Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Doc. No :
DES-0008
Revision : 0
© 2019 PC KETAPANG II LTD (PCK2L), All rights reserved. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the
permission of the copyright OWNER.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
REVISION LIST
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
Document/
No. Owner Comments Contractor Response Remarks
Page Ref.
Revise Figure 6-1 BTJT-B
1 12 Comment is incorporated. -
Facility.
Revise typo word in Section
2 15 Comment is incorporated. -
6.6 Administrative Controls.
Complete HOLD data in Table
3 16 7-1 BTJT-B WHP PSV Comment is incorporated. -
Summary Data.
BDV-6061/6062 are updated to
Add BDV-6061/6062 at GTG
4 30 BDV-7510/7520 based on P&ID -
A/B.
Rev. B1.
Check valve at Liquid Transfer
Check valve at Liquid Transfer
Pump is added in Table 7-4
5 32 Pump discharge, include class -
BTJT-B WHP Class 1 Check
1 or not?
Valves Summary Data.
BDV-6061/6062 are updated to
Add BDV-6061/6062 at GTG
6 37 BDV-7510/7520 based on P&ID -
A/B.
Rev. B1.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
TABLE OF CONTENT
1. BACKGROUND ..............................................................................................6
2. PURPOSE......................................................................................................7
3. REFERENCE ..................................................................................................7
4. DOCUMENTS ORDER OF PRECEDENCE ..........................................................8
5. TERMS AND ABBREVIATIONS .......................................................................9
5.1 TERMS ..................................................................................................9
5.2 ABBREVIATIONS ..................................................................................9
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
1. BACKGROUND
The Bukit Tua South and Southern of Bukit Tua Main are two fields to be developed
as part of the Ketapang block PSC commitment. Hence, a firm development plan has
now been undertaken by PC Ketapang II Ltd (PCK2L) to develop the field before the
PSC expires in 2028.
The field contains hydrocarbon reserve of oil and significant associated gas located
in Ketapang block, East Java basin. The field lies in the East Java Sea 100 km from
Surabaya at the North of Madura Island, in a water depth of 60 m. The nearest PC
Ketapang II Ltd operated infrastructures are BTJT-A Wellhead Platform and BT-FPSO
located at 3.6 km to the North West of this new field.
The existing facilities were developed as part of Phase 1 development with five (5)
single completion wells, two (2) future wells, one (1) future pilot water flooding well
and one (1) spare. Subsequently, two (2) additional infill wells were drilled at the
existing BTJT-A platform as part of Bukit Tua Field Development Phase 2A and
currently PC Ketapang II Ltd intends to drill four (4) additional wells and brownfield
modification at the existing BTJT-A platform as part of Bukit Tua Field Development
Phase 3. At the FPSO, gas is compressed, dehydrated and hydrocarbon dew pointed
prior to be exported to BTJT-A as gas lift and fuel gas. Then, the excess gas will be
exported to ORF. The liquid at the FPSO is separated with the oil stream is stabilized
and stored within hull storage tanks and the water is treated before disposal
overboard.
JAVA SEA
Pangkah PSC
Ketapang PSC
JS 2-1 JS 3-1
Ujung Pangkah
Bukit Tua-3A Garit-1
Field Bukit Tua-2
Bukit Tua-4
Jenggolo-1
JS8-1
Perawan-1
JS44A-1
JS19-1
MADURA
EAST
JAVA 20 km
The new facility Bukit Tua Phase 2B (BTJT-B) will be developed as a satellite Wellhead
Platform to the existing facilities. The BTJT-B platform will be unmanned with a single
Full Well Stream (FWS) of indicated 16-inch, 3.6 km pipeline tied back to the BTJT-
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
A platform prior to be transferred to the BT-FPSO processing facility via the existing
pipeline. A 6-inch, 3.6 km pipeline will supply gas lift as selected method used to
artificially lift fluid from well at the new production facility.
The BTJT-B platform will be supported by a vertical four-legged substructure with the
well conductors are protected with the internal perimeter of the jackets. The
Wellhead Platform will accommodate up to nine (9) well slots with five (5) producing
wells and four (4) spares.
The production facility will be designed to handle plateau rate of 14,700 Stb/d liquid
and 40 MMSCFD gas and assuming BTJT-A arrival pressure at 160 psia.
