Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
NCRMP-AF/B-W/AP/MPCS/ PRED/03/Rambilli/005
PACKAGE NO :
TYPE-I 7.50 T
Estimate Cost : Rs. 196.00Lakhs
Grant : NCRMP (Additional Finance)
Circle VISAKHAPATNAM
Division VISAKHAPATNAM
Subdivision Yellamanchilli
Mandal Rambilli
Asst. Exe.Engineer
PIU Yellamanchilli
DETAILED ESTIMATE
Package NCRMP-AF/B-W /AP/MPCS/PRED/
03/Rambilli/006
TYPE-I 7.50 T
Est. Cost Rs.: Rs. 196.00Lakhs
CIRCLE : VISAKHAPATNAM
DIVISION : VISAKHAPATNAM
SUB DIVISION : Yellamanchilli
MANDAL : Rambilli
SPECIFICATION REPORT
1. General: It is proposed to Construct Cyclone shelter ( TYPE - II) at VADAPALEM and the
work Sanctioned under NCRMP Phase-II and Vide Proceeding G.O.R.T. No. 127 Dt: 28-08-2015
Dt of Revenue (Disaster Management-V-SPIU) Department, Hyderabad.
2. Type of structure: The structure is designed for Stilt + Two Floor with R.C.C columns and
beams. The analysis and design of frames are done by STAAD - PRO 2008. The structural
designs based on limit state method using tables and charts of S.P - 16 a
3. Foundations: The S.B.C of Soil is adopted as per Soil investigation report enclosed. Open
Isolated footings, Combined & Strip footings are provided
ii) 200mm thick FAL G Bricks are proposed in CM (1:6) prop for External & internal Walls and
100mm thick partition walls are proposed in C.M (1:4) prop
iii) Doors :Sal wood Frame with Solid bond wood block board type Flush shutter, Windows:
Powder coated Aluminium Sliding windows, Ventilators: Sal wood Frame & Safety Rods with
Glass Louvers are Provided.
iv) Plastering: a) External :In two coats I.e 1st coat 16mm thick in C.M (1:5) prop and 2nd coat
4mm thick in C.M (1:3) prop using Recron 3S. b) Internal : 12mm thick in two coats inside
with a base coat of 8mm thick in CM(1:5) prop and top coat of 4m
v)All External and internal walls and celling paints are proposed with Plastic emulsion Paint
Grade I in two coats of approved brand and colour over primer coat
vi) Flooring with 40mm thick Cement Concrete in CC (1:1 1/2 : 3 ) prop. with neat cement
plastering on top is provided for stilt floor.
vii)Flooring with Vitrified Tiles 8 mm thick set over base coat of CM (1:8) over already laid CC
bed / RCC Roof Slab for upper floors
x) Dadooing to walls with a glazed coloured tiles of approved colour over a base coat of
C.M(1:5)prop. 12mm thick is provided for toilets up to height of 2.10 m.
xi) Weather proof course is proposed with 20mm thick in C.M (1:3) prop with water proof
compound at one kg per one bag of cement and Recron 3S fibre.
5. Water supply & Plumbing sanitary items of standared make are proposed as per SSR - 14-15
6. Electrical items including ceiling fans,tube lights, exhaust fans are proposed in the estimates
as per SSR 14-15
ii) VAT @ 5%
8. Rates: The Data rates adopted in the estimate are based on Common Standard Schedule of
Rates for all Engineering Departments for the year 2014 - 2015 . The rate for cement is adopted
as Rs 5300 /- per M.T. and Steel Fe - 500 HYSD as Rs. 40000/- per M.T.as per August 2015
Communicated rates.
16626839.80
DPR charges 20000.00
401688.2667
0.024159027
2453159.00 1.20
19079998.80
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
Cyclone Shelter (Type - II)
Detailed Estimate - Stilt Floor
S. Measurement Rate Per Amount
Description of Item No Qnty Unit
No Length Width Height
1 Earth work excavation for foundations
(Mechanical Means) for buildings in ordinary soils
and depositing on bank for all lifts and with an
initial lead of 10m and up to 3m depth including
all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and
overheads & contractors profit complete for
finished item of work excluding dewatering
charges etc., as per SS 20 B (APSS 308).
a) Footings
F1 - 1st Footing 1 x 1 2.40 2.20 0.25 1.32
F1 - 2nd Footing 1 x 1 0.80 0.60 0.05 0.02
F2 - 1st Footing 1 x 1 2.80 2.60 0.25 1.82
F2 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F3 - 1st Footing 1 x 1 2.70 2.50 0.25 1.69
F3 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F4 - 1st Footing 1 x 1 3.60 3.40 0.38 4.59
F4 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F5 - 1st Footing 1 x 1 3.50 3.30 0.38 4.33
F5 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F6 - 1st Footing 1 x 1 2.70 2.50 0.25 1.69
F6 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F7 - 1st Footing 1 x 1 2.60 2.40 0.25 1.56
F7 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F8 - 1st Footing 1 x 1 2.40 2.20 0.25 1.32
F8 - 2nd Footing 1 x 1 0.80 0.60 0.08 0.04
F9 - 1st Footing 1 x 1 2.10 1.90 0.25 1.00
F9 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F10 - 1st Footing 1 x 1 2.80 2.60 0.25 1.82
F10 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F11 - 1st Footing 1 x 1 3.45 2.60 0.35 3.14
F11 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F12 - 1st Footing 1 x 1 2.85 2.70 0.25 1.92
F12 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F13 footing (Combined footing) 1 x 1 7.73 2.90 0.25 5.60
F14 footing (Combined footing) 1 x 1 7.44 2.80 0.25 5.21
F15 - 1st Footing 1 x 1 2.80 2.60 0.25 1.82
F15 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F16 - 1st Footing 1 x 1 2.80 2.60 0.25 1.82
F16 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F17 - 1st Footing 1 x 1 2.70 2.50 0.25 1.69
S. Measurement Rate Per Amount
Description of Item No Qnty Unit
No Length Width Height
F17 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F18 - 1st Footing 1 x 1 2.85 1.85 0.25 1.32
F18 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F19 - 1st Footing 1 x 1 2.80 2.60 0.25 1.82
F19 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F20 - 1st Footing 1 x 1 3.20 3.00 0.30 2.88
F20 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F21 - 1st Footing 1 x 1 3.00 2.80 0.25 2.10
F21 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F24 - 1st Footing 1 x 1 2.70 2.50 0.25 1.69
F24 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F25 - 1st Footing 1 x 1 2.80 2.60 0.25 1.82
F25 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F26 - 1st Footing 1 x 1 2.80 2.60 0.25 1.82
F26 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F27 - 1st Footing 1 x 1 2.85 1.85 0.25 1.32
F27 - 2nd Footing 1 x 1 0.80 0.60 0.13 0.06
F28 - 1st Footing 1 x 1 2.60 2.40 0.25 1.56
F28 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F29 - 1st Footing 1 x 1 3.00 2.80 0.28 2.31
F29 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F30 - 1st Footing 1 x 1 3.00 2.80 0.25 2.10
F30 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F31 - 1st Footing 1 x 1 3.10 2.90 0.28 2.47
F31 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F32 - 1st Footing 1 x 1 2.90 2.70 0.25 1.96
F32 - 2nd Footing 1 x 1 0.80 0.60 0.15 0.07
F33 - 1st Footing 1 x 1 2.70 2.50 0.25 1.69
F33 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F34 - 1st Footing 1 x 1 2.70 2.50 0.25 1.69
F34 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F35 - 1st Footing 1 x 1 2.60 2.40 0.25 1.56
F35 - 2nd Footing 1 x 1 0.80 0.60 0.10 0.05
F36 - 1st Footing 1 x 1 2.45 1.95 0.25 1.19
F36 - 2nd Footing 1 x 1 0.80 0.60 0.05 0.02
Footings for ramp columns - 1st Footing 1 x 14 2.40 2.20 0.25 18.48
Footings for ramp columns - 2nd Footing 1 x 14 0.80 0.60 0.05 0.34
Add for Variations 5.69
Total Qty. 100.00 Cum 9160.85 1 Cum 916085.00
b) Lintels
D2 1 x 3 1.35 0.23 0.23 0.21
D3 1 x 5 1.05 0.23 0.23 0.28
Grill Shutter @ DG room 1 x 1 4.60 0.23 0.23 0.24
Grill Shutter @ stair case 1 x 1 4.00 0.23 0.23 0.21
Add for Variations 0.06
Total Qty. 1.00 Cum 11325.10 1 Cum 11325.00
a) Roof Beams
Long Beams B1 - B8 1 x 1 25.86 0.30 0.28 2.17
Long Beams B9 - B16 1 x 1 25.86 0.30 0.28 2.17
Long Beams B17 - B24 1 x 1 25.86 0.30 0.28 2.17
Long Beams B25 - B31 1 x 1 23.63 0.30 0.28 1.98
Short Beams B32 - B33 - B34 1 x 3 13.25 0.30 0.38 4.53
Short Beams B35 - B36 - B37 1 x 3 13.25 0.30 0.38 4.53
Short Beams B38 1 x 1 5.41 0.30 0.38 0.62
Short Beams B39 1 x 1 5.41 0.30 0.38 0.62
Short Beams B40 1 x 1 5.41 0.30 0.38 0.62
Short Beams B41 1 x 1 5.41 0.30 0.38 0.62
Short Beams B42 1 x 1 5.41 0.30 0.38 0.62
Short Beams B43 1 x 1 5.41 0.30 0.38 0.62
Short Beams B44 1 x 1 5.41 0.30 0.38 0.62
Short Beams B45 1 x 1 5.41 0.30 0.38 0.62
Short Beams B46 1 x 1 5.41 0.30 0.38 0.62
Short Beams B47 1 x 1 5.41 0.30 0.38 0.62
Short Beams B48 1 x 1 13.25 0.30 0.28 1.11
Short Beams B49 1 x 1 13.25 0.30 0.28 1.11
Short Beams B50 1 x 1 13.25 0.30 0.28 1.11
Short Beams B51 1 x 1 13.25 0.30 0.38 1.51
Short Beams B52 1 x 1 13.25 0.30 0.38 1.51
Short Beams B53 1 x 1 13.25 0.30 0.38 1.51
Ramp Beams 1 x 13 2.23 0.23 0.35 2.33
Stair case mid landing beam 1 x 1 4.53 0.30 0.50 0.68
Add for Variations 2.38
Total Qty. 37.00 Cum 10294.25 1 Cum 380887.00
(0+0.15)
Staircase Steps 2 x 10 2.0 0.3 /2 0.90
Add for Variations 0.10
Total Qty 1.00 Cum 8071.85 1 Cum 8072
S. Measurement Rate Per Amount
Description of Item No Qnty Unit
No Length Width Height
11 Plain Cement Concrete M 20 grade design mix
using well graded aggregate with maximum
nominal size of aggregates(MSA) of 20mm HBG
metal using Portland Slag Cement confirming to IS
455-1989 and the cement content in the mix to be
not less than 250 kg/cum with maximum water
cement ratio of 0.5, including cost and conveyance
of all materials to site, seignorage charges, steel
centering, machine mixing, concrete laying,
tamping, vibrating, watering, curing and all labour
charges, hire and operational charges of machinery,
water lead charges and including all taxes, bailing
of water.etc., complete for finished item of work
Bed Blocks & Hold Fasts for finished item of
work. (APSS No. 402)
For stilt floor outer wall three sides 1 x 1 53.53 3.18 170.23
Deduction for Ventilators -1 x 5 0.90 0.90 -4.05
Stair case room outside 1 x 2 9.14 - 3.18 58.13
DG Set Room + Watchman + Toilets front side 1 x 1 12.65 3.18 40.23
Deduction for Grill door -1 x 1 4.00 2.40 -9.6
Sitting platform walls 1 x 14 1.66 - 0.50 11.62
Add for Variations 33.44
Total Qty 300.00 Sqm 331.40 1 Sqm 99420.00
For stilt floor outer wall three sides 1 x 1 52.39 2.80 146.69
DG Set Room inside two sides 1 x 1 8.02 2.80 22.46
