Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
S
tructural engineer Cary Kopczynski once “THERE ARE
penned a prediction: “There may come a day APPLICATIONS
in the not-too-distant future when concrete FOR STEEL FI-
building structures will commonly be rein- BER THROUGH-
forced with a combination of steel fibers and OUT THE
steel reinforcing bar. Rebar requirements SHEAR WALL.”
could be reduced, perhaps significantl .” He —CARY
wrote “Beyond Rebar: A Revolution in Concrete” for KOPCZYNSKI,
the Seattle Daily Journal of Commerce in April 1994. ENGINEER
But the not-too-distant future came and went with-
out a concrete revolution. And the 40-year veteran of
earthquake engineering, who practices mostly on the
West Coast, still is making the same prediction about
reinforced concrete dosed with steel fibers as rebar
decongestants. “Looking downstream, there are ap-
plications for steel fiber throughout the shear wall,”
says Kopczynski, CEO of the 30-year-old Bellevue,
Wash., firm that bears his name. “That’s still a way off.”
In quake-prone areas, rebar congestion has long be-
deviled contractors. Kopczynski’s solution—adding high-
strength wire reinforcement—enhances ductility and shear
strength, allowing for less rebar. That, in turn, increases
constructibility, productivity and material performance.
Kopczynski’s problem: The buildings sector, in ad-
dition to having a general aversion to risk and innova-
tion, “is set up to work with rebar,” says Kopczynski.
And in seismic zones, rebar fabricators and installers
typically don’t like wire in any shape or form.
That hasn’t deterred Kopczynski. About 13 years
ago, tired of hitting his head against a “shear wall” on
the topic of steel-fibe -reinforced concrete (SFRC) in
PHOTOS COURTESY OF CARY KOPCZYNSKI & CO.
core. Workers currently are building the subgrade levels. SFRC link beam. dosage to a pumpable 150 lb per cu yd of concrete.
LSE’s general contractor, which is self-performing
Drawbacks concrete and vertical-element formwork under a
Kemper and its LSE team support future use of CKC’s $600-million contract, says SFRC link beams speeded up
beams, with caveats. “There are a few drawbacks,” says the job. “With diagonal bars in the link beams, we would
Johnny Luttrull, an associate with HKS, LSE’s archi- not have been able to maintain the schedule,” says Alan
tect. “SFRC requires building-official approval and Kniffin, project executive for GLY Construction.
bucketing [due to its density], and the steel-fiber cost The SFRC system, with 3-cu-yd link beams, allowed
is high due to a single-source supply.” for a five-day floor cycle, instead of six, which sliced two
Eyes wide open, Kopczynski is working to eliminate COVER STORY months off the schedule of the 42-story North Tower,
MATERIALS
the drawbacks. More research—now underway—will a hotel-residential high-rise with a cast-in-place rein-
32 ENR September 26/October 3, 2016 enr.com
More Straightforward
Ironworkers led with link beam and wall rebar. Tony
Gerde, LSE project superintendent for Harris Rebar-
forced-concrete structure and post-tensioned slabs. SCALED UP Central Steel, calls CKC’s approach “more straightfor-
The tower, whose lower three floors are set to open Without the SFRC ward” than any Harris has seen. It made rebar installa-
link beams in
in March, with the rest opening in August, has fiv the cores of the tion “faster and easier and helped free up crane time,”
3-ft-wide by 2-ft-deep link beams per floor—four in Lincoln Square typically needed to pick diagonal bars, says Gerde.
Expansion’s
the core and one in a separate shear wall. Compressive 31-story office Mike Dolder, senior principal of Mayes Testing
strength is 8,500 psi. tower (above) and Engineers Inc., which inspected rebar placement and
42-story residen-
LSE’s South Tower, a 31-story office building, has tial building, the tested samples of the concrete, is another fan. “Less
a steel frame with composite metal decking and a con- contractor would rebar congestion makes our job easier,” he says. “The
crete core. There are five link beams per floor until the not have been strength tests were fine, and the mix performed well.”
able to meet its
20th floor and two per floor in a smaller core above schedule. After the rebar, workers installed steel-mesh screens
that. Beams are typically 2.5 ft wide by 3 ft deep. at each end of the beam to prevent the fibrous mix from
GLY built the core to level 20 before starting the flowing into the wall area. Formwork followed.
steel because steel goes up faster. If not for CKC’s Then, crews moved the fibrous mix, trucked about
beams, GLY would have had to delay the steel another 15 minutes from Cadman’s batch plant, into the low-
day per floo . The tower is set to open in January. slump bucket, which was lifted by crane.
GLY embraces CKC’s beams. But its list of disrup- Next, crews maneuvered the bucket into position
tions caused by them is longer than Luttrull’s. Until so workers could coax the mix into place, using shovels
further notice, all fiber jobs are limited to the wire and and vibration. It took seven to 10 minutes to cast each
PHOTO COURTESY OF KEMPER DEVELOPMENT CO.
dosage tested in 2009. The lack of competition for wire 3-cu-yd beam.
did increase the mix cost—$735 per cu yd compared Then, other crews pumped the wall concrete to
to $135 for self-consolidating concrete (SCC) alone, either side of the SFRC beam. A finished beam looks
says GLY. But the expenses were offset by eliminating no different from any other.
180 tons of rebar and associated labor. On the 970 Denny job, all 386 link beams will con-
The job contains 168,300 lb of wire in 841 cu yd of tain SFRC. Instead of a mock-up, the team decided to
concrete. GLY says it kept a “continual watch” on wire use the below-grade link beams, which typically do not
enr.com September 26/October 3, 2016 ENR 33
For CKC, fibrous beams take extra time and effort, structural engineer’s experience also counted.
so far unremunerated, especially during plan review. COVER STORY The design had to match the test specimens’ fibe
MATERIALS
Until SFRC—now used most often for crack control in dosage, span-to-depth (aspect) ratio and wire tests. The
34 ENR September 26/October 3, 2016 enr.com
ect is concerned, we embrace this technology,” says Kopczynski says he hasn’t forgotten his decades-old
Schrader. “We think it might be a better system for dream of expanding the use of fibrous concrete to shear
seismic resistance, resulting in less, more evenly dis- walls, column-beam joints and other elements.
tributed damage, and we would support having it in- “Seismic design is largely about maximizing shear
troduced into the code.” strength and ductility,” he says, adding, “Fibrous con-
But until SFRC link beams are in the code, CKC crete does both.” n
enr.com September 26/October 3, 2016 ENR 35