2
Overview
4
O-Train Evolution
5
Project Benefits
6
Local Economic Benefits
7
Budget
Funds
Actual Unspent /
Stage 2 Authority Reserved /
Expenditures Uncommitted
Committed
Confederation Line Extensions
2,680,832,113 305,711,216 2,375,120,897 -
Design-Build-Finance Contract
Trillium Line Extension Design
810,159,585 34,990,026 636,647,568 -
Build Finance Maintain Contract
Deferred Equity
(Maintenance Term 138,521,991 -
Repayment)
RTG Stage 2 MOU
516,184,423 311,029,992 204,885,985 268,446
(includes 38 Alstom vehicles)
City Costs (includes project
planning, procurement, property
497,629,108 189,659,648 42,570,225 265,399,235
acquisitions, City retained
scope, and delivery oversight)
8
9
O-Train South Design Update
10
O-Train South Design Update
11
O-Train South Design Update
12
O-Train South Design Update
13
Construction
14
Walkley MSF
15
Walkley MSF (cont'd)
Completed
weld caps
16
Walkley MSF (cont'd)
17
Rail Bridge Construction
18
Airport Parkway Rail Bridge
19
Airport Parkway Pier Cap
Crews remove
casing from
cured pier cap
20
Airport Parkway Pier Cap
Completed
south pier
cap
21
Airport Parkway Rail Bridge
22
Uplands Rail Bridge
23
Uplands Rail Bridge
Pier cap
construction
24
Bowesville Rail Bridge
25
Earl Armstrong Rail Bridge
26
Earl Armstrong Bridge
Caisson rig
at Earl Armstrong
27
Limebank Rail Bridge
28
Limebank Station
Granular base
has been
installed
in preparation
for foundation
works
29
Guideway
31
Line 2 Shutdown
32
33
O-Train East Design Update (cont'd)
34
O-Train East Design Update (cont'd)
35
O-Train East Design Update (cont'd)
36
Construction
37
O-Train East
Construction Progress
• Tree and vegetation clearing is approximately 98%
complete;
• Commenced support of excavation installation at Montreal
Road Interchange;
• Watermain relocation commenced at Shefford and Jeanne
d’Arc, and,
• Completed access road to Greens Creek in preparation for
culvert works.
38
Montreal Interchange
39
Montreal Interchange
40
Montreal Interchange
Pile installation
41
Montreal Interchange
Piles have
been driven to
support
excavation
42
Montreal Interchange
Completed
lagging
installation
43
Montreal Interchange
Excavation is
underway in
preparation
for overpass
construction
44
Upcoming Q2 2020 Activities
45
Jeanne d’Arc Intersection
Reconfiguration
46
Mobility
47
48
O-Train West Design Update
49
O-Train West Design Update (Cont'd)
50
O-Train West Design Update (Cont'd)
• The City is reviewing Preliminary Designs for the following
project elements:
o Sections of Roadway Drainage;
o Light Maintenance and Storage Facility Design;
o Highway 417 Ramps – Pinecrest, Moodie & Richmond/Holly
Acres;
o Lincoln Fields Station;
o Baseline Station;
o Queensview Station;
o Pinecrest Station; and,
o Moodie Station.
51
Construction
52
Tree & Vegetation Clearing
53
Lincoln Fields
54
Iris Station
Southwest Transitway
Iris Street
55
Iris Station
56
Pinecrest Creek Pond
57
Pinecrest Creek Pond
58
Upcoming Q2 2020 Activities
59
Upcoming Q2 2020 Activities (cont’d)
60
Sir John A Macdonald Eastbound Lane
Reconfiguration
Current configuration
Future configuration
61
O-Train West Cut and Cover Tunnels
Parkway
Tunnel
62
Cut and Cover Tunnel Construction
Methodology
63
Parkway Tunnel
SUMMER
SPRING SPRING
64
Connaught Tunnel
FALL
FALL FALL
65
Pinecrest Trench
66
Stage 2 Alstom Citadis Vehicle Testing
67
Status Of Stage 2
Alstom Citadis Vehicles
Of the 38 Stage 2 Alstom Citadis Vehicles:
• 23 vehicles are awaiting production;
• 4 vehicles in production;
• 7 vehicles are undergoing testing; and
• 4 vehicles are in acceptance.
Awaiting In
Testing Acceptance
Production Production
68
Stakeholder Engagement
69
Questions?