Deduction for Grill door -1 x 1 4.00 2.40 -9.6
Watch man room 1 x 1 5.64 - 2.80 15.79
Deduction for door D2 -1 x 1 1.05 2.10 -2.21
Toilets inside 1 x 1 4.77 - 2.80 13.34
Deduction for door D2 -1 x 2 1.05 2.10 -4.41
Cross Walls 2 x 3 1.50 - 2.10 18.9
Top of walls 2 x 3 1.50 - 0.12 1.04
Front Wall 2 x 1 4.77 - 2.10 20.01
Deduction for door D2 -1 x 5 1.05 2.10 -11.03
Top of walls 2 x 1 1.50 - 0.12 0.35
Partition wall between Ladies and Gents toilets 1 x 2 3.30 - 2.80 18.48
Stair case room inside 1 x 2 7.61 - 2.80 42.62
S. Measurement Rate Per Amount
Description of Item No Qnty Unit
No Length Width Height
For shelf walls in watchman room 2x 2 0.45 2.10 3.78
Add for Variations 23.79
Total Qty 300.00 Sqm 307.90 1 Sqm 92370.00
a) Flooring
Watch man 1 x 1 3.38 2.50 8.45
Ladies Toilet 1 x 1 3.38 1.92 6.47
Deduction for wall -1 x 1 1.50 0.12 -0.17
Gents Toilet 1 x 1 3.38 2.93 9.90
Deduction for wall -1 x 2 1.50 0.12 -0.35
Add for Variations 5.70
Total Qty 30.00 Sqm 908.55 1 Sqm 27257.00
S. Measurement Rate Per Amount
Description of Item No Qnty Unit
No Length Width Height
Flooring / Treads with polished Tandur stones
slabs of 15 mm thick (457x304 mm) set over base
coat of CM (1:8) over already laid CC bed / RCC
Roof Slab, including neat cement slurry of honey
like consistency spread @ 3.3 kgs per sqm. &
Jointed with neat cement to full depth including
cost and conveyance of all materials like cement
(Portland Slag Cement confirming to IS 455-1989),
sand, and water and flooring stones etc., complete,
including seigniorage charges, labour charges for
dressing of flooring stones etc., complete for
finished item of work. (As per BLD-CSTN)
For Steps
a) Treads
Treads 2 x 10 2.00 0.30 12.00
Landing 1 x 10 4.46 1.50 66.90
Add for Variations 1.10
Total Qty 80.00 Sqm 730.60 1 Sqm 58448.00
Providing skirting to internal walls to 15cm
height/ risers of steps with polished Tandur
stone 15mm thick, length equal to flooring stones,
set over base coat of CM (1:3), 12 mm thick with
cement slurry of honey like consistency spread at
the rate of 3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of matching
shade to full depth, including cost all taxes and
conveyance of all materials like Tandur stone,
cement (Portland Slag Cement confirming to IS
455-1989), sand and water etc., complete including
seigniorage charges, all incidental, operation and
labour etc., complete for finished item of work. (As
per BLD-CSTN)
b) Skirting
Steps and Landing 1x 2 10.57 - - 21.14 Rm 93.65 1 Rm 1980.00
c) Risers
Risers 2 x 10 2- 40.00 Sqm 624.25 1 Sqm 24970.00
a) Skirting
Watch man 1x 1 11.76 - - 11.76
11.76 Rm 90.9 1 Rm 1069.00
S. Measurement Rate Per Amount
Description of Item No Qnty Unit
No Length Width Height
17 Providing dadooing to walls with glazed coloured
tiles 1st quality of size approved by Engineer-in-
Charge set over base coat of CM(1:5) 12mm thick
with cement slurry of honey like consistency
spread at the rate of 3.30kgs per sqm and jointing
with white cement paste mixed with pigment of
matching shade to full depth, including cost of all
materials like tiles, cement, sand and water, all
taxes etc., complete including seigniorage charges
all lbaour charges for all operations complete for
finished item of work. (As per BLD-CSTN)
Sump
Sump Base slab
Side walls 1x 1 4.00 2.50 10.00
Haunches 1x 1 13.00 1.20 15.60
Septic tank 1x 1 13.00 0.21 2.76
Base slab
Side walls 1x 1 4.00 1.40 5.60
Ramp 1x 1 10.80 1.30 14.04
Total Qty. 1x 1 53.47 2.00 - 106.94
Add for Variation 5.06
160.00 Sqm 365.50 1 Sqm 58480.00
8672788
a) Columns
Column C1 1 x 21 0.30 0.50 2.80 8.82
Column C2 1 x 2 0.30 0.50 2.80 0.84
Column C3 1 x 1 0.30 0.50 2.80 0.42
Column C4 1 x 2 0.30 0.50 2.80 0.84
Column C5 1 x 1 0.30 0.50 2.80 0.42
Column C6 1 x 1 0.30 0.50 2.80 0.42
Column C7 1 x 1 0.30 0.50 2.80 0.42
Column C8 1 x 1 0.30 0.50 2.80 0.42
Column C9 1 x 1 0.30 0.50 2.80 0.42
Column C10 1 x 1 0.30 0.50 2.80 0.42
Column C11 1 x 1 0.30 0.50 2.80 0.42
Column C12 1 x 1 0.30 0.50 2.80 0.42
Column C13 1 x 2 0.30 0.50 2.80 0.84
Add for Variation 0.33
Total Qty. 15.45 Cum 10933.70 1 Cum 168926
b) Lintels
Door M.D 1 x 1 2.50 0.20 0.23 0.12
D1 1 x 9 1.66 0.20 0.23 0.69
D2 1 x 3 1.21 0.20 0.15 0.11
D3 1 x 11 0.90 0.20 0.15 0.3
Windows W 1 x 14 1.66 0.20 0.23 1.07
W2 1 x 3 1.36 0.20 0.23 0.19
Ventilators V 1 x 11 0.90 0.20 0.15 0.3
Add for Variation 0.33
Total Qty. 3.11 Cum 11325.10 1 Cum 35221
S. Measurement Rate Per Amount
Description of Item No QuantityUnit
No Length WidthHeight
2 VRCC M30 Grade Design mix using well graded
aggregate with maximum nominal size of
aggregate(MSA) of 20mm HBG machine crushed and
duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-
cement ratio of 0.45, including Super plasticizer
admixture IS marked as per 9103-1999 (as approved
by Engineer) including cost and conveyance of all
materials to site, seignorage fee, machine mixing,
concrete laying, tamping, centering using Steel
scaffolding pipes , jack props , wallers , Foot plates ,
brackets , steel centering plates etc., weigh batching,
vibrating, watering, curing and all labour charges for
all operations, all taxes, hire and operational charges of
machinery and water lead charges etc., but excluding
cost of steel and its fabrication complete for finished
item of work for RCC Slabs and Beams (As per BLD-
CSTN)
a) Roof Beams
External Columns 1 x 5 13.18 0.30 0.38 7.51
Internal Columns 2 x 4 5.34 0.30 0.38 4.87
Cross Walls 3 x 1 25.86 0.30 0.28 6.52
Cross Walls 1 x 1 23.63 0.30 0.28 1.98
Stair case 1 x 35 0.30 0.30 0.28 0.88
Mid Landing Staircase 1 x 1 4.53 0.30 0.30 0.41
Add for Variation 0.83
Total Qty. 23.00 Cum 10294.25 1 Cum 236768
b) Slab(120mm thickness)
1 x 1 26.39 13.78 - 363.65
Deduct for Stair case room 1 x 1 5.11 4.00 - -20.44
Add for Variation 31.79
Total Qty. 375.00 Sqm 1208.60 1 Sqm 453225
e) Slab(175mm thickness)
Grid line between B3& B4 to F3&F4 1 14.10 4.53 63.80
Ramp slab
Section - AB 1 14.625 1.80 26.33
Section - CD 1 18.775 1.80 33.80
Stright portion 1 4.16 1.80 7.49
Add for variations 8.58
Total Qty. 140.00 Sqm 1569.55 1 Sqm 219737
c) Slab(150mm thickness)
Landing 1 x 1 4.46 1.50 - 6.69
1st flight 1 x 1 3.42 2.23 - 7.63
2nd flight 1 x 1 3.42 2.23 - 7.63
Add for variations 4.05
Total Qty. 26.00 Sqm 1398.40 1 Sqm 36358
S. Measurement Rate Per Amount
Description of Item No QuantityUnit
No Length WidthHeight
3 PCC M30 Grade Design mix using well graded
aggregate with maximum nominal size of
aggregate(MSA) of 20mm HBG machine crushed and
duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-
cement ratio of 0.45, including Super plasticizer
admixture IS marked as per 9103-1999 (as
approved by Engineer) including cost and
conveyance of all materials to site, seignorage fee,
concrete laying, tamping, including steel centering,
shuttering, lift charges, weigh batching/machine
mixing, vibrating, watering, curing and all labour
charges for all operations, all taxes, hire and
operational charges of machinery and water lead
charges etc., but excluding cost of steel and its
fabrication complete for finished item of work for
Steps. (As per BLD-CSTN)
Steps
20 x 1/2 2.00 0.30 0.15 0.90
Add for variations 0.10
Total Qty. 1.00 Cum 8125.05 1 Cum 8125
Ramp slab
Section - AB 1 14.625 0.90 13.16
S. Measurement Rate Per Amount
Description of Item No QuantityUnit
No Length WidthHeight
Section - CD 1 18.775 0.90 16.90
Stright portion 1 4.16 0.90 3.74
Add for rounding off 0.05
Add for Variations 17.51
Total Qty. 200.00 Sqm 972.13 1 Sqm 194426
Inside Ceiling
Ladies toilet 1 x 1 3.38 - 5.00 16.90
Sick Room 1 x 1 3.02 - 5.00 15.10
Store Room 1 x 1 3.02 - 5.00 15.10
Gents Hall 1 x 1 13.00 - 5.00 65.00
Gents Toilet 1 x 1 3.38 - 5.00 16.90
Ladies Hall-1 1 x 1 6.27 - 5.00 31.35
Ladies Hall-2 1 x 1 5.77 - 5.00 28.85
Kitchen 1 x 1 5.00 - 5.00 25.00
Corridor 1 x 1 21.20 - 2.50 53.00
PHC Toilet 1 x 1 1.80 - 2.50 4.50
At Entrance 1 x 1 2.50 - 2.50 6.25
Columns sides 10 x 2 0.27 - 3.18 17.17
Beam sides 6 x 2 4.74 - 0.38 21.61
Add for Lofts ,Sunshades,Lofts, Shelves etc 93.27
Total Qty. 410.00 Sqm 316.75 1 Sqm 129867
a) Flooring
Sick & Store room 1 x 2 3.02 - 5.000 30.20
Gents Hall 1 x 1 13.00 - 5.000 65.00
Ladies Hall-1 1 x 1 6.27 - 5.000 31.35
Ladies Hall-2 1 x 1 5.77 - 5.000 28.85
S. Measurement Rate Per Amount
Description of Item No QuantityUnit
No Length WidthHeight
Kitchen 1 x 1 5.00 - 5.000 25.00
Corridor 1 x 1 21.20 - 2.500 53.00
Corridor entrance 1 x 1 2.50 - 2.500 6.25
Add for Variations 10.35
Total Qty. 250.00 Sqm 908.55 1 Sqm 227138
a) Skirting
Sick Room & Store Room 1 x 2 16.04 - - 32.08
Gents Hall 1 x 1 36.00 - - 36.00
Corridor alround 1 x 1 47.37 - - 47.37
Ladies Hall-1 1 x 1 22.54 - - 22.54
Ladies Hall-2 1 x 1 21.54 - - 21.54
Kitchen 1 x 1 20.00 - - 20.00
Add for Variations 10.47
190.00 Rm 90.90 1 Rm 17271
a) Treads
Steps treads 2 x 10 2.00 - 0.300 12.00 Sqm 730.60 1 Sqm 8767
S. Measurement Rate Per Amount
Description of Item No QuantityUnit
No Length WidthHeight
Providing skirting to internal walls to 15cm height/
risers of steps with polished Tandur stone 15mm
thick, length equal to flooring stones, set over base
coat of CM (1:3), 12 mm thick with cement slurry of
honey like consistency spread at the rate of 3.30 kgs
per sqm and jointed with white cement paste mixed
with pigment of matching shade to full depth,
including cost all taxes and conveyance of all materials
like Tandur stone, cement (Portland Slag Cement
confirming to IS 455-1989), sand and water etc.,
complete including seigniorage charges, all incidental,
operation and labour etc., complete for finished item of
work. (As per BLD-CSTN)
1 x 2 3.42 - - 6.84
Mid landing 1 x 1 4.00 - - 4.00
Total Qty. 10.84 Rm 343.35 1 Rm 3722
S. Measurement Rate Per Amount
Description of Item No QuantityUnit
No Length WidthHeight
24 Painting to new wood work and flush shutters with
lappam finish , over a primary coat and painting two
coats of synthetic enamel paint 1st grade of
approved brand and shade including cost and
conveyance of all materials to site cost of primer coat