Wellhead pressure will decrease rapidly during the first two years of production.
Subsequently, pressure will be maintained at low pressure approximately 120 psia
up to the end of PSC contract in 2028.
PT. Meindo Elang Indah has been awarded the Engineering, Procurement,
Construction, Installation and Commissioning of BTJT-B Wellhead Platform, infield
pipelines and host tie-in modification for Bukit Tua Phase 2B development project,
PC Ketapang II Ltd PSC, East Java, Indonesia under contract no. 4850000373.
2. PURPOSE
The purpose of this document is to provide process description and safeguarding
philosophy to prevent failure and damage at Bukit Tua BTJT-B Platform.
3. REFERENCE
N/A
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
N/A
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
The following terms as used in this document, assume the meanings given
below:
COMPANY PC Ketapang II Ltd, as the Project developer and ultimate
owner of the facility/platform.
CONTRACTOR The party that carries out all or part of the detailed
engineering, procurement, construction, installation and
commissioning (EPCIC) contract of the project and the one
who places the order signs the contract as or on behalf of
the COMPANY. In this Project, PT. Meindo Elang Indah
(MEI).
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
The compressed gas and heated liquid will be combined into one stream and
routed to a 16” FWS pipeline and delivered to BTJT-A Wellhead Platform. The
production fluid from BTJT-B will be commingled with production fluid from
BTJT-A production manifold and routed to Production Separator (V-1020) at
BTJT-A. The separated gas from Production Separator (V-1020) will be
delivered to FPSO via wet gas pipeline, while the separated liquid will be
delivered to FPSO via liquid pipeline.
During early production (November 2021 to April 2023), the production fluid
from wells will be directly routed to BTJT-A without gas compression and liquid
transfer pump system through bypass line due to high availability of FTHP from
the wells. However, Liquid Heater (E-1330) is required to increase the well fluid
temperature before entering the Full Well Stream (FWS) pipeline. Therefore,
during early production, the Liquid Heater (E-1330) will be used as Full Well
Stream (FWS) heater.
The following Figure 6-1 shows the process schematic of Bukit Tua WHP B
(BTJT-B).
[Safeguarding Memorandum]
Doc. No : BTP2B-EPCIC-BTJTB-B-DES-0008
Revision : 0
To Vent Header
V-1030
LC
Test Manifold
LC E-2430/
H
2460
M
Production Manifold
PC
K-2420/
2450
M
V-1040 LC V-2410/
H 2440
Production Fluid
Gas Lift Manifold
to BTJT-A
Production Wellheads BTM L-1320
(Crude Oil + Gas) - Typ. 3
P-1340A/B
E-1330 TC TC
PC
E-6020
Export Gas
Production Wellheads BTS from BTJT-A
Gas Turbine
(Crude Oil + Gas) - Typ. 2 S-6060A/B R-2940
Generator Gas Sweeping
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
Pressure relief devices and other process safeguarding elements are designed
to accommodate two (2) operation modes at BTJT-B. The two (2) operation
modes at BTJT-B are classified based on production life which are early
production (November 2021 to April 2023) and late production. In early
production, the production fluid from wells will be directly routed to BTJT-A
without gas and liquid separation in Production Separator (V-1040), gas
compression and liquid transfer pump system through bypass line due to high
availability of FTHP from the wells. While in late production, the production fluid
from wells is directed to Production Separator (V-1040) to be separated as gas
and liquid stream prior to be compressed (gas) and pumped (liquid) to increase
the operating pressure and transferred to BTJT-A. As a result, the pressure
relief devices and other process safeguarding elements installed on Production
Separator (V-1040), gas compression and liquid transfer pump system will not
be operated in the early production. The BTJT-B production facility is designed
to handle fluid at the rate of 40 MMscfd and 14700 blpd (12500 bopd) and
assuming BTJT-A arrival pressure at 160 psia.
As per API 521, in evaluating relieving requirements due to any cause, any
automatic control valves that are not under consideration as causing a relieving
requirement and which would tend to relieve the system should be assumed to
remain in the position required for normal processing flow. In other words, no
credit should be taken for any favorable instrument response. However, in
designing pressure relief devices (PSV) at BTJT-B, the most conservative
approach is taken where no reduced relief flowrate considered through the
installed control valve.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
- Fire relief load can be relieved elsewhere in the system during normal
operation (when the equipment is lined up again).
