UNIT
DESCRIPTION OF MATERIALS QUANTITY UNIT
COST
TOTAL COST
REINFORCEMENT
FOUNDATION ( FOOTING F1 )
16mm DIA. BARS @ 6.0m 51.00 PCS 376.00 19176.00
TIE WIRE 8.40 KG 84.00 705.60
FOUNDATION ( FOOTING F2 )
16mm DIA. BARS @ 6.0m 11.00 PCS 376.00 4136.00
TIE WIRE 2.00 KG 84.00 168.00
WALL FOOTING ( WFT )
10mm DIA. BARS @ 6.0m 47.00 PCS 127.00 5969.00
TIE WIRE 4.00 KG 84.00 336.00
TIE BEAM ( FTB )
16mm DIA. BARS @ 6.0m 186.00 PCS 376.00 69936.00
10mm DIA. BARS @ 6.0m 134.00 PCS 127.00 17018.00
TIE WIRE 25.60 KG 84.00 2150.40
BEAM (B-1)
16mm DIA. BARS @ 6.0m 201.00 PCS 376.00 75576.00
10mm DIA. BARS @ 6.0m 105.00 PCS 127.00 13335.00
TIE WIRE 31.50 KG 84.00 2646.00
BEAM (B-2)
16mm DIA. BARS @ 6.0m 62.00 PCS 376.00 23312.00
10mm DIA. BARS @ 6.0m 48.00 PCS 127.00 6096.00
TIE WIRE 7.00 KG 84.00 588.00
CROSS BEAM (C-B)
16mm DIA. BARS @ 6.0m 8.00 PCS 376.00 3008.00
10mm DIA. BARS @ 6.0m 8.00 PCS 127.00 1016.00
TIE WIRE 1.40 KG 84.00 117.60
ROOF BEAM ( RB )
16mm DIA. BARS @ 6.0m 160.00 PCS 376.00 60160.00
10mm DIA. BARS @ 6.0m 139.00 PCS 127.00 17653.00
TIE WIRE 21.70 KG 84.00 1822.80
COLUMN 1 ( C-1 ) G-F
16mm DIA. BARS @ 6.0m 132.00 PCS 376.00 49632.00
10mm DIA. BARS @ 6.0m 107.00 PCS 127.00 13589.00
TIE WIRE 12.10 KG 84.00 1016.40
COLUMN 1 ( C-2 ) G-F
16mm DIA. BARS @ 6.0m 19.00 PCS 376.00 7144.00
10mm DIA. BARS @ 6.0m 19.00 PCS 127.00 2413.00
TIE WIRE 2.30 KG 84.00 193.20
COLUMN 1 ( C-3 ) G-F
16mm DIA. BARS @ 6.0m 12.00 PCS 376.00 4512.00
10mm DIA. BARS @ 6.0m 19.00 PCS 127.00 2413.00
TIE WIRE 2.30 KG 84.00 193.20
COLUMN 1 ( C-1 ) 2ND-F
16mm DIA. BARS @ 6.0m 88.00 PCS 376.00 33088.00
10mm DIA. BARS @ 6.0m 60.00 PCS 127.00 7620.00
TIE WIRE 6.80 KG 84.00 571.20
TWO-WAY SLAB ( S2 )
10mm DIA. BARS @ 6.0m (L) 384.00 PCS 127.00 48768.00
TIE WIRE 35.00 KG 84.00 2940.00
ONE-WAY SLAB ( S1 )
10mm DIA. BARS @ 6.0m (L) 28.00 PCS 127.00 3556.00
TIE WIRE 3.00 KG 84.00 252.00
GROUND SLAB
10mm DIA. BARS @ 6.0m (L) 63.00 PCS 127.00 8001.00
10mm DIA. BARS @ 6.0m (W) 63.00 PCS 127.00 0.00
TIE WIRE 17.00 KG 84.00 1428.00
STAIRS
12mm DIA. BARS @ 6.0m 11.00 PCS 186.00 2046.00
10mm DIA. BARS @ 6.0m 14.00 PCS 127.00 1778.00
16mm DIA. BARS @ 6.0m 9.00 PCS 376.00 3384.00
10mm DIA. BARS @ 6.0m 6.00 PCS 127.00 762.00
TIE WIRE 2.50 KG 84.00 210.00
CHB REINFORCEMENT FOR BACKFILL