and all labour charges etc. complete including applying
sand paper on lappam coats for neat finish including
sales & other taxes on cost of all materials
etc.complete (APSS No.1200, 1207 & 1211) in all
floors
a) Columns
Column C1 1 x 21 0.30 0.50 2.80 8.82
Column C2 1 x 2 0.30 0.50 2.80 0.84
Column C3 1 x 1 0.30 0.50 2.80 0.42
Column C4 1 x 2 0.30 0.50 2.80 0.84
Column C5 1 x 1 0.30 0.50 2.80 0.42
Column C6 1 x 1 0.30 0.50 2.80 0.42
Column C7 1 x 1 0.30 0.50 2.80 0.42
Column C8 1 x 1 0.30 0.50 2.80 0.42
Column C9 1 x 1 0.30 0.50 2.80 0.42
Column C10 1 x 1 0.30 0.50 2.80 0.42
Column C11 1 x 1 0.30 0.50 2.80 0.42
Column C12 1 x 1 0.30 0.50 2.80 0.42
Column C13 1 x 2 0.30 0.50 2.80 0.84
Add for Variations 0.38
Total Qty. 15.50 Cum 11334.25 1 Cum 175681
b) Lintels
D1 1 x 8 1.66 0.20 0.23 0.61
D2 1 x 2 1.21 0.20 0.23 0.11
D3 1 x 11 0.90 0.20 0.15 0.3
Windows W 1 x 13 1.66 0.20 0.23 0.99
V 1 x 2 1.35 0.20 0.23 0.12
Ventilators V 1 x 11 0.90 0.20 0.15 0.3
Add for Variations 0.76
Total Qty. 3.19 Cum 11670.85 1 Cum 37230
S. Measurement Rate Per Amount
Description of Item No Quantity Unit
No Length Width Height
2 VRCC M30 Grade Design mix using well graded
aggregate with maximum nominal size of
aggregate(MSA) of 20mm HBG machine crushed and
duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be not
less than 325 Kg/cum, with maximum water-cement
ratio of 0.45, including Super plasticizer admixture IS
marked as per 9103-1999 (as approved by Engineer)
including cost and conveyance of all materials to site,
seignorage fee, machine mixing, concrete laying,
tamping, centering using Steel scaffolding pipes , jack
props , wallers , Foot plates , brackets , steel centering
plates etc., weigh batching, vibrating, watering, curing
and all labour charges for all operations, all taxes, hire
and operational charges of machinery and water lead
charges etc., but excluding cost of steel and its
fabrication complete for finished item of work for RCC
Slabs and Beams (As per BLD-CSTN)
a) Roof Beams
1 x 5 13.18 0.30 0.38 7.51
2 x 4 5.34 0.30 0.38 4.87
4 x 1 25.79 0.30 0.28 8.67
Add for Variations 0.95
Total Qty. 22.00 Cum 10569.85 1 Cum 232537
b) Slab(120mm thickness)
1 x 1 26.39 13.78 - 363.65
Deduct staircase room 1 x 1 5.11 4.00 - -20.44
Add for Variations 16.79
Total Qty. 360.00 Sqm 1240.60 1 Sqm 446616
c) Slab(150mm thickness)
Landing 1 x 1 4.46 2.23 - 9.95
1st & 2nd flight 1 x 2 3.42 2.23 - 15.25
Add for Variations 0.30
Total Qty. 25.50 Sqm 1433.85 1 Sqm 36563
Steps
For Steps 2 x 10x1/2 2.00 0.30 0.15 0.90
Add for Variations 0.10
Total Qty. 1.00 Cum 8231.15 1 Cum 8231
S. Measurement Rate Per Amount
Description of Item No Quantity Unit
No Length Width Height
4 Plain Cement Concrete M 20 grade design mix using
well graded aggregate with maximum nominal size of
aggregates(MSA) of 20mm HBG metal using Portland
Slag Cement confirming to IS 455-1989 and the
cement content in the mix to be not less than 250
kg/cum with maximum water cement ratio of 0.5,
including cost and conveyance of all materials to site,
seignorage charges, steel centering, machine mixing,
concrete laying, tamping, vibrating, watering, curing
and all labour charges, hire and operational charges of
machinery, water lead charges and including all taxes,
bailing of water.etc., complete for finished item of work
for Bed blocks (As per BLD-CSTN)
Inside Ceiling
S. Measurement Rate Per Amount
Description of Item No Quantity Unit
No Length Width Height
Gents Toilet 1 x 2 3.38 - 5.000 33.80
Sick & Store Room 1 x 2 3.02 - 5.000 30.20
Gents Hall 1 x 1 15.23 - 5.000 76.15
Ladies Hall-1 1 x 1 6.27 - 5.000 31.35
Ladies Hall-2 1 x 1 11.00 - 5.000 55.00
Corridor 1 x 1 25.33 - 2.500 63.33
Stair Case Landing 1 x 1 4.00 - 2.000 8.00
1st & 2nd flight 1 x 2 3.42 - 2.000 13.68
Columns side 13 x 2 0.27 - 3.180 22.32
Beam Sides 8 x 2 4.34 - 0.380 26.39
Add for Variations Sunshades,Lofts, shelves 89.78
Total Qty. 450.00 Sqm 345.00 1 Sqm 155250
External plastering 20mm thk. Qty. + Elevation Qty. 370.00 Sqm 126.05 1 Sqm 46639
a) Flooring
Sick room & Store Room 1 x 2 3.02 - 5.000 30.20
Gents Hall 1 x 1 15.23 - 5.000 76.15
Ladies Hall-1 1 x 1 6.27 - 5.000 31.35
Ladies Hall-2 1 x 1 11.00 - 5.000 55.00
Corridor 1 x 1 25.33 - 2.500 63.33
Door D1 1 x 8 1.20 - 0.120 1.15
Stair Case Landing 1 x 1 4.00 - 2.000 8.00
Add for Variations 14.82
Total Qty. 280.00 Sqm 933.65 1 Sqm 261422
a) Skirting
Sick Room & Store Room 1 x 2 16.04 - - 32.08
Gents Hall 1 x 1 40.46 - - 40.46
Ladies Hall-1 1 x 1 22.54 - - 22.54
Ladies Hall-2 1 x 1 32.00 - - 32.00
Corridor alround 1 x 1 55.66 - - 55.66
Deduct Doors D1 1 x 8 1.20 - - -9.60
D2 1 x 2 1.05 - - -2.10
171.04 Rm 90.90 1 Rm 15548
S. Measurement Rate Per Amount
Description of Item No Quantity Unit
No Length Width Height
Providing skirting to internal walls to 15cm height/
risers of steps with polished Tandur stone 15mm
thick, length equal to flooring stones, set over base coat
of CM (1:3), 12 mm thick with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm
and jointed with white cement paste mixed with pigment
of matching shade to full depth, including cost all taxes
and conveyance of all materials like Tandur stone,
cement (Portland Slag Cement confirming to IS 455-
1989), sand and water etc., complete including
seigniorage charges, all incidental, operation and labour
etc., complete for finished item of work. (As per BLD-
CSTN)
a) Skirting
Stair Case Landing 1 x 1 8.00 - - 8.00
2 x 1 0.45 - - 0.90
Steps 2 x 11 2.00 - - 44.00
Total Qty. 52.90 Rm 95.80 1 Rm 5068
b) Risers
Steps 2x2 x 11 0.30 - 0.30 21.78
21.78 Sqm 638.65 1 Sqm 13910
Flooring / Treads with polished Tandur stones slabs of
15 mm thick (457x304 mm) set over base coat of CM
(1:8) over already laid CC bed / RCC Roof Slab,
including neat cement slurry of honey like consistency
spread @ 3.3 kgs per sqm. & Jointed with neat cement
to full depth including cost and conveyance of all
materials like cement (Portland Slag Cement confirming
to IS 455-1989), sand, and water and flooring stones
etc., complete, including seigniorage charges, labour
charges for dressing of flooring stones etc., complete for
finished item of work. (As per BLD-CSTN)
c) Treads
Steps treads 2 x 10 2.00 - 0.300 12.00 Sqm 752.30 1 Sqm 9028
0
S. Measurement Rate Per Amount
Description of Item No Quantity Unit
No Length Width Height
Superintending Engineer Executive Engineer Deputy Exe.Engineer Asst. Exe.Engineer
PR Visakhapatnam PIU Visakhapatnam PIU Yellamanchilli PIU Yellamanchilli
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
Cyclone Shelter (Type - II)
Detailed Estimate - Head Room
P
S. Measurement Rate
Description of Item No Qnty Unit er
No
Length Width Height
1 VRCC M30 Grade Design mix using well graded
aggregate with maximum nominal size of
aggregate(MSA) of 20mm HBG machine crushed and
duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-
cement ratio of 0.45, including Super plasticizer
admixture IS marked as per 9103-1999 (as
approved by Engineer) including cost and
conveyance of all materials to site, seignorage fee,
machine mixing, concrete laying, tamping, centering
using Steel scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering plates etc.,
weigh batching, vibrating, watering, curing and all
labour charges for all operations, all taxes, hire and
operational charges of machinery and water lead
charges etc., but excluding cost of steel and its
fabrication complete for finished item of work for
Columns, Lintels, Water Tanks, RCC Walls in
Buildings. (As per BLD-CSTN)
a) Columns
Head Room and Over Head Tank
C2 1 x 2 0.30 0.50 2.95 0.89
C4 1 x 2 0.30 0.50 2.95 0.89
Upto Water Tank bottom
C2 1 x 2 0.30 0.50 0.20 0.06
C4 1 x 2 0.30 0.50 0.20 0.06
Add for Variations 0.6
Total Qty. 2.50 Cum 11334.25 1 Cum
b) Lintels
D 1 x 1 2.46 0.23 0.23 0.13
Windows W 1 x 1 1.96 0.23 0.23 0.10
Add for Variations 0.17
0.40 Cum 11670.85 1 Cum
P
S. Measurement Rate
Description of Item No Qnty Unit er
No
Length Width Height
2 VRCC M30 Grade Design mix using well graded
aggregate with maximum nominal size of
aggregate(MSA) of 20mm HBG machine crushed and
duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-
cement ratio of 0.45, including Super plasticizer
admixture IS marked as per 9103-1999 (as
approved by Engineer) including cost and
conveyance of all materials to site, seignorage fee,
machine mixing, concrete laying, tamping, centering
using Steel scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering plates etc.,
weigh batching, vibrating, watering, curing and all
labour charges for all operations, all taxes, hire and
operational charges of machinery and water lead
charges etc., but excluding cost of steel and its
fabrication complete for finished item of work for
RCC Slabs and Beams (As per BLD-CSTN)
a) Beams
Head Room Beams @ 12.05 m Level
B1 & B2 2 X 1 3.93 0.30 0.280 0.66
B3 & B4 2 X 1 4.41 0.30 0.380 1.01
Add for Variations 0.33
2.00 Cum 10569.85 1 Cum
Water Tank floor Beams @ 12.65 m Level
B1 & B2 2 X 1 3.93 0.30 0.280 0.66
B3 & B4 2 X 1 4.41 0.30 0.380 1.01
Add for Variations 0.33
2.00 Cum 10569.85 1 Cum
b) Slab(120mm thickness)
Head Room Slab (120mm thick)
Head Room Slab & Water tank top slab 1 x 2 5.93 5.06 - 60.01
Add for Variations 9.99
Total Qty. 70.00 Sqm 1240.60 1 sqm
c) Slab(150mm thickness)
Head Room Slab (150mm thick)
Head Room Slab & Water tank bottom slab 1 x 1 5.34 4.46 - 23.82
Staire case Waist Slab to Water Tank 1 x 1 9.00 0.75 6.75
Add for Variations 4.43
Total Qty. 35.00 Sqm 1433.85 1 sqm
Side wall ( 150mm thk )for Water Tank Over Head Room
1x 1 18.68 1.35 25.22 Sqm 2071.82 1 sqm
P
S. Measurement Rate
Description of Item No Qnty Unit er
No
Length Width Height
3 Masonry work in CM (1:6) prop with Flyash Cement
solid blocks of size 290 x 200 x 140 mm for
manufacturing of flyash solid blocks using flyash of 80
kgs, cement of 15 kgs. Gypsum of 5 kgs. and stone dust
including cost and conveyance of all materials, labour
charges, seiniorage charges, scaffolding and curing etc.,
complete with a compresive streangth not lessthan 50
kg/sqcm for walls for Superstructure Walls.