- Procedures are in place for promptly draining and depressurizing equipment
that is isolated for maintenance. This credit is typically taken only for spared
equipment that are intended to be put into operation at a pre-determined
frequency (examples: filters, driers, etc).
Valve operation control applications are defined as controls that limit and clarify
the use of the valve in a pre-defined position: open or closed. Valve for
operation controls are valves with a chained and locked, or key/mechanical
locked, or a car-seal based system, instrumented interlock or 3-way valve.
[Safeguarding Memorandum]
Doc. No : BTP2B-EPCIC-BTJTB-B-DES-0008
Revision : 0
PROVISION OF EPCIC OF BTJT-B WELLHEAD PLATFORM, INFIELD PIPELINES AND HOST TIE IN MODIFICATION FOR BUKIT
Page : 16 of 49
TUA PHASE 2B DEVELOPMENT PROJECT
7. SAFEGUARDING ELEMENTS
7.1 Ultimate Safeguard – Summary of Relief Devices and Instrumented Protective Functions
Relief
Design Design
Device Set
Tag No. Service Location P&ID No. Pressure Relief Path Temperature
Pressure
(barg) (oC)
(barg)
Test Separator
PSV-1030 BTJT-B-B-PID-1511 35 35 Vent Header 86
(V-1030)
Production Separator
PSV-1040A/B BTJT-B-B-PID-1512 35 35 Vent Header 86
(V-1040)
Liquid Heater
PSV-1330A/B BTJT-B-B-PID-1513 35 35 Vent Header 100
(E-1330)
[Safeguarding Memorandum]
Doc. No : BTP2B-EPCIC-BTJTB-B-DES-0008
Revision : 0
PROVISION OF EPCIC OF BTJT-B WELLHEAD PLATFORM, INFIELD PIPELINES AND HOST TIE IN MODIFICATION FOR BUKIT
Page : 17 of 49
TUA PHASE 2B DEVELOPMENT PROJECT
Relief
Design Design
Device Set
Tag No. Service Location P&ID No. Pressure Relief Path Temperature
Pressure
(barg) (oC)
(barg)
Air Dryer
PSV-5412A/B/C/D BTJT-B-B-PID-1542 12 12 Atmosphere 70
(S-5412A/B/C/D)
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
b. PSV-1040A/B
PSV-1040A/B are installed to protect Production Separator (V-1040) from
overpressure during emergency fire scenario. Overpressure due to
blocked outlet is not considered during operation since the Production
Separator is protected by PZAHH-1041 that will initiate PSD and close
upstream SDV.
1. Electrical Failure
General - Production Separator heater will be tripped by SIS and
no relief takes place.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
c. PSV-2410/2440
PSV-2410/2440 are installed to protect Compressor Suction Scrubber
Train A/B (V-2410/2440) from overpressure during emergency fire
scenario.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Not applicable.
6. Other Failure
Not detected.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
7. Fire
Governing case.
8. Thermal Expansion
Not applicable.
d. PSV-2420/2450
PSV-2420/2450 are installed to protect Gas Compressor Train A/B (K-
2420/2450) from overpressure during blocked discharge scenario.
1. Electrical Failure
General – Gas Compressor will be tripped by SIS and no relief
takes place.
Single – Gas Compressor will be tripped by SIS and no relief takes
place.
Partial – Gas Compressor will be tripped by SIS and no relief takes
place.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Governing case.
6. Other Failure
Not detected.
7. Fire
Identified but not considered as governing case.
8. Thermal Expansion
Not applicable.
e. PSV-1330A/B
PSV-1330A/B are installed to protect Liquid Heater (E-1330) from
overpressure during emergency fire scenario.
1. Electrical Failure
General – Liquid Heater will be tripped by SIS and no relief takes
place.
Single – Liquid Heater will be tripped by SIS and no relief takes
place.
Partial – Liquid Heater will be tripped by SIS and no relief takes
place.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
f. PSV-1320
PSV-1320 is installed to protect FWS Pig Launcher (L-1320) from
overpressure during emergency fire scenario.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Not applicable.
6. Other Failure
Not detected.
7. Fire
Governing case.
8. Thermal Expansion
Not applicable.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
g. PSV-6020A/B
PSV-6020A/B are installed to protect Fuel Gas Heater (E-6020) from
overpressure during emergency fire scenario. Overpressure due to
blocked outlet is not considered during operation since the maximum
source pressure is lower than PSV set pressure.
