THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM

ID WBS Task Name Duration Start Finish


2019 2020 2021 2022 2023 2024 2025
101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2
1 1 THE DETAILED DESIGN AND SUPERVISION WORKS FOR 1484 days Sun 26/1/20 Thu 2/10/25
PALEKBANG BRIDGE KOTA BHARU, KELANTAN DARUL NAIM FOR
THE EAST COAST ECONOMIC REGION DEVELOPMENT COUNCIL
2 1.1 (ECERDC)
COMMENCEMENT OF WORK 0 days Sun 26/1/20 Sun 26/1/20 26/1
3 1.2 PROJECT MILESTONE 1484 days Sun 26/1/20 Thu 2/10/25
16 1.3 DETAIL DESIGN STAGE 499 days Mon 27/1/20 Thu 23/12/21
17 1.3.1 Site Visit 14 days Mon 27/1/20 Thu 13/2/20 27/1 13/2
18 1.3.2 Data Gathering 21 days Mon 27/1/20 Mon 24/2/20 27/1 24/2
19 1.3.3 INCEPTION REPORT 15 days Thu 6/2/20 Wed 26/2/20
20 1.3.3.1 Preparation 5 days Thu 6/2/20 Wed 12/2/20 6/2 12/2
21 1.3.3.2 TOR for Engineering Survey Works 10 days Thu 6/2/20 Wed 19/2/20 6/2 19/2
22 1.3.3.3 TOR for Soil Investigation Works 10 days Thu 6/2/20 Wed 19/2/20 6/2 19/2
23 1.3.3.4 TOR for Hydraulic Study 15 days Thu 6/2/20 Wed 26/2/20 6/2 26/2
24 1.3.3.5 TOR & Inception Report Submission 0 days Wed 26/2/20 Wed 26/2/20 26/2
25 1.3.4 PRE-DEVELOPMENT WORKS 64 days Thu 27/2/20 Tue 26/5/20
26 1.3.4.1 ENGINEERING SURVEY 64 days Thu 27/2/20 Tue 26/5/20
27 1.3.4.1.1 Documentation Preparation (RFP) 5 days Thu 27/2/20 Wed 4/3/20 27/2 4/3
28 1.3.4.1.2 Submission 1 day Thu 5/3/20 Thu 5/3/20 5/3 5/3
29 1.3.4.1.3 Review 5 days Fri 6/3/20 Thu 12/3/20 6/3 12/3
30 1.3.4.1.4 Final RFP 1 day Fri 13/3/20 Fri 13/3/20 13/3 13/3
31 1.3.4.1.5 Tender & Award Stage 5 days Mon 16/3/20 Fri 20/3/20
32 1.3.4.1.5.1 Work Order 5 days Mon 16/3/20 Fri 20/3/20 16/3 20/3
33 1.3.4.1.6 Fieldwork 47 days Fri 20/3/20 Tue 26/5/20
34 1.3.4.1.6.1 Commencement 0 days Fri 20/3/20 Fri 20/3/20 20/3
35 1.3.4.1.6.2 Topographical Survey 42 days Mon 23/3/20 Tue 19/5/20 23/3 19/5
36 1.3.4.1.6.3 Bathymetric Survey 30 days Mon 23/3/20 Fri 1/5/20 23/3 1/5
37 1.3.4.1.6.4 Field Survey Report 5 days Wed 20/5/20 Tue 26/5/20 20/5 26/5
38 1.3.4.2 SOIL INVESTIGATION 64 days Thu 27/2/20 Tue 26/5/20
39 1.3.4.2.1 Documentation Preparation (Quotation) 5 days Thu 27/2/20 Wed 4/3/20 27/2 4/3
40 1.3.4.2.2 Submission 1 day Thu 5/3/20 Thu 5/3/20 5/3 5/3
41 1.3.4.2.3 Review 5 days Fri 6/3/20 Thu 12/3/20 6/3 12/3
42 1.3.4.2.4 Final RFP 1 day Fri 13/3/20 Fri 13/3/20 13/3 13/3
43 1.3.4.2.5 Tender & Award Stage 5 days Mon 16/3/20 Fri 20/3/20
44 1.3.4.2.5.1 Work Order 5 days Mon 16/3/20 Fri 20/3/20 16/3 20/3
45 1.3.4.2.6 Field Work 47 days Mon 23/3/20 Tue 26/5/20
46 1.3.4.2.6.1 Commencement 32 days Mon 23/3/20 Tue 5/5/20 23/3 5/5
47 1.3.4.2.6.2 S.I. Interpretavie Report 15 days Wed 6/5/20 Tue 26/5/20 6/5 26/5
48 1.3.4.3 HYDRAULIC STUDY REPORT 64 days Thu 27/2/20 Tue 26/5/20
49 1.3.4.3.1 Data Gathering (Historical Data & Topographical Data) 21 days Thu 27/2/20 Thu 26/3/20 27/2 26/3
50 1.3.4.3.2 Hydraulic Analysis 10 days Fri 27/3/20 Thu 9/4/20 27/3 9/4
51 1.3.4.3.3 Scour Analysis 10 days Fri 10/4/20 Thu 23/4/20 10/4 23/4
52 1.3.4.3.4 Sediment & Transport Analysis 10 days Fri 24/4/20 Thu 7/5/20 24/4 7/5
53 1.3.4.3.5 Bridge Deck Drainage Design 10 days Fri 8/5/20 Thu 21/5/20 8/5 21/5
54 1.3.4.3.6 Report Submission 3 days Fri 22/5/20 Tue 26/5/20 22/5 26/5
55 1.3.5 DESIGN BRIEF 87 days Thu 27/2/20 Fri 26/6/20
56 1.3.5.1 Bridge Design Brief 51 days Thu 27/2/20 Thu 7/5/20
57 1.3.5.1.1 Architectural Design & Bridge Aesthetics 21 days Thu 27/2/20 Thu 26/3/20 27/2 26/3
58 1.3.5.1.2 Functional Requirements 5 days Fri 27/3/20 Thu 2/4/20 27/3 2/4
59 1.3.5.1.3 Main Superstructure Elements 20 days Fri 3/4/20 Thu 30/4/20 3/4 30/4
60 1.3.5.1.4 Deck & Wearing Surface 9 days Fri 1/5/20 Wed 13/5/20 1/5 13/5