Head Room
Parapet 1 x 1 77.02 - 2.030 156.35
Head Room 1 x 1 24.82 - 2.750 68.26
Columns 1 x 1 1.60 - 0.200 0.32
Water Tank alround 1 x 1 19.60 - 1.200 23.52
Deductions :
W 1 x 1 1.20 - 1.200 -1.44
D 1 x 1 2.00 - 2.100 -4.20
Add for Variations 17.19
Total Qty. 260.00 Sqm 365.00 1 sqm
P
S. Measurement Rate
Description of Item No Qnty Unit er
No
Length Width Height
5 Plastering 12mm thick in two coats using portland
slag cement (conforming to IS:455-1989 ) with a
base coat of 8mm thick in CM(1:5) prop and top coat
of 4mm thick in CM (1:3) prop. with dubara sponge
finish including cost and conveyance of all materials
and water to work site, all taxes, seigniorage and all
operational incidental, labour charges such as
scaffolding, mixing mortar lift charges curing etc.,
including using Recron 3S @ 125gms /per 1 bag of
cement in first coat, complete for finished item of
work. for Internal surfaces (As per BLD-CSTN).
1 x 7 11.30 - - 79.10
1 x 1 15.00 - - 15.00
Add for Variations 25.90
Total Qty. 120.00 Rmt 335.40 1 Rmt
P
S. Measurement Rate
Description of Item No Qnty Unit er
No
Length Width Height
PCC M30 Grade Design mix using well graded
aggregate with maximum nominal size of
aggregate(MSA) of 20mm HBG machine crushed and
duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-
cement ratio of 0.45, including Super plasticizer
admixture IS marked as per 9103-1999 (as
approved by Engineer) including cost and
conveyance of all materials to site, seignorage fee,
concrete laying, tamping, including steel centering,
shuttering, lift charges, weigh batching/machine
mixing, vibrating, watering, curing and all labour
charges for all operations, all taxes, hire and
operational charges of machinery and water lead
charges etc., but excluding cost of steel and its
fabrication complete for finished item of work
forHuanches. (As per BLD-CSTN)
28336
4668
Amount
21140
21140
21140
86842
50185
52247
Amount
233353
94900
Amount
19834
12075
32766
Amount
11909
8281
13283
Amount
380
155800
300532
40248
Amount
16462
1225521
Asst. Exe.Engineer
PIU Yellamanchilli
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
WH pit @ 40% of 65 mm metal 0.40 3.00 2.00 2.00 4.80 Cum 999.90 1 Cum
Soak pit @ 20% of brick bats 0.40 2.20 2.20 1.00 1.94 Cum
2.00 Cum 843.60 1 Cum
7) Supply and fixing of SWG pipe of ISI make
conforming to ISI-651, 4" dia (110 mm) including cost
and conveyance of all materials, all taxes labour
charges etc. complete for fininshed item of work.
for Soak pit 2 10.0 20.00 RMT 470.90 1 RMT
6136
4800
9003
6346
1409
1687
9418
38799
Asst. Exe.Engineer
PIU Yellamanchilli
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
TYPE-I 7.50 T
Sanitary & Water Supply Detailed & Abstract Estimate
Measurement
S.No Description of Item No Quantity Unit Rate Amount
Length Width Height
1 Supply & fixing 580mm x 440mm size white virerous orissa pan of Hindware/ Parryware/Neycer make with
attached footrests of approved make confirming to IS 2556 (part - III) with 'P' or 'S' trap, including 10 lit. low level
PVC flusihing system of parryware make confirming to IS 7231 with all internal fittings, CI brackets, 32mm dia
CP flush pipe, 15mm dia 450mm long PVC connerctor, 15mm dia Cp brass strop cock 300 grams of ISI make,
cutting and making good the walls and floors wherever required including cost & conveyance of all material to
work site, all labour charges for all operations for fixing, all taxes etc., complete for finished item of work.
2 Supply & fixing European water closet of I st quality confirming to IS:2556-part-2-1973 of Hindusthan /Neycer
or Parryware make white Glazed with P Trap complete.for finished item of work.
Ground floor 2.00
First floor 3.00
Second floor 0.00
5.00 Nos. 5253.85 26269.00
3 Supplying & Fixing Indian make Flat Back Wash Hand Basin (HSW/Parryware/ Neycer) 1st quality conforming to
IS:2556-Part-4:1972 with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting with parallel pipe
thread conforming to IS:2963-197
Ground floor 3.00
First floor 5.00
Second floor 0.00
8.00 Nos. 2345.49 18764.00
4 Supplying & Fixing white glazed flat back Bowl urinals of size 440 mm x 265 mm x 315 mm with internal flushing
rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to IS:2556-1995
Ground floor 2.00
First floor 3.00
Second floor 0.00
5.00 Nos. 1122.90 5615.00
5 Supply & fixing of tested NP bib taps at all levels of 12.70mm dia of Indian make 300g first quality including cost
& conveyance of all materials, labour charges for finished item of work, and all taxes complete for all floors
6 Supplying and fixing 4" (101.6 mm ) multi floor trap with Jali- UPVC/SWR Pipe fittings of standard make of ISI
Brand (Prince/Sudhakar or any ISI Brand) including fixing in CM1:3 prop. and cost and conveyance of all
materials at site, all taxes complete for finished item of work.
8 Supply & fixing SWG 150x100mm gully trap of 1st class as per IS standards with CI grating and constructing
brick masonry chamber of size 50x35x30cm in CM 1:6 prop. Over CC 1:5:10 prop. Bed of size 50x5x10cm and
plastering 12mm thick in CM 1:4 prop. To both inside & outside surfaces of the brick chamber and fitted with
30x22.5cm CI frame and hinged cover, including cost and conveyance of all material, labour charges, all taxes
etc., complete.
13 Supplying & Fixing 31.75 mm C.P bottle trap (Heavy type) Parryware or equivalent including cost and
conveyance of all materila, all labour charges, and all taxes.
4.00 Nos 534.95 2140.00
14 Supply and Fixing 31.75mm dia PVC flexible waste pipe of 914.4mm length of 1st quality.(SSR No.315)
including cost and conveyance of all materila, all labour charges, and all taxes.
17.00 Nos 30.85 524.00
15 Drilling of bore hole 150 mm dia using machinery etc complete including cost and conveyance of all materila, all
labour charges, and all taxes.
45.00 Mt 355.85 16013.00
16 Providing of PVC casing pipe 160 mm dia of 6 Kg / cm2 including cost and conveyance of all materila, all labour
charges, and all taxes.
45.00 Mt 690.75 31084.00
17 Supply and erecting, ISI mark submersible pumpset of 1.00HP suitable for 4" Bore well. Makes: Kirloskar /
Crompton / CRI / L&T / Texmo / Varsha with high quality water resistant and dynamically balanced bronze
impeller with stainless steel shaft sleeves, pump coupling and pivot of Single phase 250V, 50Hz.. A.C. power
supply copper winding with water proof insulation and high precision strength not to be effected by chemical in
water and suitable bronze bearings with nut and bolts etc., with necessary H-type clamp of suitable size and
strength.
1.00 Nos 20981.14 20981.00
Measurement
S.No Description of Item No Quantity Unit Rate Amount
Length Width Height
Supply of 2.5 Sqmm 3/20 WPSC (Weather Proof Single Core ) ISI Alluminium Wire Finolex / Polycab / Gold
Medal / Million / Payal / Power Flex make for service mains including cost of material and labour charges and
18 taxes etc., complete.
60.00 Rmt 8.74 524.00
Supply & Fixing of D.O.L Starter 250V, Single phase, 50Hz. With SS enclouser comprising of contactor with bi-metalic relay
with necessary push buttons, etc., complete . etc., complete.including cost and conveyance of all materila, all labour charges,
19 and all taxes.
2.00 Nos 925.20 1850.00
20 Manufacture, supply, & delivery of 40mm dia 8kg/sqcm HDPE pipes conforming to IS 4984 - 1995 including transportation to
any where in A.P, excluding specials etc., complete.including cost and conveyance of all materila, all labour charges, and all
taxes.
45.00 Rmt 81.40 3663.00
21 Supply of 3 Core 1.5 Sqmm Flat Copper cable of ISI for Submersible Motors of makes Finolex / Polycab / Gold Medal / Million
/ Payal / Power Flex / Fortune Art make including cost of material and labour charges and taxes etc., complete.
22 Supply and fixing of submersible pump of suitable capacity 0.5 HP for drawing water including cost of labour
for fixing transportation etc complete.
1.00 Nos 7123.35 7123.00
359454.00
Sl. Amount
Qty. Description of Item Rate Unit
No. Rs.
1 320.00 RM Supply and Fixing of 25mm dia 1.5/1.8mm thick Conceld 66.05 RM 21136.00
P.V.C. pipe (ISI MARK) with all accessories including all labour
charges etc., complete for run of mains.
2 160.00 Nos Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant 575.30 Nos 92048.00
(FR) P.V.C. insulated flexible copper cable (ISI MARK) in
existing pipe with 6A (Modular) switch and G I Matel Conceld
box to switch control box including all labour charges etc.(For
light,fan,exhaust fan points )
3 900.00 Rm Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C. 20.10 Rm 18090.00
insulated flexible copper cable in existing pipe for earth
continuity including all labour charges etc., complete.
4 1000.00 Rm Supplying & run of 2 of 2.5 Sqmm 36/0.3mmFR PVC insulated 113.59 Rm 113590.00
flexible copper cable in Existing pipe for mains incl all labour
charges
7 25.00 No Supply and fixing of 6A 3 pin wall plug socket with 6A switch 111.26 Each 2782.00
(Modular) control on a common switch board with earth
continuity including wire leads, earth connections along with all
labour charges etc., complete.
8 12.00 No Supply and fixing of 16A 3pin / 6A 3pin plug socket with 255.93 Each 3071.00
indicator lamp and 16 Amps (Modular) switch and G I Matel
Conceld box to switch control box including all labour charges
etc.
9 18.00 No Supply and Fixing Stepped type electronic Regulator for ceiling 290.13 Each 5222.00
fans 900/1200/1400mm sweep complete erected on existing
board.
10 18.00 No Supply of 1200mm (48") sweep 230V, A.C 50 Hz.Ceiling fan 2420.00 Each 43560.00
with 3 Blades and double ball bearings with all standard
accessories.
11 18.00 No Labour charges for Fixing of Ceiling fan and regulator including 140.59 Each 2531.00
transportation and giving connections with twin core wire,
including cost & conveyance of all material, all labour charges
and all taxes etc., complete.
12 35.00 No Supply and Fixing of 1x36/40W box type tube light luminaire 962.00 Each 33670.00
with Electranic Ballast, tube etc., complete as per IS standards.
Electrical 83
Sl. Amount
Qty. Description of Item Rate Unit
No. Rs.
13 35.00 No Fixing of 36W tube light luminaire on wall / ceiling with T.W. 126.49 Each 4427.00
round blocks with all accessories including giving connections
and all labour charges etc., complete.
14 35.00 No Supply and Fixing of 18W CFL lights etc., 1023.72 Each 35830.00
15 6.00 No Supply of IS make fresh air exhaust fan of light duty 250V A.C. 3168.75 Each 19013.00
50Hz 300mm size (12") 1350 RPM Metallic body plastic blades,
wire mesh, etc., complete
16 6.00 No Labour charges for fixing of Exhaust fan in all with necessary 534.15 Each 3205.00
connections and masonry work of making hole, finishing etc.,
complete.
17 1.00 No Supply and fixing of 3-Phase Meter Board with 18" x30" size 3027.30 Each 3027.00
Peta Board with 3 No. of 32A, 415 V Fuse Unit and 32A
Standard make including giving internal connections
Electrical 84
Sl. Amount
Qty. Description of Item Rate Unit
No. Rs.