1. Electrical Failure
General – Fuel Gas Heater will be tripped by SIS and no relief
takes place.
Single – Fuel Gas Heater will be tripped by SIS and no relief takes
place.
Partial – Fuel Gas Heater will be tripped by SIS and no relief takes
place.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by-PZALL 5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Not applicable.
6. Other Failure
Not detected.
7. Fire
Governing case.
8. Thermal Expansion
Not applicable.
h. PSV-6060A/B
PSV-6060A/B are installed to protect Fuel Gas Filter (S-6060A/B) from
overpressure due to inadvertent valve opening scenario. The
overpressure occurs if the PCV-6060A/B is stuck open during gas
operational flow from BTJT-A.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
i. PSV-2940
PSV-2940 is installed to protect Temporary BTJT-A to BTJT-B Gas Lift Pig
Receiver from overpressure during emergency fire scenario.
Overpressure due to blocked outlet is not considered during operation
since the maximum source pressure is lower than PSV set pressure.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Not applicable.
6. Other Failure
Not detected.
7. Fire
Governing case.
8. Thermal Expansion
Not applicable.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
j. PSV-6770
PSV-6770 is installed to protect Diesel Injection Pump (P-6770) from
overpressure due to blocked discharge scenario. The overpressure occurs
if any manual valve at the pump discharge is closed. The relief rate at
this condition based on the pump rated flow.
1. Electrical Failure
General – Diesel Injection Pump will be tripped by SIS and no
relief takes place.
Single – Diesel Injection Pump will be tripped by SIS and no relief
takes place.
Partial – Diesel Injection Pump will be tripped by SIS and no relief
takes place.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Governing case.
6. Other Failure
Not detected.
7. Fire
Identified but not considered as governing case.
8. Thermal Expansion
Not applicable.
k. PSV-5413
PSV-5413 is installed to protect Instrument Air Receiver (V-5410) from
overpressure during emergency fire scenario.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
l. PSV-5930
PSV-5930 is installed to protect downstream equipment of Nitrogen Rack
Skid (A-5930) from overpressure due to inadvertent valve opening
scenario. The overpressure occurs if the PCV-5931/5932 is stuck open
during operational flow of nitrogen for compressor back-up seal.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Governing case.
5. Blocked Outlet
Not applicable.
6. Other Failure
Not detected.
7. Fire
Not applicable.
8. Thermal Expansion
Not applicable.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
m. PSV-5410A/B
PSV-5410A/B are installed to protect downstream equipment of 1st Stage
Air Compressor (K-5410A/B-1) from overpressure due to blocked
discharge scenario.
1. Electrical Failure
General – Air Compressor will be tripped by SIS and no relief takes
place.
Single – Air Compressor will be tripped by SIS and no relief takes
place.
Partial – Air Compressor will be tripped by SIS and no relief takes
place.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Governing case.
6. Other Failure
Not detected.
7. Fire
Not applicable.
8. Thermal Expansion
Not applicable.
n. PSV-5411A/B
PSV-5411A/B are installed to protect downstream equipment of 2 nd Stage
Air Compressor (K-5410A/B-2) from overpressure due to blocked
discharge scenario.
1. Electrical Failure
General – Air Compressor will be tripped by SIS and no relief takes
place.
Single – Air Compressor will be tripped by SIS and no relief takes
place.
Partial – Air Compressor will be tripped by SIS and no relief takes
place.
2. Total Cooling Failure
Not applicable.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
o. PSV-5412A/B/C/D
PSV-5412A/B/C/D are installed to protect Air Dryer (S-5412A/B/C/D)
from overpressure due to emergency fire scenario.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Not applicable.
6. Other Failure
Not detected.
7. Fire
Governing case.
8. Thermal Expansion
Not applicable.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
p. PSV-6420A/B
PSV-6420A/B is installed to protect Closed Drain Transfer Pump (P-
6420A/B) from overpressure due to blocked discharge scenario. The
overpressure occurs if any manual valve at the pump discharge is closed.
The relief rate at this condition based on the pump rated flow.
1. Electrical Failure
General – Closed Drain Transfer Pump will be tripped by SIS and
no relief takes place.