Task Summary Rolled Up Progress Inactive Task Duration-only Finish-only


Critical Task Rolled Up Task Split Inactive Milestone Manual Summary Rollup Group By Summary
Progress Rolled Up Critical Task External Tasks Inactive Summary Manual Summary Deadline
Milestone Rolled Up Milestone Project Summary Manual Task Start-only

DETAILED MASTER IMPLEMENTATION PROGRAM Page 1 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM

ID WBS Task Name Duration Start Finish


2019 2020 2021 2022 2023 2024 2025
101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2
61 1.3.5.2 Geotechnical Design Brief 34 days Thu 27/2/20 Tue 14/4/20
62 1.3.5.2.1 Slope / Ground Treatment Design 7 days Thu 27/2/20 Fri 6/3/20 27/2 6/3
63 1.3.5.2.2 Embankment Design 14 days Mon 9/3/20 Thu 26/3/20 9/3 26/3
64 1.3.5.2.3 Structural Foundation 8 days Fri 27/3/20 Tue 7/4/20 27/3 7/4
65 1.3.5.2.4 Culvert Foundation 5 days Wed 8/4/20 Tue 14/4/20 8/4 14/4
66 1.3.5.3 Presentation to ECERDC 19 days Thu 14/5/20 Tue 9/6/20 14/5 9/6
67 1.3.5.4 Review & Comment / Submission 8 days Wed 10/6/20 Fri 19/6/20 10/6 19/6
68 1.3.5.5 Approval for Design Brief 5 days Mon 22/6/20 Fri 26/6/20 22/6 26/6
69 1.3.6 SCHEMATIC DESIGN 107 days Thu 27/2/20 Fri 24/7/20
70 1.3.6.1 Bridge Design 84 days Thu 27/2/20 Tue 23/6/20
71 1.3.6.1.1 Foundation Design 14 days Thu 27/2/20 Tue 17/3/20 27/2 17/3
72 1.3.6.1.2 Pier Design 7 days Wed 18/3/20 Thu 26/3/20 18/3 26/3
73 1.3.6.1.3 Abutment Design 7 days Fri 27/3/20 Mon 6/4/20 27/3 6/4
74 1.3.6.1.4 Bearings 7 days Tue 7/4/20 Wed 15/4/20 7/4 15/4
75 1.3.6.1.5 Main Superstructure Design 21 days Thu 16/4/20 Thu 14/5/20 16/4 14/5
76 1.3.6.1.6 Deck & Deck Wearing Surface 7 days Fri 15/5/20 Mon 25/5/20 15/5 25/5
77 1.3.6.1.7 Bridge Traffic Barriers 14 days Tue 26/5/20 Fri 12/6/20 26/5 12/6
78 1.3.6.1.8 Expansion Joints & Relieving Slabs 7 days Mon 15/6/20 Tue 23/6/20 15/6 23/6
79 1.3.6.1.9 Services, Lighting, Miscellaneous 14 days Thu 16/4/20 Tue 5/5/20 16/4 5/5
80 1.3.6.1.10 Paint System & Structural Steel 14 days Tue 26/5/20 Fri 12/6/20 26/5 12/6
81 1.3.6.1.11 Bridge Modelling 28 days Thu 16/4/20 Mon 25/5/20 16/4 25/5
