the transfer mechanism. Limit switches
ATS1 and ATS2 are in the closed position and allow standby voltage to energize the
8. With the transfer mechanism in the neutral position, limit switches AX and BX close.
With LS AX and BX closed, standby voltage from 234 (1 on TD) can get through to
B1 on the transfer mechanism to the SC. E2 has a direct path through B2 on the
transfer mechanism. These two voltages energize the SC. When this is done, both
LS limit switches are pulled to the opposite position, allowing standby voltage to the
C. Once the SC de-energizes, the LS limit switches return to their normal position.
9. With standby voltage going to C, this electrically actuates the mechanism to the
Emergency Position. Limit switches AX and BX open, both LS’s return to their
normal position, ATS1 and ATS2 open and BTS1 and BTS2 close. Standby voltage
10. The utility auxiliary contact moves to the normally open side and powers the
Utility Return
1. When utility returns, voltage is on N1, N2, N3 (N4, if so equipped) and delivered to
the UVS via wires 224, 225, 226 and 227. If this reduced voltage is above the
Voltage Pick Up Sensor percentage, wire 199 is then closed by wire 202, which
signals to the IMPCB that utility has returned. The IMPCB then takes over for the
two-wire start and the Return to Utility Timer starts. Once this timer times out, the
2. When all timers have been met, the IMPCB then opens wire 23, de-energizing the TR
coil, allowing utility voltage to actuate the TC via wire 125 (1 on TR) to wire 126 (7
on TR) on BT1 and N2 on BT2. When the TC trips the mechanism to the neutral
position, limit switches AX and BX close, BTS1 and BTS2 open and ATS1 and
ATS2 close, which wait for the loss of utility. Once that happens, utility source
voltage can get though via wire 125 (7 on TR) to wire 233 (through 9 to 3 on TR) to
A1 and N2 on A2. This voltage then gets through on the LS limit switches to C. This
electrically actuates the transfer switch mechanism to the utility side contacts. When
3. The auxiliary contact on the utility side then goes back to its normally closed
position, which de-energizes the “Emergency” light and illuminates the “Utility” light
4. The Engine Cool Down is active now for the duration that has been selected. Once
this timer times out, 178 opens from ground and shuts down the generator.
NOTES:
• When the unit is exercising (177 is closed to ground via 178), wire 198 on the 7-Day
Exerciser opens from 202 and delivers 10 to 12 VDC to the IMPCB. This tells the
• Placing the Operating Mode switch in the Normal Test mode will run the system as if
a Utility loss has occurred, even though Utility is available. This test goes through
the normal timers and runs for that duration of time. The IMPCB knows it is in a
• If a Fast Test is selected, the switch must be held down, as this part of the switch is
spring loaded. This will start the generator and transfer to standby within five
seconds, bypassing all timers. Once the switch is released, the unit will shut down
after the transfer back to Utility has occurred. The IMPCB knows it is in a Fast Test