Single – Closed Drain Transfer Pump will be tripped by SIS and no
relief takes place.
Partial – Closed Drain Transfer Pump will be tripped by SIS and
no relief takes place.
2. Total Cooling Failure
Not applicable.
3. Total Instrument Air Failure
Instrument air supply failure will initiate PSD by PZALL-5425A/B/C
detection and no relief takes place.
4. Inadvertent Valve Opening
Not applicable.
5. Blocked Outlet
Governing case.
6. Other Failure
Not detected.
7. Fire
Identified but not considered as governing case.
8. Thermal Expansion
Not applicable.
q. PSV-6070
PSV-6070 is installed to protect FWS pipeline from overpressure due to
control valve failure via gas sweeping line. The overpressure occurs if the
control valve at downstream of Fuel Gas Heater (E-6020) is inadvertently
full open.
1. Electrical Failure
General – Not applicable.
Single – Not applicable.
Partial – Not applicable.
2. Total Cooling Failure
Not applicable.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
Class 1
Check Valve Location P&ID No. Purpose
Tag Number
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
Regarding to section 7.2.2, the BTJT-B wellhead platform is equipped with mitigating
system that is blowdown valves installed at each isolatable section. This isolatable
section will be limited by shutdown valves (SDV) which will be air actuated or
motorized valve (MOV) which will be electric driven. The isolatable sections are
summarized in the following table.
200-P0401-9C607-E50 WV-0210
200-P0402-9C607-E50 WV-0220
200-P0403-9C607-E50 WV-0230
200-P0404-9C607-E50 WV-0240
200-P0405-9C607-E50 WV-0250
Production
200-P0406-9C607-E50 MOV-0421 BDV-0411 -
Manifold
100-P0407-9C607-E50 MOV-0422
100-P0408-9C607-E50 MOV-0423
100-P0409-9C607-E50 MOV-0424
100-P0410-9C607-E50 MOV-0425
400-P0429-9C607-E50 SDV-1040
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
Affected WV
(WV-
0210/0220/
200-P0413-9C607-E50 0230/0240/
200-P0414-9C607-E50 0250)
200-P0415-9C607-E50 MOV-0411 Only affected WV
Test Manifold BDV-0412
100-P0416-9C607-E50 will be closed.
MOV-0412
100-P0417-9C607-E50 MOV-0413
200-P0430-9C607-E50 MOV-0414
MOV-0415
SDV-1030
SDV-1030
SDV-1031
Test Separator V-1030 BDV-1030 -
SDV-1032
SDV-1033
SDV-1040
Production SDV-1041
V-1040 BDV-1040 -
Separator SDV-2410
SDV-2440
V-2410
Gas Compression SDV-2410
K-2420 BDV-2420 -
System Train A SDV-2420
E-2430
V-2440
Gas Compression SDV-2440
K-2450 BDV-2450 -
System Train B SDV-2450
E-2460
SDV-1040 will
SDV-1040 become a
SDV-1041 boundary limit
Liquid Transfer during early
Pump, Liquid SDV-2420 production whilst
P-1340A/B
Heater, Topside MOV-1311 BDV-1320 SDV-1041 will
Piping and Inlet of E-1330 become a
MOV-1312
FWS Pipeline boundary limit
MOV-1321 during operating of
SDV-1320 Production
Separator.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
E-6020
150-PG0613-9C318B-N
100-PG0626-9C607-N
100-PG0620-9C607-N
100-PG0625-9C607-N
SDV-2940
50-PG6004-9C607-H40
SDV-6060
Gas Lift Pig 50-PG0601-9C607-N
Receiver, Topside SDV-0621
50-PG0602-9C607-N
Piping, Fuel Gas SDV-0622 BDV-2940 -
Heater and Gas Lift 50-PG0603-9C607-N
SDV-0623
Manifold 50-PG0604-9C607-N
SDV-0624
50-PG0605-9C607-N SDV-0625
50-PG0606-9C607-N
50-PG0607-9C607-N
50-PG0608-9C607-N
50-PG0609-9C607-N
50-PG0610-9C607-N
S-6060A/B
50-FG6005-9C607-H40
80-FG6006-3C607-H40
Fuel Gas Filter and SDV-6060