82 1.3.6.2 Presentation to ECERDC 7 days Mon 29/6/20 Tue 7/7/20 29/6 7/7
83 1.3.6.3 Review & Comment / Submission 8 days Wed 8/7/20 Fri 17/7/20 8/7 17/7
84 1.3.6.4 Approval Schematic Design 5 days Mon 20/7/20 Fri 24/7/20 20/7 24/7
85 1.3.7 DETAILED DESIGN 66 days Mon 27/7/20 Mon 26/10/20
86 1.3.7.1 Drawing Preparation 47 days Mon 27/7/20 Tue 29/9/20
87 1.3.7.1.1 Geotechnical Works 22 days Mon 27/7/20 Tue 25/8/20
88 1.3.7.1.1.1 Relocation Works 2 days Mon 27/7/20 Tue 28/7/20 27/7 28/7
89 1.3.7.1.1.2 Slope / Ground Treatment 5 days Wed 29/7/20 Tue 4/8/20 29/7 4/8
90 1.3.7.1.1.3 Reinforced Soil Structure (RSS) Wall 5 days Wed 5/8/20 Tue 11/8/20 5/8 11/8
91 1.3.7.1.1.4 Structural Foundation 5 days Wed 12/8/20 Tue 18/8/20 12/8 18/8
92 1.3.7.1.1.5 Culvert Foundation 5 days Wed 19/8/20 Tue 25/8/20 19/8 25/8
93 1.3.7.1.2 Bridge Components 42 days Mon 27/7/20 Tue 22/9/20
94 1.3.7.1.2.1 Foundation 7 days Mon 27/7/20 Tue 4/8/20 27/7 4/8
95 1.3.7.1.2.2 Pier 5 days Wed 5/8/20 Tue 11/8/20 5/8 11/8
96 1.3.7.1.2.3 Abutment 5 days Wed 12/8/20 Tue 18/8/20 12/8 18/8
97 1.3.7.1.2.4 Bearings 5 days Wed 19/8/20 Tue 25/8/20 19/8 25/8
98 1.3.7.1.2.5 Main Superstructure 10 days Wed 12/8/20 Tue 25/8/20 12/8 25/8
99 1.3.7.1.2.6 Deck & Deck Wearing Surface 5 days Wed 26/8/20 Tue 1/9/20 26/8 1/9
100 1.3.7.1.2.7 Bridge Traffic Barriers 5 days Wed 2/9/20 Tue 8/9/20 2/9 8/9
101 1.3.7.1.2.8 Expansion Joints & Relieving Slabs 5 days Wed 9/9/20 Tue 15/9/20 9/9 15/9
102 1.3.7.1.2.9 Paint System & Structural Steel 5 days Wed 16/9/20 Tue 22/9/20 16/9 22/9
103 1.3.7.1.3 Mechanical & Electrical Services 5 days Wed 23/9/20 Tue 29/9/20
104 1.3.7.1.3.1 Services, Lighting, Miscellaneous 5 days Wed 23/9/20 Tue 29/9/20 23/9 29/9
105 1.3.7.2 Final Detail Engineering Design Report 19 days Wed 30/9/20 Mon 26/10/20
106 1.3.7.2.1 Preparation 5 days Wed 30/9/20 Tue 6/10/20 30/9 6/10
107 1.3.7.2.2 First Submission 2 days Wed 7/10/20 Thu 8/10/20 7/10 8/10
108 1.3.7.2.3 Presentation 1 day Fri 9/10/20 Fri 9/10/20 9/10 9/10
109 1.3.7.2.4 Comments 4 days Mon 12/10/20 Thu 15/10/20 12/10 15/10