19 9.00 No Supply and fixing of 1x40W weatherproof flourescent streetlight 2149.81 Each 19348.00
fitting comprising canopy of sheet Aluminium in stove enamel
finish with copper / VPIT ballast, capacitor, tube and starter
etc.including fixing to the wall with 1.0 Mtr., 25mm dia GI pipe
b
20 100.00 Rm Supply and run of 3.5X35 sq mm Aluminium aromoured UG 104.88 Each 10488.00
Cables(IS 1554) for service wire including internal connection
and labour charges etc., complete
21 1.00 Nos Supply and fixing TPN Distribution board with IP-42 protection 6493.44 Each 6493.00
suitable for 3 phase ELCB / RCCB / FP Isolator as incomer and
10kA SP MCBs as outing going including internal connection
and labour charges for surface / flush mounting etc., complete.
22 1.00 Nos Supply and fixing of (copper) lightning arrester,as per IS Rmt 0.00
standard and necessary accessories including internal
connection and labour charges etc.,complate.
23 1.00 No Supply and Insulation of photo voltaic solar panel to suite the 100000.00 Each 0.00
requirement of power sopply to18w X 10Nos CFL lighting with
minimam 12 hours back up facility including cost of
transportation and macking suitable connections cost of all lab.
i) Series connected crystalline silicon solar cells with poly
crystalline technology.ii)Toughened high transmission glass.
iii)Ethyl vinyl Acetate (EVA) encapsulate. iv) Anodized
Aluminium frame. v) Wather Resistant frame seal. vi) Resistant
to water abrasion and hail impact. vii) Suitable junctionbox with
weather proof lid and three cable gland entry point .
viii)Warranty of 10years.
24 1.00 No Provision towards cost ,supply and erection of suitable DG Set LS 0.00
of approved make incl all charges etc complete.
Electrical 85
Construction of MPCS (Type I-7.50T) at VADAPALEM Village, RAMBILLI Mandal of VISAKHAPATNAM
District.
2) Plain Cement concrete in M20 Grade Design mix.with 20mm size graded
machine crushed hard granite metal (coarse aggregate) with minimum
cement content of 250 kg/cum (portland slag cement conforming to IS: 455 -
I989) including cost and conveyance of materials to site, cost of machine
mixing, concrete laying tamping, vibrating, watering curing, water lead
charges, bailing of water.etc,and all labour charges, hire and operational
charges of machinery, and including royalties ,all taxes etc., complete for
finished item of work for foundation concrete (BLD-CSTN-3-14)
993834.00
Detailed and Abstract estimate of Gate
1) Earth work excavation for foundations and depositing on bank for all lifts and
with an initial lead of 10m including all operational, incidental, labour
charges such as shoring ,sheeting, planking, strutting, dewatering charges
etc including royalties and all taxes complete for finished item of work as
per SS - 20 B (APSS 308).
2*2 1.350 1.350 1.650 12.03 Cum 244.82 Cum 2945.00
2) Plain Cement concrete in M20 Grade Design mix.with 20mm size graded
machine crushed hard granite metal (coarse aggregate) with minimum
cement content of 250 kg/cum (portland slag cement conforming to IS: 455 -
I989) including cost and conveyance of materials to site, cost of machine
mixing, concrete laying tamping, vibrating, watering curing, water lead
charges, bailing of water.etc,and all labour charges, hire and operational
charges of machinery, and including royalties ,all taxes etc., complete for
finished item of work for foundation concrete (BLD-CSTN-3-14)
4) VRCC M30 Grade Design mix using well graded aggregate with maximum
nominal size of aggregate using 20 mm to 6mm HBG machine crushed
graded metal (70% 20mm,10% 12mm, 10% 10mm & 10% 6 mm and duly
down graded; cement content in the mix to be not less than 325 Kg / m³
(portland slag cement conforming to IS: 455 - I989) with maximum water -
cement ratio of 0.45 including cost and conveyance of materials to site,
Machine mixing, concrete laying, tamping, centering, weigh batching
vibrating, watering curing and all labour charges, hire and operational
charges of machinery and water lead charges etc. including royalties and
all taxes, but excluding cost of steel and its fabrication complete for finished
item of work. (BLD-CSTN-3-15) for Columns , Lintels, Water Tanks.
Column 2*2 3.000 0.450 0.450 2.43 Cum 10933.70 Cum 26569.00
5) Plastering 12mm thick inside in two coats using portland slag cement
(conforming to IS:455-1989 ) with a base coat of 8mm thick in CM(1:5) prop
and top coat of 4mm thick in CM (1:3) prop. with dubara sponge finish
including cost and conveyance of all materials and water to work site and all
operational incidental, labour charges such as scaffolding, mixing mortar lift
charges curing etc., including using Recron 3S @ 125gms /per 1 bag of
cement in first coat, including royalties and all taxes complete for finished
item of work. (BLD-CSTN-8-10).
6) Supplying of Mild steel section i.e angles, channels etc. including cost and
conveyance of material to the site, overlaps and wastages, labour for
cutting, bending welding and placing them in position etc.,including all taxes
complete for finished item of work.(BLD-CSTN-4-3)
8) Cost ,supply ,and Filling Use full Earth insde the Compound Wall including
Ramming ,Watering Etc.Complte.
S.No. Description Nos. Length Breadth Depth Quantity Unit Rate Per Amount
In Between compound wall
1 50.000 30.000 0.600 900.00
Deduct :Building portion 1 17.945 13.905 0.600 -149.72
Deduct:Ramp Portion 1 8.280 4.370 0.600 -21.71
Deduct:Ramp triangular
Portion 1 2.300 4.370 0.600 -3.02
Add for variations 74.44
800.00 Cum 258.20 Cum
9 Painting two coats with Anti corrosive bitumen paint (black) grade 1 over a
primary coat of red oxide paint of grade-II to new steel works after the
surface are thoroughly cleaned and scrapped including primary coat item of
work ,cost and conveyance of all materials ,labourcharges etc.as per SS and
directed by the departmental authorities for finished item of work. (As per
BLD-CSTN)
2 4.00 2.25 1.50 27.00 Sqm 154.10 Sqm 4161
Superintending Engineer
PR Visakhapatnam
6826.63 1671323
975.23 5745226
5882.35 28552432
5201.24 1723691
2786.38 13524854
22291.02 7387244
21151.7 2666172
61270942.0
458.11
This is included in excavation
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
VSP Gajuwaka
Flyashbrick
s 729/0 Aganampudi
HBG
METAL 8/0Km 6/2Km 0/0 0/0 14/4Km 0/0Km 10/0Km
AKP JN. ATP JN.
BOWLUWADA Thmmapal 745/0 14/8Km
Bricks
Rambilli C.S.
11/0Km
Panchadarla 7/2 0/0Km 10/0Km
Gravel
Kothuru 5/2
Filling sand
0/0 Km
774/0Km
0/0 5/3 Yellamanchili
786/0
ADDA ROAD
PANDURUFilling
21/0Km 31/0
SAND QUARRY
sand for Filling OTG Fly ash
130Km mortor Sand Gravel HBG Metal Bricks bricks
130.00 5.80 3.80 8.00 6.20 3.80
5.30 10.00 14.40 14.40
TUNI 11.00 3.80 3.80 10.00
Sand for Mortor Rajahmundry 10.00 10.00 10
10.00
156.30 15.80 13.80 36.20 34.40 13.80
Superintending Engineer Executive Engineer, Dy. Executive Engineer, Asst. Executive Engineer,
P.R. Circle, Visakapatnam P.I.U.Visakhapatnam. P.I.U., Yellamanchili P.I.U., Yellamanchili
Shelter at Rambilli of Rambilli Mandal
16
LEAD CHART (COMMON SSR 2014-2015) ( Cement & Steel - August- 2015 Rates )
Construction of MPCS (Type I-7.50T) at VADAPALEM Village, RAMBILLI Mandal of VISAKHAPATNAM
District.
Seignioage
Initial MA Charges/1.1
Ref. to S.No./ Cost Convey- Un 9 (Excluding
Sl. Source of Lead in Loading
Description SSR page Item Unit excluding ance loading Contractor Total
No. Materials KM charges
No. Code No. seigniorage Charges charges 0.00% Profit
charges @13.615% &
Vat@ 5%)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14)
Portland Slag Cement (including loading
1 1 MT - 5300.00 - 46.47 5346.47
charges)
2 Fe 500 1 MT - 40000.00 - 55.71 40055.71
3 6 mm M.S.Rods 1 MT - 41500.00 - 55.71 41555.71
Mild steel, structural steel, i.e
4 1 MT - 41000.00 - 55.71 41055.71
Angles channels & I-sections
5 Coarse sand for Mortar Rajamundry 1 Cum 156.30 672.00 1490.79 33.72 2196.51
6 Coarse sand for Concrete Rajamundry 1 Cum 156.30 610.00 1490.79 33.72 2134.51
7 Coarse sand for filling Kothuru 1 Cum 15.80 460.00 166.07 33.72 659.79
8 2nd Class Bricks Thumpala 13 BMT-A-01 1000 Nos 34.40 4700.00 586.51 38.73 38.73 32.46 5396.42
Fly ash cement / lime solid blocks of 50 Atchuthapur
9 am 10 BMT-A-10 1000 Nos 13.80 19000.00 231.61 38.73 38.73 0.00 19309.06
kg/sq.cm of size 290 x 200 x 140 mm
10 Fly Ash Bricks of size 290 x100 x140 mm Atchuthapur 11 BMT-A-13 1000 Nos 13.80 11000.00 231.61 38.73 38.73 0.00 11309.06
with compressive strength of 50 Kg /sq.cm am
9 Aggregates 40mm nominal size (HBG) Bowluwada 28 M - 055 1 Cum 36.20 845.00 381.82 42.15 1268.97
10 Aggregates 20mm nominal size (HBG) Bowluwada 27 M - 053 1 Cum 36.20 1365.00 381.82 42.15 1788.97
Aggregates 13.20 / 12.50mm nominal size
11 Bowluwada 27 M - 052 1 Cum 36.20 1097.00 381.82 42.15 1520.97
(HBG)
12 Aggregates 10mm nominal size (HBG) Bowluwada 27 M - 051 1 Cum 36.20 935.00 381.82 42.15 1358.97
13 Aggregates 6mm nominal size (HBG) Bowluwada 27 M - 050 1 Cum 36.20 735.00 381.82 42.15 1158.97
1) Certified that the leads mentioned in the lead statement are shortest and correct.
2) Certified that metal items are to be obtained by blasting.
3) Certified that sufficient quantities & quanlity material are available in the above mentioned quarries.
4) Certified that for non SSR items lowest market rates are adopted
(Lead)
charges
(Lead)
for trucks
(Lead) charges for
(Lead) and
charges for trucks and
charges for tippers (Lead) (Lead)
trucks and tippers per
trucks and for charges for charges
tippers for cu.meter
tippers for Cement/ trucks and for trucks
Rubble/Size for PCC
Sl No. Distance Earth / Sand Steel/ tippers per and
stones/ Cut slabs/
/Gravel / RCC cu.meter tippers
Stones/ Shahabad
Murrum/ poles/ AC slabs/ CC & for water/ for Bricks
Coarse & GI 1000 litres /1000 nos
Lime/ Surki/ Laterite
aggregate
per cu.meter sheets/
per cu.meter blocks/
Packed
Wood/ cum
materials/t
onne
1 2 3 4 5 6 7 8
1 Lead up to 1 km 1 31.50 30.40 19.00 44.70 18.80 50.70
2 Lead up to 2 km 2 44.10 42.60 26.60 62.60 26.30 71.00
3 Lead up to 3 km 3 58.90 58.90 36.80 86.60 35.00 94.60
4 Lead up to 4 km 4 71.50 71.50 44.70 105.10 42.50 114.90
5 Lead up to 5 km 5 84.10 84.10 52.60 123.70 50.00 135.20
for Every km beyond 5 km up to 30
6 km 30 12.60 12.60 7.90 18.50 7.50 20.30
7 for Every km beyond 30 km 10000 10.50 10.50 6.60 15.50 6.30 16.90
Rubble/
Earth /
size stone/
Sand
cut stone/
/Gravel cement in steel in brick work
Sl No. Description of item Coarse
Murrum/ / Rs/tonne Rs./tonne Rs/1000
aggregate,
Surki/ Rs /
Lime in
cum
Rs/cum
Construction of MPCS (Type I-7.50T) at VADAPALEM Village, RAMBILLI Mandal of VISAKHAPATNAM District.
COMMON SSR 2014-15
Sl. S.No./ Item
Items Page No Rate per
No Code No.