50-FG6007-3C607-H40
Inlet to GTG SDV-7510 BDV-6060 -
Package 50-FG6008-3C607-H40
SDV-7520
50-FG6010-3S600-H40
50-FG6050-3S600-H40
50-FG6019-3S600-H40
S-7510 SDV-7510
Fuel Gas Line to 50-FG6050-3S600-H40 SDV Fuel Gas BDV-7510 -
GTG A Package 50-FG6022-3S600-N Line Inside
50-FG6020-3S600-N GTG A Package
S-7520 SDV-7520
Fuel Gas Line to 50-FG6019-3S600-H40 SDV Fuel Gas BDV-7520 -
GTG B Package 50-FG6023-3S600-N Line Inside
50-FG6021-3S600-N GTG B Package
[Safeguarding Memorandum]
Doc. No : BTP2B-EPCIC-BTJTB-B-DES-0008
Revision : 0
Backflow
Suction Discharge Differential What
Equipment Protection Safeguards
Description PID No. Pressure Pressure Pressure Mechanism
Tag Number Tag Employed/Rationale
(barg) (barg) (bar) Can Sustain
Number
High pressure
Closed Drain VX-13165 on inlet of Check valve at pump
B-B-PID- 0.2 – 0.3 13.6 – 13.9 13.4 – 13.6
P-6420A/B Transfer discharge
VX-13172 1524 Production
Pump
Separator
Backflow during
delivering liquid
to Closed Drain Check valve at pump
Open Drain VX-64146 B-B-PID- 0 1.1 1.1
P-6530 discharge
Pump 1526 Vessel (V-6420)
by Caisson
Pump (P-6540)
[Safeguarding Memorandum]
Doc. No : BTP2B-EPCIC-BTJTB-B-DES-0008
Revision : 0
Backflow
Suction Discharge Differential What
Equipment Protection Safeguards
Description PID No. Pressure Pressure Pressure Mechanism
Tag Number Tag Employed/Rationale
(barg) (barg) (bar) Can Sustain
Number
Backflow during
delivering liquid
to Closed Drain Check valve at pump
VX-64272 B-B-PID- (-)0.6 – (-)0.53 1.2 – 1.3 1.8 – 1.9
P-6540 Caisson Pump discharge
1526 Vessel (V-6420)
by Open Drain
Pump (P-6530)
Corrosion
Inhibitor
CITHP of Check valve at pump
Injection N/A B-B-PID- 0 103.4 103.4
P-6860A-E discharge
Pump 1534 wellheads
(Wellhead
Injection)
Corrosion
Inhibitor
High pressure Check valve at pump
Injection N/A B-B-PID- 0 11.3 11.3
P-6860F discharge
Pump (FWS 1534 on FWS pipeline
Pipeline
Injection)
Scale Inhibitor
Injection CITHP of Check valve at pump
N/A B-B-PID- 0 103.4 103.4
P-6870A~E Pump discharge
1535 wellheads
(Wellhead
Injection)
Scale Inhibitor
Injection High pressure Check valve at pump
N/A B-B-PID- 0 10.9 10.9
P-6870F Pump (FWS discharge
1535 on FWS pipeline
Pipeline
Injection)
[Safeguarding Memorandum]
Doc. No : BTP2B-EPCIC-BTJTB-B-DES-0008
Revision : 0
Backflow
Suction Discharge Differential What
Equipment Protection Safeguards
Description PID No. Pressure Pressure Pressure Mechanism
Tag Number Tag Employed/Rationale
(barg) (barg) (bar) Can Sustain
Number
Pour Point
CITHP of Check valve at pump
Depressant N/A B-B-PID- 0 103.5 103.5
P-6890A/B discharge
Injection 1536 wellheads
Pump
Backflow during
water filling to
Safety Service/Potable Check valve at pump
VX-52104 B-B-PID- 0 2.3 2.3
P-5220 Shower/Eye discharge
1538 /Wash Water
Washer Pump
Tote Tank (T-
5220)
Backflow during
Diesel diesel filling to Check valve at pump
VX-67125 B-B-PID- 0.7 1.7 1
P-6730 Transfer discharge
1539 Diesel Storage
Pump
Tank (T-6720)
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
This section specifically describes detail impact and consequences of the failure of
utility system at Bukit Tua BTJT-B platform. It also describes the management
strategy to mitigate any failure of utility system at Bukit Tua BTJT-B platform. The
detail impact and consequences of the failure are described as follow.