Task Summary Rolled Up Progress Inactive Task Duration-only Finish-only


Critical Task Rolled Up Task Split Inactive Milestone Manual Summary Rollup Group By Summary
Progress Rolled Up Critical Task External Tasks Inactive Summary Manual Summary Deadline
Milestone Rolled Up Milestone Project Summary Manual Task Start-only

DETAILED MASTER IMPLEMENTATION PROGRAM Page 2 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM

ID WBS Task Name Duration Start Finish


2019 2020 2021 2022 2023 2024 2025
101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2
110 1.3.7.2.5 Second Submission 2 days Fri 16/10/20 Mon 19/10/20 16/10 19/10
111 1.3.7.2.6 Approved by ECERDC 5 days Tue 20/10/20 Mon 26/10/20 20/10 26/10
112 1.3.7.3 Tender Documentation Preparation 66 days Mon 27/7/20 Mon 26/10/20
113 1.3.7.3.1 Instruction to Tenderers (prepared by QS) 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
114 1.3.7.3.2 Condition of Contract (prepared by QS) 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
115 1.3.7.3.3 Form of Tender (prepared by QS) 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
116 1.3.7.3.4 Specification of Structure 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
117 1.3.7.3.5 Specification of Pipe Work 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
118 1.3.7.3.6 Specification of Mechanical 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
119 1.3.7.3.7 Specification of Electrical 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
120 1.3.7.3.8 Specification of Instrumentation 5 days Mon 27/7/20 Fri 31/7/20 27/7 31/7
121 1.3.7.3.9 BOQ Structure (prepared by QS) 10 days Mon 27/7/20 Fri 7/8/20 27/7 7/8
122 1.3.7.3.10 BOQ Pipeworks (prepared by QS) 10 days Mon 27/7/20 Fri 7/8/20 27/7 7/8
123 1.3.7.3.11 BOQ Mechanical 10 days Mon 27/7/20 Fri 7/8/20 27/7 7/8
124 1.3.7.3.12 BOQ Electrical 10 days Mon 27/7/20 Fri 7/8/20 27/7 7/8
125 1.3.7.3.13 Schedule of Particulars Civil 10 days Mon 27/7/20 Fri 7/8/20 27/7 7/8
126 1.3.7.3.14 Schedule of Particulars Mechanical 10 days Mon 27/7/20 Fri 7/8/20 27/7 7/8
127 1.3.7.3.15 Schedule of Particulars Electrical 10 days Mon 27/7/20 Fri 7/8/20 27/7 7/8
128 1.3.7.3.16 Appendices 1 day Mon 10/8/20 Mon 10/8/20 10/8 10/8
129 1.3.7.3.17 Document & Drawing Compilation 55 days Tue 11/8/20 Mon 26/10/20
130 1.3.7.3.17.1 1st Draft 1 day Tue 11/8/20 Tue 11/8/20 11/8 11/8
131 1.3.7.3.17.2 Review by ECERDC 5 days Wed 12/8/20 Tue 18/8/20 12/8 18/8
132 1.3.7.3.17.3 2nd Draft 5 days Wed 19/8/20 Tue 25/8/20 19/8 25/8
133 1.3.7.3.17.4 Review by ECERDC 5 days Wed 26/8/20 Tue 1/9/20 26/8 1/9
134 1.3.7.3.17.5 Final 5 days Tue 20/10/20 Mon 26/10/20 20/10 26/10
135 1.3.7.3.17.6 Cost Review by ECERDC 5 days Tue 20/10/20 Mon 26/10/20 20/10 26/10
136 1.3.7.3.18 Tender Evalution Criteria 7 days Fri 16/10/20 Mon 26/10/20 16/10 26/10
137 1.3.8 AUTHORITY SUBMISSION & ENGINEERING APPROVALS 499 days Mon 27/1/20 Thu 23/12/21
138 1.3.8.1 Land Alienation 145 days Mon 27/1/20 Fri 14/8/20
139 1.3.8.1.1 Drawing Preparation by ES 20 days Mon 23/3/20 Fri 17/4/20 23/3 17/4
140 1.3.8.1.2 Land Valuation Report 5 days Mon 20/4/20 Fri 24/4/20 20/4 24/4
141 1.3.8.1.3 Submission to Land Office for Approval Land Alienation 1 day Mon 27/1/20 Mon 27/1/20 27/1 27/1
142 1.3.8.1.4 5A Notice 100 days Tue 28/1/20 Mon 15/6/20 28/1 15/6
143 1.3.8.1.5 Final Approval of Land Alienation by Land Office (Before 31 days Tue 16/6/20 Tue 28/7/20 16/6 28/7
Tender)
144 1.3.8.1.6 Final Report of Land Alienation Status 13 days Wed 29/7/20 Fri 14/8/20 29/7 14/8
145 1.3.8.2 Land Acquisition 459 days Mon 23/3/20 Thu 23/12/21
146 1.3.8.2.1 Drawing Preparation by ES 20 days Mon 23/3/20 Fri 17/4/20 23/3 17/4
147 1.3.8.2.2 Land Valuation Report 5 days Mon 20/4/20 Fri 24/4/20 20/4 24/4
148 1.3.8.2.3 Submission to Land Office for Approval Land Acquisition 1 day Mon 27/4/20 Mon 27/4/20 27/4 27/4
149 1.3.8.2.4 Obtaining Borang K 200 days Tue 28/4/20 Mon 1/2/21 28/4 1/2
150 1.3.8.2.5 Final Approval of Land Acquisition by Land Office (Before Tender) 22 days Tue 2/2/21 Wed 3/3/21 2/2 3/3
151 1.3.8.2.6 Final Report of Land Acquisition Status 11 days Thu 9/12/21 Thu 23/12/21 9/12 23/12
152 1.3.8.3 Submission to Authorities 114 days Wed 20/5/20 Mon 26/10/20
153 1.3.8.3.1 JABATAN PENGAIRAN & SALIRAN (JPS) 114 days Wed 20/5/20 Mon 26/10/20
154 1.3.8.3.1.1 Drawing Submission for Approval 34 days Wed 20/5/20 Mon 6/7/20 20/5 6/7
155 1.3.8.3.1.2 Review & Comment 40 days Tue 7/7/20 Mon 31/8/20 7/7 31/8
156 1.3.8.3.1.3 Approval 40 days Tue 1/9/20 Mon 26/10/20 1/9 26/10
157 1.3.8.3.2 MAJLIS PERBANDARAN / DAERAH (OSC) 114 days Wed 20/5/20 Mon 26/10/20