LABOUR CHARGES
1 1st class mason 6 11 385.00 1 Each
2 2nd class mason 8 35 345.00 1 Each
Mazdoor (unskilled)/ Heavy
3 Mazoor/ Light Mazdoor 8 3 295.00 1 Each
Cost of Materials :
16 Binding wire 25 173 70.00 1 Kg
17 White cement 1012 BMS-W.68 29.00 1 Kg
Polished Shahabad/Tandur stone
18 LC 3115.46 10 sqm
slabs 15mm to 18mm thick
Ceramic Tiles Non-skid variety 7.3
19 15 BMT-C.01 465.00 1 Sqm
m thick of all shades
Edge Cut - Rectified Ceramic tiles
20 15 BMT-C.02 560.00 1 Sqm
8mm thick
Vitrified tiles 8mm to 10mm thick
21 of size 600mm x 600mm , 1st 16 BMT-C.16 631.00 1 Sqm
quality
Granite stone tiles 8mm thick
22 15 BMT-B.16 999.00 1 Sqm
(mirror polished of all shades)
Glazed coloured tiles Ist Quality
23 15 BMT-C.07 413.00 1 Sqm
for Dadooing
Cement Primer Waterbase Interior
Gr- 1 Asian/ Berger/ Nerolac/
24 34 BMT-J-01 144.00 1 Kg
Saicoat/Indocem/ PMCC/ ESSAR
or equivalent grade - I
60 Add for MA @ 0%
62 VAT @ 5% 5%
CENTERING :
HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Wooden Reapers,
Runners, Wood Posts, Wall Plates etc., for BRICK MASONRY/STONE MASONRY - 1 sqm
HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casuarinas Ballies, Bamboos, Wooden Reapers,
Runners, Wood Posts, Wall Plates etc., for PLASTERING to WALLS - 1 sqm
B) Plastering to walls
a) 1st floor Page 108 0.99 5.87 1 Sqm 6.86
b) 2nd floor 0.99 8.30 1 Sqm 9.29
c) 3rd floor 0.99 10.74 1 Sqm 11.73
d) 4th floor 0.99 13.18 1 Sqm 14.17
e) 5th floor 0.99 15.61 1 Sqm 16.60
f) 6th floor 0.99 18.05 1 Sqm 19.04
g) 7th floor 0.99 20.49 1 Sqm 21.48
HIRE CHARGES FOR STAGE SCAFFOLDING - up to 3.66 M using Casuarinas Ballies, Bamboos, Wooden Reapers,
Runners, Wood Posts, Wall Plates etc., for CEILING PLASTERING - 1 sqm
62 Hire charges for Stage
Scaffolding
Ceiling Plastering
a) 1st floor Page 108 2.37 11.95 1 Sqm 14.32
b) 2nd floor 2.37 16.75 1 Sqm 19.12
c) 3rd floor 2.37 21.54 1 Sqm 23.91
d) 4th floor 2.37 26.33 1 Sqm 28.70
e) 5th floor 2.37 31.13 1 Sqm 33.50
f) 6th floor 2.37 35.92 1 Sqm 38.29
g) 7th floor 2.37 40.71 1 Sqm 43.08
63 A) HIRE CHARGES FOR CENTERING & SCAFFOLDING
Labour
Material hire
Type of member charges upto Toatal upto FF SF TF
charges
FF
a) Footings, Bed blocks, Steps 277.00 446.00 723.00 491.00 540.00
b) Pedestals 315.00 710.00 1025.00
c) Plinth beams 1335.00 1075.00 2410.00
d) RCC Vertical walls of plane
surface - Page 302 (32 b-4) 796.00
B) HIRE CHARGES FOR CENTERING & SCAFFOLDING - Unsupported Height upto 3.66 M Steel scaffolding pipes,
jack Props, wallers, Foot plates, brackets, steel Centering Plates, etc.,
Labour
Material hire
Type of member charges upto SF TF
charges
FF
a) Lintels 1133.00 1141.00 1255.00 1369.00
b) Chajjas - Sunshades 224.00 175.00 193.00 210.00
c) Columns 341.00 1603.00 1763.00 1924.00
d) Beams 2002.00 1344.00 1478.00 1613.00
e) SLABS - Up to 150 mm thick 227.00 152.00 167.00 182.00
SLABS - above 150 mm - Up to
f) 233.00 157.00 173.00 188.00
300 mm thick
CEMENT MORTARS :
CEMENT MORTAR PER CUM CM (1:2) CM (1:3) CM (1:4) CM (1:5) CM (1:6) CM (1:8)
20 mm GRADED METAL
20mm HBG M/c chips 0.70 1788.97 1252.28
13.2/12.5mm HBG M/c chips 0.10 1520.97 152.10
10mm HBG M/c chips 0.10 1358.97 135.90
6mm HBG M/c chips 0.10 1158.97 115.90
Rate per Cum 1656.18
12 mm GRADED METAL
13.2/12.5mm HBG M/c chips 0.60 1520.97 912.58
10mm HBG M/c chips 0.20 1358.97 271.79
6mm HBG M/c chips 0.20 1158.97 231.79
Rate per Cum 1416.16
DATA
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
1 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing
of sides and bottom and backfilling in trenches with excavated suitable material including seigniorage charges, all taxes etc.,
complete as per Technical Specification 305 MORD / 304 MORTH in ordinary Soil - Manual Means up to 3m depth.
a) Labour
Mazdoor ( Unskilled) 3.64 Nos. 295.00 1 No. 1073.80
Add for MA @ 0.00 1073.80 0.00
Add 75% for foundations 75.00% 1073.80 805.35
Seigniorage charges 10.00 cum 18.49 1 cum 184.87
Cost for 10 cum 2064.02
Over Heads & Contractor's profit 13.615% 2064.02
@ 13.615% 281.02
VAT @ 5% 5.00% 2064.02 103.20
Rate per 10cum 2448.24
Rate per 1cum 244.82
Say 244.824
2 Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey Soils like BC
Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour charges such as shoring,
strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour charges etc., complete for finished
item of work including seignerage charges excluding dewatering charges etc., complete for Septic tank soak pit and sump.
(APSS No. 308)
Unit : 1 cum
Taking output : 10Cum
Mazdoor ( Unskilled) 3.64 Nos. 295.00 1 No. 1073.80
Add for MA @ 0.00 1073.80 0.00
Cost for 10 cum 1073.80
Seigniorage charges 10.00 cum 22.00 1 cum 220.00
Over Heads & Contractor's profit 13.62% 1073.80
@ 13.615% 146.20
VAT @ 5% 5.00% 1073.80 53.69
1493.69
Rate per 1cum 149.37
Say 149.4
3 Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations and basement with initial lead in
layers not exceeding 15 cm thick, consolidating each deposited layer by watering and ramming including cost and conveyance
of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of
work. (APSS NO. 309 & 310) As per BLD-CSTN
Unit : 1 cum
Taking output : 6Cum
a) Labour
Mazdoor ( Unskilled ) 3.12 Nos. 295.00 1 No. 920.40
Rate per 6 cum 920.40
Over Heads & Contractor's profit 13.62% 920.40
@ 13.615% 125.31
VAT @ 5% 5.00% 920.40 46.02
Rate per 6cum 1091.73
Rate per 1cum 181.96
Say 182
b) Machinery
Hydraulic Excavator 1 cum bucket 6.00 Hours 2848.50 1 Hour 17091.00
capacity
Cost for 240 cum 25823.17
Over Heads & Contractor's profit 13.62% 25823.17 3515.82
@ 13.615%
VAT @ 5% 5.00% 25823.17 1291.16
Rate per 10cum 30630.15
Rate per 1cum 127.63
Say 127.625625
Unit : 1 cum
Taking output : 10Cum
a) Labour
Mazdoor ( Unskilled) 3.64 Nos. 295.00 1 No. 1073.80
Add for MA @ 0.00 1073.80 0.00
Seigniorage charges 10.00 cum 18.49 1 cum 184.87
Cost for 10 cum 1258.67
Over Heads & Contractor's profit 13.62% 1258.67
@ 13.615% 171.37
VAT @ 5% 5.00% 1258.67 62.93
Rate per 10cum 1492.97
Rate per 1cum 149.30
Say 149.3
1 Filling with useful available excavated earth (Excluding rock) in trenches, sides of foundations and basement with initial lead in
layers not exceeding 15cm thick, consolidating each deposited layers by watering and ramming including cost and conveyance
of water to work site and all operational incidental, labour charges, hire charges of T & P etc., including all taxes complete for
finished item of work (APSS No. 309 & 310) BLD - CSTN-2.9)
Unit : 1 cum
Taking output : 6Cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 295.00 1 No. 91.45
Rate per 6 cum 91.45
Over Heads & Contractor's profit 13.62% 91.45 12.45
@ 13.615%
VAT @ 5% 5.00% 91.45 4.57
Rate per 6cum 108.47
Rate per 1cum 18.08
Say 18.1
2 Supplying and filling sand including watering, tamping etc.for foundations and basement including seigniorage charges, all
taxes and all labour charges for all operations etc., complete finished Item of work.(APSS NO. 309 & 310)
Unit : 1 cum
Taking output : 6Cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 295.00 1 No. 91.45
Add for MA @ 0.00 91.45 0.00
b)Material :
Coarse sand for filling 6.00 cum 659.79 1 cum 3958.76
Rate per 6 cum (a+b) 4050.21
Over Heads & Contractor's profit 13.62% 4050.21
@ 13.615% 551.44
VAT @ 5% 5.00% 4050.21 202.51
Rate per 6cum 4804.16
Rate per 1cum 800.69
Say 800.7
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
3 Supply and filling with good Gravel soil in layers not exceeding 150 mm., each layer being watered and well compacted before
the succeeding layer is laid, including seigniorage charges, all taxes and all labour charges for all operations etc., complete for
finished Item of work. (APSS No.309&310).
Unit : 1 cum
Taking output : 6Cum
a) Labour
Mazdoor (Unskilled ) 0.31 Nos. 295.00 1 No. 91.45
Add for MA @ 0.00 91.45 0.00
b)Material :
Gravel 6.00 cum 265.44 1 cum 1592.62
Rate per 6 cum (a+b) 1684.07
Over Heads & Contractor's profit 13.62% 1684.07
@ 13.615% 229.29
VAT @ 5% 5.00% 1684.07 84.20
Rate per 6cum 1997.56
332.93
Rate per 1cum Say 332.95
4 Plain Cement Concrete M 20 grade design mix using well graded aggregate with maximum nominal size of
aggregates(MSA) of 20mm HBG metal using Portland Slag Cement confirming to IS 455-1989 and the cement content in
the mix to be not less than 250 kg/cum with maximum water cement ratio of 0.5, including cost and conveyance of all
materials to site, seignorage charges, steel centering, machine mixing, concrete laying, tamping, vibrating, watering, curing
and all labour charges, hire and operational charges of machinery, water lead charges and including all taxes, bailing of
water.etc., complete for finished item of work for foundations. (As per BLD-CSTN)
5 Coursed Rubble stone masonry 2nd sort, in CM(1: 6) prop: (Cement: Sand) using hard blasted granite stones from approved
quarry and portland slag cement (conforming to IS:455-1989) including cost and conveyance of all materials like portland slag
cement, sand, water, Granite stones, etc., to site including seigniorage charges, sales & other taxes on all materials, all
operational, incidental, and labour charges such as cutting stones to required size and shape, mixing of cement mortar,
constructing masonry, curing etc., complete for finished item of work for foundation and basement (As per BLD-CSTN).