10mm DIA. BARS @ 6.0m 27.00 PCS 127.00 3429.00
10mm DIA. BARS @ 6.0m 27.00 PCS 127.00 3429.00
TIE WIRE 4.00 KG 84.00 336.00
CHB REINFORCEMENT FOR GROUND FLOOR
10mm DIA. BARS @ 6.0m 42.00 PCS 127.00 5334.00
10mm DIA. BARS @ 6.0m 42.00 PCS 127.00 5334.00
TIE WIRE 5.00 KG 84.00 420.00
CHB REINFORCEMENT FOR 2ND FLOOR
10mm DIA. BARS @ 6.0m 55.00 PCS 127.00 6985.00
10mm DIA. BARS @ 6.0m 59.00 PCS 127.00 7493.00
TIE WIRE 9.70 KG 84.00 814.80
CONCRETING
FOUNDATION ( FOOTING F1 )
BAGS OF CEMENT 67.00 BAGS 225.00 11700
VOL. OF SAND 3.80 CU.M 600.00 2280
VOL. OF 3/4 CRUSHED 7.50 CU.M 780.00 5850
TOTAL VOL. OF MIX 7.44 CU.M
WALL FOOTING ( WFT )
BAGS OF CEMENT 52.00 BAGS 225.00 11700
VOL. OF SAND 2.90 CU.M 600.00 1740
VOL. OF 3/4 CRUSHED 5.80 CU.M 780.00 4524
TOTAL VOL. OF MIX 5.76 CU.M
GROUND SLAB
BAGS OF CEMENT 129.00 BAGS 225.00 29025
VOL. OF SAND 7.20 CU.M 600.00 4320
VOL. OF 3/4 CRUSHED 14.30 CU.M 780.00 11154
TOTAL VOL. OF MIX 14.25 CU.M
TWO-WAY SLAB ( S2 )
BAGS OF CEMENT 81.00 BAGS 225.00 5304
VOL. OF SAND 4.50 CU.M 600.00 2700
VOL. OF 3/4 CRUSHED 9.00 CU.M 780.00 7020
TOTAL VOL. OF MIX 9.00 CU.M
COLUMN 1 ( C1 ) GROUND FLOOR
BAGS OF CEMENT 51.00 BAGS 225.00 11475
VOL. OF SAND 2.90 CU.M 600.00 1740
VOL. OF 3/4 CRUSHED 5.70 CU.M 780.00 4446
TOTAL VOL. OF MIX 5.84 CU.M
COLUMN 2 ( C2 ) GROUND FLOOR
BAGS OF CEMENT 8.00 BAGS 225.00 1800
VOL. OF SAND 0.50 CU.M 600.00 300
VOL. OF 3/4 CRUSHED 0.90 CU.M 780.00 702
TOTAL VOL. OF MIX 0.82 CU.M
COLUMN 3 ( C3 ) GROUND FLOOR
BAGS OF CEMENT 9.00 BAGS 225.00 2025
VOL. OF SAND 0.50 CU.M 600.00 300
VOL. OF 3/4 CRUSHED 1.00 CU.M 780.00 780
TOTAL VOL. OF MIX 0.92 CU.M
COLUMN 1 ( C1 ) 2ND FLOOR
BAGS OF CEMENT 32.00 BAGS 225.00 7200
VOL. OF SAND 1.80 CU.M 600.00 1080
VOL. OF 3/4 CRUSHED 3.60 CU.M 780.00 2808
TOTAL VOL. OF MIX 3.52 CU.M
TIE BEAM ( FTB )
BAGS OF CEMENT 57 BAGS 225.00 12825
VOL. OF SAND 3.2 CU.M 600.00 1920
VOL. OF 3/4 CRUSHED 6.3 CU.M 780.00 4914
TOTAL VOL. OF MIX 6.24 CU.M
BEAM 1 ( B1 )
BAGS OF CEMENT 58 BAGS 225.00 13050
VOL. OF SAND 3.2 CU.M 600.00 1920
VOL. OF 3/4 CRUSHED 6.4 CU.M 780.00 4992
TOTAL VOL. OF MIX 6.39 CU.M
BEAM 2 ( B2 )
BAGS OF CEMENT 19 BAGS 225.00 4275
VOL. OF SAND 1.1 CU.M 600.00 660
VOL. OF 3/4 CRUSHED 2.2 CU.M 780.00 1716
TOTAL VOL. OF MIX 2.1 CU.M
CROSS BEAM (C-B)
BAGS OF CEMENT 3 BAGS 225.00 675