Task Summary Rolled Up Progress Inactive Task Duration-only Finish-only


Critical Task Rolled Up Task Split Inactive Milestone Manual Summary Rollup Group By Summary
Progress Rolled Up Critical Task External Tasks Inactive Summary Manual Summary Deadline
Milestone Rolled Up Milestone Project Summary Manual Task Start-only

DETAILED MASTER IMPLEMENTATION PROGRAM Page 3 REVISED MIP : PRELIMINARY DATED 25 JAN 2020
THE DETAILED DESIGN AND SUPERVISION WORKS FOR PALEKBANG BRIDGE, KOTA BHARU, KELANTAN DARUL NAIM

ID WBS Task Name Duration Start Finish


2019 2020 2021 2022 2023 2024 2025
101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2 3 4 5 6 7 8 9 101112 1 2
158 1.3.8.3.2.1 Building Plan Approval 114 days Wed 20/5/20 Mon 26/10/20
159 1.3.8.3.2.1.1 Drawing Submission for Approval 34 days Wed 20/5/20 Mon 6/7/20 20/5 6/7
160 1.3.8.3.2.1.2 Review & Comment 40 days Tue 7/7/20 Mon 31/8/20 7/7 31/8
161 1.3.8.3.2.1.3 Approval 40 days Tue 1/9/20 Mon 26/10/20 1/9 26/10
162 1.3.8.3.2.1.4 Documents / Drawing Approval by Authorities 5 days Tue 20/10/20 Mon 26/10/20 20/10 26/10
163 1.4 TENDER STAGE 74 days Tue 27/10/20 Fri 5/2/21
164 1.4.1 Final Tender Document 1 day Tue 27/10/20 Tue 27/10/20 27/10 27/10
165 1.4.2 Tender Process Approval 5 days Wed 28/10/20 Tue 3/11/20 28/10 3/11
166 1.4.3 Tender Advertisment 5 days Wed 4/11/20 Tue 10/11/20 4/11 10/11
167 1.4.4 Tender Period Untill Closing Date 20 days Wed 11/11/20 Tue 8/12/20 11/11 8/12
168 1.4.5 Tender Opening 1 day Wed 9/12/20 Wed 9/12/20 9/12 9/12
169 1.4.6 Tender Evaluation Report 10 days Thu 10/12/20 Wed 23/12/20 10/12 23/12
170 1.4.7 Tender Evaluation Committee Meeting 5 days Thu 24/12/20 Wed 30/12/20 24/12 30/12
171 1.4.8 Tender Clarification (If Any) 6 days Thu 31/12/20 Thu 7/1/21 31/12 7/1
172 1.4.9 Proc Board A 5 days Fri 8/1/21 Thu 14/1/21 8/1 14/1
173 1.4.10 Letter of Award (LOA) 5 days Fri 15/1/21 Thu 21/1/21 15/1 21/1
174 1.4.11 Site Possession 1 day Fri 5/2/21 Fri 5/2/21 5/2 5/2
175 1.5 CONSTRUCTION STAGE 695 days Fri 5/2/21 Thu 5/10/23
176 1.5.1 Construction (32 Months) 695 days Fri 5/2/21 Thu 5/10/23 5/2 5/10
177 1.5.2 Preparation of Construction & Contract Drawings 30 days Fri 5/2/21 Thu 18/3/21 5/2 18/3