Unit = 1 cum
Taking output : 1Cum
A.MATERIALS
Cement 76.80 Kgs 5.35 1 Kgs 410.61
Coursed Rubble Stone 0.94 Cum 826.94 1 Cum 777.32
Bond stone 0.16 Cum 1795.20 1 Cum 287.23
Fine aggregate(sand) 0.32 Cum 2134.51 1 Cum 683.04
B) LABOUR
1st class mason 1.50 Nos. 385.00 1 Each 577.50
Mazdoor (unskilled) 2.32 Nos. 295.00 1 Each 684.40
Add for MA @ 0.00 1261.90 0.00
Rate per 1cum 3420.10
Over Heads & Contractor's profit 13.62% 3420.10
@ 13.615% 465.65
VAT @ 5% 5.00% 3420.10 171.01
Rate per 1cum 4056.76
Say 4056.8
6 Random Rubble stone masonry in CM (1:6) prop: (Cement: Sand) using hard granite stones carted from approved quarry
including cost and conveyance of all materials like cement, sand, water, stones etc., from approved quarry, to site and including
seigniorage charges, sales & other taxes on all materials including labour for cutting stones to required size and shape, mixing,
of cement, mortar, construction, curing etc.,and Overheads & Contractors profit complete for finished item of work in
foundation and basement. (APSS No. 601 & 615) ( BLD-CSTN-6-13 )
Unit = 1 cum
Taking output : 1Cum
A.MATERIALS
Cement 79.20 Kgs 5.35 1 Kgs 423.44
CR stone (30x x30 x 60cm) 0.44 Cum 826.94 1 Cum 363.85
Rough Stone 0.50 Cum 690.06 1 Cum 345.03
Bond Stones 7Nos (0.24 x 0.24 x 0.16 Cum 1795.20 1
Cum
0.39 = 0.16cum) 287.23
Fine aggregate (Sand) 0.33 Cum 2134.51 1 Cum 704.39
B) LABOUR
1st class mason 1.20 Nos. 385.00 1 Each 462.00
Mazdoor (unskilled) 2.00 Nos. 295.00 1 Each 590.00
Add for MA @ 0.00 1052.00 0.00
Rate per 1cum 3175.94
Over Heads & Contractor's profit 13.62% 3175.94
@ 13.615% 432.40
VAT @ 5% 5.00% 3175.94 158.80
Rate per 1cum 3767.14
Say 3767.15
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
7 Plain Cement Concrete M 20 grade design mix using well graded aggregate with maximum nominal size of aggregates(MSA) of
20mm HBG metal using Portland Slag Cement confirming to IS 455-1989 and the cement content in the mix to be not less than
250 kg/cum with maximum water cement ratio of 0.5, including cost and conveyance of all materials to site, seignorage charges,
steel centering, machine mixing, concrete laying, tamping, vibrating, watering, curing and all labour charges, hire and
operational charges of machinery, water lead charges and including all taxes, bailing of water.etc., complete for finished item of
work for Foundations (As per BLD-CSTN)
Foundations
A.MATERIALS :
Cement 250.00 Kgs 5.35 1 Kg 1336.62
20mm HBG metal 0.90 Cum 1656.18 1 Cum 1490.56
Sand 0.45 Cum 2134.51 1 Cum 960.53
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
B.LABOUR :
1st class Mason 0.100 Nos 385.00 1 Each 38.50
Mazdoor (both men&women) 1.39 Nos 295.00 1 Each 410.05
Add for MA @ 0.00 448.55 0.00
C.MACHINERY :
Concrete mixer 1.000 hours 518.40 1 hour 518.40
Hire charges of centering and
scaffolding 1.00 Cum 277.00 1 Cum 277.00
Labour charges 1.00 Cum 446.00 1 Cum 446.00
5570.06
Over Heads & Contractor's profit 13.62% 5570.06
@ 13.615% 758.36
VAT @ 5% 5.00% 5570.06 278.50
Rate per 1cum 6606.92
Say 6606.95
8 PCC M30 Grade Design mix using well graded aggregate with maximum nominal size of aggregate(MSA) of 20mm HBG
machine crushed and duly down graded; cement (Portland Slag Cement confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-cement ratio of 0.45, including Super plasticizer admixture IS marked as
per 9103-1999 (as approved by Engineer) including cost and conveyance of all materials to site, seignorage fee, concrete
laying, tamping, including steel centering, shuttering, lift charges, weigh batching/machine mixing, vibrating, watering,
curing and all labour charges for all operations, all taxes, hire and operational charges of machinery and water lead charges etc.,
but excluding cost of steel and its fabrication complete for finished item of work for Steps. (As per BLD-CSTN)
Material
Graded Metal 20mm to 6mm 0.80 cu.m. 1656.18 1 cu.m. 1324.94
Sand 0.40 cu.m. 2134.51 1 cu.m. 853.81
Cement 350.00 kgs 5346.47 1000 kgs 1871.26
Water 1.20 KL 77.00 1 KL 92.40
Machinery
Batchingplant 0.5 cum 1.333 Hour 816.30 1 Hour 1088.13
Needle vibrator 40 mm (petrol) 1.333 Hour 302.30 1 Hour 402.97
LA on crew charges 0% 917.37 1 0.00
Labour
1st class Masons 0.1 Nos. 385.00 1 Each 38.50
Man and Mazdoor 1.39 Nos. 295.00 1 Each 410.05
9 VRCC M30 Grade Design mix using well graded aggregate with maximum nominal size of aggregate(MSA) of 20mm HBG
machine crushed and duly down graded; cement (Portland Slag Cement confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-cement ratio of 0.45, including Super plasticizer admixture IS marked as
per 9103-1999 (as approved by Engineer) including cost and conveyance of all materials to site, seignorage fee, machine
mixing, concrete laying, tamping, centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., weigh batching, vibrating, watering, curing and all labour charges for all operations, all taxes, hire and
operational charges of machinery and water lead charges etc., but excluding cost of steel and its fabrication complete for
finished item of work for Foundations, Plinth, Pedestals (Below Plinth). (As per BLD-CSTN)
A.MATERIALS :
Cement 325.00 Kgs 5.35 1 Kg 1737.60
20mm HBG graded metal 0.80 Cum 1656.18 1 Cum 1324.94
Sand 0.40 Cum 2134.51 1 Cum 853.81
B.LABOUR :
1st class Mason 0.133 Nos 385.00 1 Each 51.21
2nd class Mason 0.267 Nos 345.00 1 Each 92.12
Mazdoor (both men & women) 4.60 Nos 295.00 1 Each 1357.00
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 816.30 1 hour 1088.13
Needle vibrator 40mm ( petrol ) 1.333 hours 302.30 1 hour 402.97
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
Basic cost per 1cum 7000.18
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
a Footings
Rate for Design mix M 30 1.00 Cum 7000.18 1 Cum 7000.18
Hire charges of centering and
scaffolding 1.00 Cum 277.00 1 Cum 277.00
Labour charges 1.00 Cum 446.00 1 Cum 446.00
Add for MA @ 0.00 446.00 0.00
7723.18
Over Heads & Contractor's profit 13.62%
@ 13.615% 7723.18 1051.51
VAT @ 5% 5.00% 7723.18 386.16
9160.85
Rate per 1cum Say 9160.85
b Pedastals
Rate for Design mix M 30 1.00 Cum 7000.18 1 Cum 7000.18
Hire charges of centering and
scaffolding 1.00 Cum 315.00 1 Cum 315.00
Labour charges 1.00 Cum 710.00 1 Cum 710.00
8025.18
Over Heads & Contractor's profit 13.62%
@ 13.615% 8025.18 1092.63
VAT @ 5% 5.00% 8025.18 401.26
9519.07
Rate per 1cum Say 9519.1
c Plinth Beams
Rate for Design mix M 30 1.00 Cum 7000.18 1 Cum 7000.18
Hire charges of centering and
scaffolding 1.00 Cum 1335.00 1 Cum 1335.00
Labour charges 1.00 Cum 1075.00 1 Cum 1075.00
Add for MA @ 0.00 1075.00 0.00
9410.18
Over Heads & Contractor's profit 13.62%
@ 13.615% 9410.18 1281.20
VAT @ 5% 5.00% 9410.18 470.51
11161.89
Rate per 1cum Say 11161.9
10 VRCC M30 Grade Design mix using well graded aggregate with maximum nominal size of aggregate(MSA) of 20mm HBG
machine crushed and duly down graded; cement (Portland Slag Cement confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-cement ratio of 0.45, including Super plasticizer admixture IS marked as
per 9103-1999 (as approved by Engineer) including cost and conveyance of all materials to site, seignorage fee, machine
mixing, concrete laying, tamping, centering using Steel scaffolding pipes, jack props, wallers, Foot plates, brackets, steel
centering plates etc., weigh batching, vibrating, watering, curing and all labour charges for all operations, all taxes, hire and
operational charges of machinery and water lead charges etc., but excluding cost of steel and its fabrication complete for
finished item of work for Columns, Lintels, Water Tanks, RCC Wallsin Buildings. (As per BLD-CSTN)
A.MATERIALS :
Cement 325.00 Kgs 5.35 1 Kg 1737.60
20mm HBG graded metal 0.80 Cum 1656.18 1 Cum 1324.94
Sand 0.40 Cum 2134.51 1 Cum 853.81
B.LABOUR :
1st class Mason 0.167 Nos 385.00 1 Each 64.30
2nd class Mason 0.167 Nos 345.00 1 Each 57.62
Mazdoor (both men&women) 5.60 Nos 295.00 1 Each 1652.00
Add for MA @ % 0.00 1773.92 0.00
C.MACHINERY :
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
A COLUMNS :
for un supported height of 3.66 m
Rate for other Floors STILT/ GF FF SF TF
Rate as above 7273.77 7273.77 7273.77 7273.77
Hire charges of centering and
scaffolding 341.00 341.00 341.00 341.00
Labour charges 1603.00 1603.00 1763.30 1923.60
Add for MA @ 0.00 0.00 0.00 0.00
(Manual)Lift charges of materials
0.00 0.00 177.39 354.78
Add for MA @ 0.00 0.00 0.00 0.00
Rate per 1cum 9217.77 9217.77 9555.46 9893.15
Over Heads & Contractor's profit 1255.00 1255.00 1300.98 1346.95
@ 13.615%
VAT @ 5% 460.89 460.89 477.77 494.66
TOTAL Rate per Cu.m 10933.7 10933.7 11334.25 11734.8
B LINTELS :
Rate for other Floors STILT/ GF FF SF TF
Rate as above 7273.77 7273.77 7273.77 7273.77
Hire charges of centering and
scaffolding 1133.00 1133.00 1133.00 1133.00
Labour charges 1141.00 1141.00 1255.10 1369.20
Add for MA @ 0.00 0.00 0.00 0.00
(Manual)Lift charges of materials
0.00 0.00 177.39 354.78
Add for MA @ 0.00 0.00 0.00 0.00
Rate per 1cum 9547.77 9547.77 9839.26 10130.75
Over Heads & Contractor's profit 1299.93 1299.93 1339.62 1379.30
@ 13.615%
VAT @ 5% 477.39 477.39 491.96 506.54
TOTAL Rate per Cu.m 11325.1 11325.1 11670.85 12016.6
C WATER TANKS :
150mm thick side walls
Cost of M 30 design mix 0.15 cum 7273.77 1.00 cum 1091.07
Centering charges RCC vertical
walls of Plain Surfce (PH Items 1.00 sqm 629.00 1 Sqm 629.00
32.b, 4 page-302)
1720.07
Rate for other Floors STILT/ GF FF SF TF
Rate as above 1720.07 1720.07 1720.07 1720.07
(Manual)Lift charges of materials
0.00 0.00 26.61 53.22
7th floor 0.00 0.00 0.00 0.00
1720.07 1720.07 1746.68 1773.29
Over Heads & Contractor's profit 234.19 234.19 237.81 241.43
@ 13.615%
VAT @ 5% 86.00 86.00 87.33 88.66
Rate per 1 sqm 2040.26 2040.26 2071.82 2103.39
Say 2040.3 2040.3 2071.85 2103.4
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
11 VRCC M30 Grade Design mix using well graded aggregate with maximum nominal size of aggregate(MSA) of 20mm HBG
machine crushed and duly down graded; cement (Portland Slag Cement confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-cement ratio of 0.45, including Super plasticizer admixture IS marked as
per 9103-1999 (as approved by Engineer) including cost and conveyance of all materials to site, seignorage fee, machine
mixing, concrete laying, tamping, centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel
centering plates etc., weigh batching, vibrating, watering, curing and all labour charges for all operations, all taxes, hire and
operational charges of machinery and water lead charges etc., but excluding cost of steel and its fabrication complete for
finished item of work for RCC Slabs and Beams (As per BLD-CSTN)
A.MATERIALS :
Cement 325.00 Kgs 5.35 1 Kg 1737.60
20mm HBG graded metal 0.80 Cum 1656.18 1 Cum 1324.94
Sand 0.40 Cum 2134.51 1 Cum 853.81
B.LABOUR :
1st class Mason 0.067 Nos 385.00 1 Each 25.80
2nd class Mason 0.133 Nos 345.00 1 Each 45.89
Mazdoor (both men&women) 3.077 Nos 295.00 1 Each 907.72
Add for MA @ % 0.00 979.41 0.00
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 816.30 1 hour 251.42
Needle vibrator 40mm ( petrol ) 0.308 hours 302.30 1 hour 93.11
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
Basic cost per 1cum 5332.69
B RCC SLABS :
Shelves 50 mm thick :
for un supported height of 3.66 m
Rate for Design mix M 30 0.050 Cum 5332.69 1 Cum 266.63
12 VRCC M30 Grade Design mix using well graded aggregate with maximum nominal size of aggregate(MSA) of 20mm HBG
machine crushed and duly down graded; cement (Portland Slag Cement confirming to IS 455-1989) content in the mix to be
not less than 325 Kg/cum, with maximum water-cement ratio of 0.45, including Super plasticizer admixture IS marked as per
9103-1999 (as approved by Engineer) including cost and conveyance of all materials to site, seignorage fee, machine mixing,
concrete laying, tamping, steel scaffolding & centering, weigh batching, vibrating, watering, curing and all labour charges for all
operations, all taxes, hire and operational charges of machinery and water lead charges etc., but excluding cost of steel and its
fabrication complete for finished item of work for 60cm wide sun-shades of 75mm thick at fixed end and 50mm thick at free
end with an average thickness of 62.5mm, and Lofts. (As per BLD-CSTN)
A.MATERIALS :
Cement 325.00 Kgs 5.35 1 Kg 1737.60
20mm HBG graded metal 0.80 Cum 1656.18 1 Cum 1324.94
Sand 0.40 Cum 2134.51 1 Cum 853.81
B.LABOUR :
1st class Mason 0.067 Nos 385.00 1 Each 25.80
2nd class Mason 0.133 Nos 345.00 1 Each 45.89
Mazdoor (both men & women) 3.077 Nos 295.00 1 Each 907.72
Add for MA @ 0.00 979.41 0.00
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 816.30 1 hour 251.42
Add for MA @ 0.00 302.30 0.00
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
Basic cost per 1cum 5239.58
Rate per 1 Rm
Cost of RCC M 30 design mix 0.0375 cum 5239.58 1 cum 196.48
13 Brick masonry in C.M (1:6) prop. with Portland Slag (Cement confirming to IS 455-1989) using Second Class bricks of
traditional size of 230 x 110 x 70 mm including cost and conveyance of all materials to site, seignorage charges, mixing of
cement mortar and laying of bricks and mortar to specified thickness, watering, curing, including all scaffolding, hire and
operational charges of machinery, all taxes and all labour charges and all water lead charges etc., complete for finished item of
work.(As per BLD-CSTN).