VOL. OF SAND 0.2 CU.M 600.00 120
VOL. OF 3/4 CRUSHED 0.3 CU.M 780.00 234
TOTAL VOL. OF MIX 0.3 CU.M
ROOF BEAM ( RB )
BAGS OF CEMENT 84 BAGS 225.00 18900
VOL. OF SAND 3.4 CU.M 600.00 2040
VOL. OF 3/4 CRUSHED 6.8 CU.M 780.00 5304
TOTAL VOL. OF MIX 6.74 CU.M
STAIRS
BAGS OF CEMENT 18 BAGS 225.00 4050
VOL. OF SAND 1 CU.M 600.00 600
VOL. OF 3/4 CRUSHED 2 CU.M 780.00 1560
TOTAL VOL. OF MIX 1.96 CU.M
MASONRY
CHB LAYING
TOTAL AREA 409.3 SQ.M
NO. 6 CHB 5843.00 PCS 13.00 75959
BAGS OF CEMENT 415.00 BAGS 225.00 93375
VOL. OF SCREEN SAND 34.70 CU.M 500.00 17350
PLASTERING
TOTAL AREA 376.30 SQ.M
BAGS OF CEMENT 284.00 BAGS 225.00 63900
VOL. OF FINE SAND 13.20 CU.M 500.00 6600
TOTAL 257184
ELECTRICAL
GROUND FLOOR
CONVINIENCE OUTET 15 750 11250
LIGHTING OUTLET 13 750 9750
FIN LIGTH 25 350 8750
SWITCH 8 750 6000
ACU OUTLET 1 850 850
REF OUTLET 1 850 850
POWER BOX 1 10000 10000
2ND FLOOR 64 47450
CONVINIENCE OUTET 14 750 2550
LIGHTING OUTLET 28 750 21000
FIN LIGTH 25 350 8750
SWITCH 9 750 6750
ACU OUTLET 3 850 2550
REF OUTLET 0 850 0
POWER BOX 1 10000 10000
4 12550
PLUMBING
COMFORT ROOM 3 UNITS 37600 112800
KITCHEN COUNTER 2 UNITS 37600 75200
GROUND FLOOR
DOORS
SOLID PANEL DOOR 2 UNITS 10000 20000
PVC DOOR TYPE 3 UNITS 3760 11280
SLIDING DOOR 1 UNITS 13760 13760
SLIDING DOOR 2 UNITS 9500 19000
ROOMPANEL DOOR 8 UNITS 8000 64000
WINDOWS
WINDOW 1 4 UNITS 9500 38000
WINDOW 2 2 UNITS 8000 16000
WINDOW 3 5 UNITS 6000 30000
WINDOW 4 2 UNITS 6000 12000
WINDOW 5 3 UNITS 4500 13500
WINDOW 6 1 UNITS 3500 3500
2ND FLOOR 241040
FINISHING
TILES
GROUND FLOOR
60 X 60 GRANITE TILE 263 PCS 376.97 99143.11
CEMENT MORTAR 8 BAGS 454.67 3637.36
WHITE CEMENT 45 KGS 35 1575
ADHESIVE 10 BAGS 710.5 7105
2ND FLOOR 111460.47
60 X 60 GRANITE TILE 205 PCS 376.97 77278.85
CEMENT MORTAR 7 BAGS 454.67 3182.69
WHITE CEMENT 35 KGS 35 1225
ADHESIVE 8 BAGS 710.5 5684
KITCHEN COUNTER 87370.54
KITCHEN GRANITE 5 PCS 7500 37500
CEMENT MORTAR 1 BAGS 454.67 454.67
WHITE CEMENT 20 KGS 35 700
ADHESIVE 4 BAGS 710.5 2842
41496.67
PAINTING
GROUND FLOOR
PAINT AREA 409.3 27 81 1950 157950
2ND FLOOR 112557.5
PAINT AREA 376.30 27 81 1950 157950
GROUND FLOOR CEILING 103482.5
PAINT AREA 90 13 39 1257 49023
2ND FLOOR CEILING 16830
PAINT AREA 70.00 7 21 1257 26397
13090
DOORS AND DOOR JAMB 16 UNITS 3000 48000
75420
K.M.