8.3.1 Electrical Power System
Electrical power generation at Bukit Tua BTJT-B platform shall be as 2x100%
configuration which consists of two (2) Gas Turbine Generator A/B (GT-
7510/7520) unit and one (1) Emergency Diesel Generator (GD-7730) unit.
The GTG unit is the primary electrical power generation to the platform. The
EDG shall be back-up power for the platform during emergency condition
and black start-up. No external power supply to be provided during SIPROD,
the GTG to be used as main power generation and EDG to be used for GTG
auxiliaries start up.
The GT-7510/7520 and GD-7730 will feed into a 400 VAC switchboard SB-
77100 for distribution to the various platforms loads. During normal
operation, GTG will be energized with 1x100% configuration to provide
power to the platform.
During synchronizing between GTG and EDG, the offload generator shall
regulate its voltage, frequency and phase angle to match with the onload
generator. Thus, EDG shall regulate itself to match with GTG’s voltage,
frequency and phase angle in order to synchronize with GTG, prior to load
transfer from GTG to EDG, and in the other hand GTG shall regulate itself to
match with EDG’s voltage, frequency and phase angle in order to synchronize
with EDG prior to load transfer from EDG to GTG.
8.3.2 Fuel Gas System
Gas lift and fuel gas source is taken from FPSO export line via BTJT-A
Wellhead Platform via 6” gas lift pipeline. Gas is received at BTJT-B and then
is routed to Fuel Gas Heater (E-6020). This heater is used to increase the
gas temperature.
The outlet of Fuel Gas Heater (E-6020) is then routed to Fuel Gas Filter (S-
6060A/B). The fuel gas pressure shall be reduced via a split range pressure
control valves approximately to 25 barg prior to be routed to 2x100% Fuel
Gas Filter (S-6060A/B). The fuel gas from Fuel Gas Filter (S-6060A/B) is then
routed to the Gas Turbine Generator A/B (GT-7510/7520) as fuel, to Gas
Compressor Train A/B (K-2420/2450) as primary seal gas and to vent header
as purge gas.
The Fuel Gas Filter (S-6060A/B) are equipped with Pressure Safety Valve
(PSV-6060A/B) to protect against overpressure due to control valve failure
when control valve is inadvertently open. The low temperature protection
(TALL) is also provided to protect the Gas Turbine Generator A/B (GT-
7510/7520) from any liquid condensation.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
The open drain system will be directed to an Open Drain Tank (T-6530) with
overflow to an Open Drain Caisson (T-6540) on the platform. Pneumatically
driven Open Drain Pump (P-6530) and Caisson Pump (P-6540) will transfer
any oil separated in the Open Drain Tank (T-6530) and the Open Drain
Caisson (T-6540) respectively to the Closed Drain Vessel (V-6420) or to the
bucket at sub cellar deck. All the operations regarding the open drain system
shall be performed manually.
Both Closed Drain Vessel (V-6420) and Open Drain Tank (T-6530) will be
equipped by electric heaters to ensure liquid is in a fluidic state for ease of
pumping during maintenance.
9. MISCELLANEOUS
This section describes the aspect of the process safeguarding procedure that are not
addressed in the previous section of the safeguarding memorandum to be understood by
the operation personnel.
9.1 Operation of Interlocking System for PSV
In normal operation, the interlocking system provided for the block valves of the
relief valve is arranged so that the inlet block valve of the open dummy on the spare
position is closed and the block valve on the outlet is open. This configuration is
used because the pressure rating of the outlet PSV is lower than the inlet PSV.
Changeover is accomplished in the following sequence:
1. The inlet block valve of the spare relief valve is opened and locked.
2. The inlet of the relief valve to be removed is closed.
3. The outlet of the relief valve to be removed is closed.
4. The removed relief valve is replaced by a spool piece (dummy).
5. The outlet block valve of the dummy is opened and locked.
9.2 Operation of Locking System for Pig Launcher/Pig Receiver
In pipeline pigging operation, locking device is provided for block valve at kicker
line, inlet pig launcher/pig receiver block valve, block valves at drain lines and block
valves at vent lines. At BTJT-B, drain and vent for pig launcher/pig receiver are
connected to a closed system (closed drain header and vent header). The basic
functionality of locking device for pig launcher/pig receiver is as follow:
All main and kicker line block valves to the launcher/receiver are locked closed
before the closure door is opened;
The vent and drain block valves are opened and closed again. This activity may
have to be repeated several times before the closure door is opened;
After launching or receiving pig, the launcher/receiver is guaranteed to be
vented and drained (when block valves at vent and drain line are opened, the
block valves at main and kicker line to the launcher/receiver are closed).
