Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INTRODUCTION
1. DISPUTES
for the parties to predict and deal in advance with every eventuality.
It is for this reason that all of the standard form Contracts used
and provide mechanisms for dealing with those claims once they
arise.
Contractual mechanisms.
claim has arisen, whether that right to claim persists and how,
presuming that the claim has survived the claiming mechanism set
Most claims can, will and should be dealt with and disposed of
When faced with any claim the starting off point has to be the actual
This is, of course, stating the obvious, but it does bear repeating – in
Contracts.
standard terms and conditions but also all of the other documents
can imply certain conditions into Contracts which means that there
PRIORITY OF DOCUMENTS
provisions the Contract itself will almost invariably set out a priority list
clause 1.3.
As stated when dealing with any claim the first port of call must be the
Contract itself.
CLAIMS AND DISPUTES
As already stated not all claims will lead to dispute – most of them will
be quite satisfactorily dealt with under the terms of the Contract itself.
claim under the Contract – whether for payment, for time, for
STAGES OF CLAIM
pre tender, will be paid for exactly in accordance with the payment
lead to disputes.
TRADITIONAL APPROACH TO CLAIMS UNDER THE CONTRACT
GDLA forms of Building Contract or the IEI form for Civil Engineering
Works. All of these forms of Contract provide that the Works will be
requirements, will be carried out within the scheduled time period and
Each of the Contracts also however makes provision for the fact and
payment and even that the Employer may elect to omit a proportion
Each of the Contracts vest responsibility for dealing with these issues
as and when they arise in the Contract Administrator (being either the
The Contracts will also determine a means whereby these claims can
dispute arises.
evaluate the full extent of all claims which will then fall to be
with as they arise during the life of the Contract and that both the
Employer and the Contractor are fully apprised of the value and
reducing risk and exposure. The practice, under the traditional forms
Contracts was so that the Government could procure cost and time
For this reason the new Government Forms of Contract introduce not
those which arise under the traditional form of Contract (with some
with by the Contractor in the first instance and then by the Contract
Clause 9 of the Contract deals with time and Clause 10 with claims
The effect of this section is that all Contractor claims for time or
PROCEDURES
(i.e. RIAI / GDLA/ IEI forms of Contract) failure to comply strictly with
either Contractual procedures or with time limits set out in the said
under the terms of the Contract. Apart from this one exception the
other side.
claim and failed within a further 20 days to give the full and detailed
particulars specified in the Contract then he will lose the right to claim
satisfy this burden of proof his claim would fail from the outset of the
part of the courts is to look at the terms of the contract which the
parties actually entered into, and apply those terms, even though the
ensure that the Contractor has complied with the provisions of clause
10.3. A dispute will arise between the parties where the Contractor
contends that he has complied with the procedure and the Employer
complied with (to the extent that this is a necessary pre condition) the
whether or not the principal of the claim is acceptable under the terms
where these are pre conditioned, and assuming that the Contract
question which arises is to decide the true value of the claim being
be evaluated.
All of the standard forms set out events which, should they occur, will
Again with a view to obtaining the stated objective of time and cost
impact. Under the new Government forms any claim for time is
in section 10.
sums due to the Contractor. The most common forms of set off in
The other contra or set off which an Employer might claim during the
Contractor to carry out the Works and claims the costs of that
dispute.
programme.
OTHER DISPUTES
other party alleges a failure on the part of the other party to deal with
with its terms. The allegation would be that the failure to ensure the
where one party purports to terminate the contract, and the other
technically compliant.
parties can arise and it is now appropriate to review how the various
Contracts direct the parties to deal with those disputes. Again – the
that a dispute has arisen is to check the specific terms of the dispute
If any of the standard form contracts have been used – each contains
Every dispute whether under the new form or under the traditional
other setting out the issue between them and the matter which is to
Conciliation or Arbitration.
CONCILIATION – is a facilitated negotiation with the added facility
that at the end of the process, if the parties cannot reach agreement
The procedure under the new Government form is very specific and
issues directions not only to the parties but also to the Conciliator
Contract.
the rules devised by the appointing authority whether the RIAI or the
IEI and under the new Government forms are the new Arbitration