TAN CITY
LABOR
COST
19881.60 10636.6
4304.00 2294.16
6305.00 3846.48
89104.40
38792.2
10966.6
91557.00
41920.6
8593.2
29996.00
12930.7
3928.32
4141.60
1668.48
654.72
79635.80
33369.6
11375.8
64237.40
27529.9
8756.88
9750.20
3962.64
1554.96
7118.20
2502.72
1554.96
41279.20
18353.3
4910.4
51708.00
31426.6
3808.00
2291.52
9429.00
5155.92
5155.92
8180.00
1292.28
1145.76
1877.04
491.04
7194.00
2209.68
2209.68
11088.00
3437.28
3437.28
15292.80
4501.2
4828.56
20313.3
16387
15543
21697
17516
144090
19830
17964
44499
15024
17661
2802
3105
11088
19659
19962
6651
1029
26244
9315
186684
70500
49700
106500
100696.9125
86770.74375
47450 22400
12550 1400
188000
241040
111460.47
41496.67
115 43274.5
115 8050
2300 36800
216040 47069.5
29920 43274.5
SC BALINAGAY BUILDERS
Km. 120 NE Aurora Rd., Lourdes, Cabanatuan City
I EXCAVATION
FOUNDATION ( FOOTING F1 ) 11 1.3 1.3 1.5 27.89 CU.M
FOUNDATION ( FOOTING F2 ) 4 1 1 1.2 4.80 CU.M
WALL FOOTING ( WFT ) 76 0.5 1 1 38.00 CU.M
TIE BEAM ( FTB ) 76 0.5 1.5 1 57.00 CU.M
TOTAL
II BACKFILL
FOUNDATION ( FOOTING F1 ) 14 1.15 1.15 1.7 31.48 CU.M
WALL FOOTING ( WFT ) 76 0.4 1 1 30.40 CU.M
TIE BEAM ( FTB ) 76 0.3 1.2 1 27.36 CU.M
TOTAL
III EARTHFILL
FLOOR AREA - - - 0.6 89.95 CU.M
TOTAL
LABOR
9759.75 350
1680 350
13300 350
19950 350
44689.8
2518.04 80
2432 80
2188.8 80
7138.84
35979 400
35979
FTB(FOOTING TIE BEAM)
BEAM LENGTH TIE WIRE 16mm DIA. 10mm DIA.
3.45 1.1 8 5
3.45 1.1 8 5
3.04 1.1 8 5
3.04 1.1 8 5
1.65 0.8 5 4
2.90 1 8 5
2.90 1 8 5
6.35 1.6 12 9
3.45 1.1 8 5
2.00 0.9 5 4
1.35 0.8 4 4
3.65 1.1 8 6
3.65 1.1 8 6
3.65 1.1 8 6
1.70 1.1 8 6
3.00 1 8 5
0.70 0.7 4 3
1.00 0.7 4 3
3.65 1.1 8 6
1.50 1.1 8 6
5.00 1 8 7
2.48 1 8 5
2.85 1 8 5
4.90 1 8 7
5.00 1 8 7
TOTAL 25.6 186 134
76.31
BEAM (B-1)
BEAM LENGTH TIE WIRE 16mm DIA. 10mm DIA.
3.45 1.7 12 5
4.90 2.1 13 7
4.90 2.1 13 7
1.65 1.3 6 4
1.35 1.3 5 4
1.35 1.3 5 4
2.85 1.6 11 5 63.88
2.48 1.5 10 5
5.00 2.1 13 7
5.00 2.1 13 7
3.85 1.8 12 6
3.65 1.8 12 6
3.45 1.7 12 5
3.00 1.6 11 5
3.50 1.7 12 5
3.50 1.7 12 5
3.65 1.7 12 5
6.35 2.4 17 8
TOTAL 31.5 201 100
BEAM (B-2)
BEAM LENGTH TIE WIRE 16mm DIA. 10mm DIA.
2.50 0.8 7 5
4.00 1 8 6 26.30
3.50 0.5 7 5
1.50 0.7 5 4
1.50 0.7 5 4
3.65 0.5 7 5
3.65 0.5 7 5
1.50 0.7 5 4
2.50 0.8 5 5
2.00 0.8 7 5
TOTAL 7 63 48
BEAM (B-3)
BEAM LENGTH TIE WIRE 16mm DIA. 10mm DIA.
1.50 0.7 4 4
1.50 0.7 4 4
TOTAL 1.4 8 8
ROOF BEAM (R-B)
BEAM LENGTH TIE WIRE 16mm DIA. 10mm DIA.
3.04 0.9 6 10 84.28
3.04 0.9 6 10
3.45 1 7 5
5.10 1.2 9 7
5.10 1.2 9 7
5.10 1.2 9 7
5.10 1.2 9 7
4.90 1.2 9 7
4.90 1.2 9 7
3.65 1 8 6
6.35 1.4 11 8
6.35 1.4 11 8
6.35 1.4 11 8
2.90 0.9 6 10
3.45 1 7 5
3.85 1 8 6
1.35 0.7 4 4
1.35 0.7 4 4
5.10 1.2 9 7
3.85 1 8 6
TOTAL 21.7 160 139
COLUMN C-1 0.25x0.4
HEIHGT TIE WIRE 16mm DIA. 10mm DIA.
1.90 5.3 44 47
3.20 6.8 88 60
3.20 6.8 88 60
COLUMN C-2 0.2x0.4
HEIHGT TIE WIRE 16mm DIA. 10mm DIA.
1.90 1 6 8
3.20 1.3 12 10
COLUMN C-3 0.3x0.3
HEIHGT TIE WIRE 16mm DIA. 10mm DIA.
1.90 1 4 8
3.20 1.3 8 11
63.88