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
Specific operating procedures are required for some of the processes in this facility
whereby the system and equipment are not designed with engineering safeguards
but merely depend on the valve operation control to achieve the required level of
protection.
Generally, the Process Monitoring and Control System (PMCS) shall provide the
process control and monitoring for the facilities and be the primary operator
interface to the Safety Instrumented System (SIS) and other equipment package
control panels. The control hardware and marshalling cabinets shall be in the E&I
room, which shall be pressurized and air-conditioned.
PMCS has an overall availability of 99.99%. PMCS shall also be based on redundant
hot/standby controllers, redundant networks and simplex I/O structure. PMCS is
also utilized for regulatory set-point control, sequential control, on/off control, non-
safety related interlocks, process monitoring and alarm purposes. PMCS shall be
fully pre-programmed with extensive capabilities and options for control and data
acquisition including but not limited to:
Computational function.
Any combination of continuous/discrete/sequential and advanced (cascade)
control algorithms.
BTJT-B Wellhead Platform shall be remotely monitored and controlled from the
FPSO. Field instrumentation in general shall meet the requirement for
environmental, service conditions and area classification of the installed location.
9.4 Equipment Isolation, Start Up, and Shut Down Procedures
The Safety Instrumented System (SIS) shall include separate elements for
Emergency Shutdown (ESD), Process Shutdown (PSD) and Unit Shutdown (USD).
The Emergency Shutdown is further sub-divided to ESD-1 and ESD-2. The Fire and
Gas system shall also be configured onto the SIS system.
Emergency depressurizing (automatic blowdown) is considered the highest level of
shutdown for the platform and only be activated during confirmed fire detection,
SIPROD on the platform or via specific pushbutton or break glass initiators at the
operator’s discretion. During SIPROD mode, ESD-2 at normal mode shall be
upgraded to ESD-1 with automatic blowdown with provision of time delay. Operation
team shall determine the time delay prior to SIPROD. While PSD and some of USDs
at normal mode will be upgraded to ESD-2 during SIPROD.
During normal operation (no drilling activity) when confirmed fire is detected, ESD-
1 shall be triggered and automatic blowdown will be activated.
The Safety Instrumented System (SIS) shall be PLC based and shall carry out the
required process safety and protection functions on the remote platform. The
primary objective of the SIS is to safeguard personnel, equipment and prevent
pollution to the environment.
This system is expected to achieve the following functions:
Monitor the process shutdown due to fire and gas initiators.
Provide first-up indication of the shutdown causes.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
Perform shutdown logic as per the Process Cause and Effect Matrix.
Provide local shutdown (ESD/PSD/USD) and shutdown reset (ESD/PSD/USD)
facility.
Provide remote shutdown (ESD/PSD/USD).
Provide maintenance and start-up override.
Remote reset and start-up will be allowed upon remote initiation of USD and
PSD from the FPSO via BTJT-B with maximum of 3 hours in the plan shutdown
condition.
Provide remote shutdown from the FPSO.
Another objective of the SIS is to prevent uncontrollable sequence of events
following process upsets or abnormal plant conditions. In such events, the shutdown
system will initiate necessary shutdowns in a controlled manner to bring the facility
to a safe state.
9.5 Flame and Detonation Arrestors
Relief devices shall be located above the header into which they discharge. The
upstream piping shall slope down towards the protected equipment and the
downstream piping shall slope down towards to the vent header.
In the event of a general instrument air failure, control valves action shall be
established to prevent any unsafe conditions. The sequences applied for the
selection of the control valve sparing action are as follow:
Shut-off supply.
Open off-gas line to vent system.
Close all product lines.
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
[Safeguarding Memorandum]
BTP2B-EPCIC-BTJTB-B-
Doc. No :
DES-0008
Revision : 0
APPENDIX A
PROCESS SAFEGUARDING FLOW SCHEME (PSFS)
[Safeguarding Memorandum]
M EI N DO
ELANG INDAH
PETRONAS