178 1.5.3 Issued Contract Documents 30 days Fri 19/3/21 Thu 29/4/21 19/3 29/4
179 1.5.4 Testing & Commissioning 15 days Fri 15/9/23 Thu 5/10/23
180 1.5.4.1 Mobilisation 15 days Fri 15/9/23 Thu 5/10/23 15/9 5/10
181 1.5.4.2 1st Submission 3 days Fri 15/9/23 Tue 19/9/23 15/9 19/9
182 1.5.4.3 Presentation 1 day Wed 20/9/23 Wed 20/9/23 20/9 20/9
183 1.5.4.4 Comments 8 days Thu 21/9/23 Mon 2/10/23 21/9 2/10
184 1.5.4.5 2nd Submission 3 days Tue 3/10/23 Thu 5/10/23 3/10 5/10
185 1.5.4.6 Final Approval 1 day Thu 5/10/23 Thu 5/10/23 5/10 5/10
186 1.5.5 Operation & Maintenance (O&M) Manual 30 days Fri 25/8/23 Thu 5/10/23
187 1.5.5.1 Mobilisation 30 days Fri 25/8/23 Thu 5/10/23 25/8 5/10
188 1.5.5.2 1st Submission 7 days Fri 25/8/23 Mon 4/9/23 25/8 4/9
189 1.5.5.3 Presentation 1 day Tue 5/9/23 Tue 5/9/23 5/9 5/9
190 1.5.5.4 Comments 10 days Wed 6/9/23 Tue 19/9/23 6/9 19/9
191 1.5.5.5 2nd Submission 7 days Wed 20/9/23 Thu 28/9/23 20/9 28/9
192 1.5.5.6 Final Approval 1 day Fri 29/9/23 Fri 29/9/23 29/9 29/9
193 1.6 POST CONSTRUCTION STAGE (12 Months - DLP end on 21/10/20) 520 days Thu 5/10/23 Thu 2/10/25
194 1.6.1 Performance Review Report 0 days Thu 5/10/23 Thu 5/10/23 5/10
195 1.6.2 Report on Project Assets Management and Integration Works with 0 days Thu 5/10/23 Thu 5/10/23 5/10
Existing System
196 1.6.3 Defect Inspections & Reports 0 days Thu 5/10/23 Thu 5/10/23 5/10
197 1.6.4 Approval & Recommend the Method to Carry Out of Remedial / 0 days Thu 5/10/23 Thu 5/10/23 5/10
Defects Rectification Works
198 1.6.5 Inspect & Witness Defect Rectification Works 0 days Thu 5/10/23 Thu 5/10/23 5/10
199 1.6.6 Issuance of Certificate of Making Good Defects (CMGD) 0 days Thu 2/10/25 Thu 2/10/25 2/10
200 1.6.7 Project Final Account Report 0 days Thu 2/10/25 Thu 2/10/25 2/10
201 1.6.8 Project Closing 0 days Thu 2/10/25 Thu 2/10/25 2/10

Task Summary Rolled Up Progress Inactive Task Duration-only Finish-only


Critical Task Rolled Up Task Split Inactive Milestone Manual Summary Rollup Group By Summary
Progress Rolled Up Critical Task External Tasks Inactive Summary Manual Summary Deadline
Milestone Rolled Up Milestone Project Summary Manual Task Start-only

DETAILED MASTER IMPLEMENTATION PROGRAM Page 4 REVISED MIP : PRELIMINARY DATED 25 JAN 2020