Unit : 1cum
A.MATERIALS :
Cement 48 Kgs 5.35 1 Kgs 256.63
Bricks 2nd class 23x11x7cms 512 Nos 5396.42 1000 Nos 2762.97
Fine aggregate ( Sand ) 0.20 cu.m. 2134.51 1 cu.m. 426.90
B.LABOUR :
1st class mason 0.24 Nos. 385.00 1 Each 92.40
2nd class mason 0.56 Nos. 345.00 1 Each 193.20
Mazdoor (Unskilled) 1.89 Nos. 295.00 1 Each 557.55
Add for MA @ 0.00 843.15 0.00
Rate for 1 cu.m. 4289.65
a) Internal walls :
Rate for other Floors STILT/ GF FF SF TF
Rate as worked out above 4289.65 4289.65 4289.65 4289.65
Hire charges for Access Scaffolding
43.17 43.17 43.17 23.00
Labour charges for scaffolding 255.04 255.04 361.00 466.91
Add for MA @ 0.00 0.00 0.00 0.00
Lift charges (Page 131 of Std. Data 0.00 0.00 84.32 168.63
)
Add for MA @ 0.00 0.00 0.00 0.00
Rate for 1 cu.m. 4587.86 4587.86 4778.14 4948.19
Over Heads & Contractor's profit 624.64 624.64 650.54 673.70
@ 13.615%
VAT @ 5% 229.39 229.39 238.91 247.41
5441.89 5441.89 5667.60 5869.30
Say 5441.9 5441.9 5667.6 5869.3
b) External walls :
Rate for other Floors STILT/ GF FF SF TF
Rate as worked out above 4289.65 4289.65 4289.65 4289.65
Hire charges for Access Scaffolding
43.17 43.17 86.35 129.52
Labour charges for scaffolding 255.04 255.04 361.00 466.91
Add for MA @ 0.00 0.00 0.00 0.00
Lift charges ( Page 131 of Std. 0.00 0.00 84.32 168.63
Data )
Add for MA @ 0.00 0.00 0.00 0.00
Rate for 1 cum. 4587.86 4587.86 4821.32 5054.71
Over Heads & Contractor's profit 624.64 624.64 656.42 688.20
@ 13.615%
VAT @ 5% 229.39 229.39 241.07 252.74
5441.89 5441.89 5718.81 5995.65
Say 5441.9 5441.9 5718.85 5995.65
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
14 Reinforced Brick Masonry 115mm thk. with portland slag cement (conforming to IS:455-1989) in CM (1:4) using second
class bricks of size of 230x110x70 mm and placing two numbers of 8mm dia. Fe 500 steel coated with cement slurry embedded
in every 3 rd layer with free ends of reinforcement keyed in to mortar joints of the main brick work, including cost of all
materials, all taxes, seignourage and all operational incidental labour charges such as scaffolding, mixing mortar, constructing
masonry, curing etc., but excluding cost of steel and its fabrication charges etc. complete for finished item of work. (As per
BLD-CSTN)
Unit - 10sqm
A.MATERIALS :
Bricks 2nd class 23x11x7cms 512 Nos. 5396.42 1000 Nos. 2762.97
Cement Mortar (1:4) 0.20 cu.m. 4290.07 1 cu.m. 858.01
B.LABOUR :
1st class mason 0.60 Nos. 385.00 1 Each 231.00
2nd class mason 0.60 Nos. 345.00 1 Each 207.00
Mazdoor (Unskilled) 2.75 Nos. 295.00 1 Each 811.25
Add for MA @ 0.00 1249.25 0.00
Rate for 1 cum 4870.23
Rate for 1 sqm 560.08
Internal walls :
Rate for other Floors STILT/ GF FF SF TF
Rate as worked out above 560.08 560.08 560.08 560.08
Hire charges for Access Scaffolding
9.93 9.93 9.93 9.93
Labour charges for scaffolding 58.66 58.66 83.03 107.39
Add for MA @ 0.00 0.00 0.00 0.00
Lift charges ( Page 131 of Std. 0.00 0.00 12.49 24.99
Data )
Add for MA @ 0.00 0.00 0.00 0.00
Rate per 10 sqm 628.67 628.67 665.53 702.39
Over Heads & Contractor's profit 85.59 85.59 90.61 95.63
@ 13.615%
VAT @ 5% 31.43 31.43 33.28 35.12
Rate per 1 sqm 745.70 745.70 789.42 833.14
Say 745.7 745.7 789.45 833.15
Masonry work in CM (1:6) prop with Flyash Cement solid blocks of size 290 x 200 x 140 mm for manufacturing of
flyash solid blocks using flyash of 80 kgs, cement of 15 kgs. Gypsum of 5 kgs. and stone dust including cost and
conveyance of all materials, labour charges, seiniorage charges, scaffolding and curing etc., complete with a
compresive streangth not lessthan 50 kg/sqcm for walls for Superstructure Walls.
C.M (1:6) cum 0.10 3648.49 364.85
Fly ash bricks no.s 110.00 19.31 2124.00
Mason 1st class Day 0.42 385.00 161.70
Mason 2nd class Day 0.92 345.00 317.40
Mazdoor (unskilled) Day 2.80 295.00 826.00
1305.10 3793.95
Add 13.615%( overhead
charges Cum Contractor
profit ) 516.55
4310.49
GF/Stilt FF SF TF
Basic Rate 3793.95 3793.95 3793.95 3793.95
Scaffolding Charges 43.17 43.17 86.35 129.52
Labour Charges 255.04 255.04 361.00 466.91
Lift charges 0.00 0.00 130.51 261.02
4092.16 4092.16 4371.80 4651.40
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Reinforced Brick Masonary walls of 11.5cm in CM(1:4) using Fly Ash bricks having a crushing strength of not less
than 50.00kg/cm2 - IS:12894-1990 - CLASS - 5 of size 225x100x60 and using two mild steel bars of 8m dia in every
third layer of brick masory, with free joints of the main block work including cost and seignorage charges and
conveyance of all materials and water from approved sources to work site and all operational, incidental, labour
charges such as scaffolding mixing mortor constructing masonary lift charges, curing etc. complete but excluding
cost of steel and its fabrication charges for finished item of work as per SS 509.
Unit 10 sqm
A. MATERIALS:
Fly ash bricks Class - 5 Bricks
cum 512.00 11.31 5790.24
C.M.(1:4) cum 0.20 4290.07 858.01
B. LABOUR:
Mason 1st class day 0.60 385.00 231.00
Mason 2nd class day 0.6 345.00 207.00
Man Mazdoor (unskilled) day 2.75 295.00 811.25
1249.25 7897.50
7898
Internal walls :
Rate per other floors GF FF SF TF
Basic Rate per 10 Sqm 7897.50 7897.50 7897.50 7897.50
Hire charges for Access 43.17 43.17 86.35 129.52
Scaffolding
Labour charges for scaffolding
255.04 255.04 361.00 466.91
Lift charges per 10 sqm 0.00 0.00 124.93 249.85
8195.71 8195.71 8469.77 8743.78
over head charges @13.615%
1115.85 1115.85 1153.16 1190.47
VAT @ 5% 409.785748425487 409.785748425487 423.488694077661 437.189139729835
Supply and filling with Selected Earth in layers not exceeding 150 mm., each layer being watered and well compacted before
the succeeding layer is laid, including seigniorage charges, all taxes and all labour charges for all operations etc., complete for
finished Item of work. (APSS No.309&310) in betwen Compound wall and Basement .
Unit : 1 cum
Taking output : 6Cum
a) Labour
Mazdoor (Unskilled ) 0.31 Nos. 295.00 1 No. 91.45
Over Heads & Contractor's profit 0.00 91.45
@ 13.615% 0.00
b)Material :
Selected Earth 6.00 cum 202.44 1 cum 1214.62
Rate per 6 cum (a+b) 1306.07
Over Heads & Contractor's profit 13.615% 1306.07
@ 13.615% 177.82
VAT @ 5% 5.00% 1306.07 65.30
Rate per 6cum 1549.19
258.20
Rate per 1cum Say 258.2
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
15 Supplying of Fe 500 steel coated with cement slurry including all labour charges for cranking, bending rods and tying grills
and placing them in position including cost of all material, all taxes and cost of binding wire etc., complete for finished item of
work. (As per BLD-CSTN)
Unit - 1 MT
a) Material
HYSD bars including 5% for
overlaps and wastage 1.05 MT 40055.71 1 MT 42058.50
Binding wire 6.00 Kgs 70.00 1 Kgs 420.00
b) Labour for cutting, bending,
shifting to site, tying and placing in
position
Blacksmith / Barbender (Bld SSR)
10.00 Nos. 450.00 1 Each 4500.00
Mazdoor(Unskilled) 10.00 Nos. 295.00 1 Each 2950.00
Add for MA @ 0.00 7450.00 0.00
49928.50
16 Supplying of Mild steel section i.e angles, channels etc. including cost and conveyance of material to the site, overlaps and
wastages, labour for cutting, bending welding and placing them in position etc., complete for finished item of work.(BLD-
CSTN-4-3)
Unit - 1 MT
a) Material
Mild steel bars including 5% for 1.05 MT 41055.71 1 MT 43108.50
overlaps and wastage
b)
Labour charges for fabricating steel
works like Window Grills,
Compound Wall Grills, Iron Doors,
1
Windows including cost of welding
rods, power charges, excluding cost
of fixing in position BMM -14
Kgs 22.00 1 MT 22000.00
69108.50
17 Ornamental Plastering 12mm thick to ceiling in two coats using Portland Slag Cement (confirming to IS 455-1989) with a base
coat of 8mm thick in CM(1:5) prop and top coat of 4mm thick in CM (1:3) prop. with dubara sponge finish including cost and
conveyance of all materials and water to work site, seigniorage charges, all taxes and all operational incidental, labour charges
such as scaffolding, mixing mortar, lift charges, curing etc., including using Recron 3S @ 125gms /per 1 bag of cement in first
coat, complete for finished item of work (As per BLD-CSTN).
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:5), 8mm thick
18 Plastering 12mm thick inside in two coats using portland slag cement (conforming to IS:455-1989 ) with a base coat of 8mm
thick in CM(1:5) prop and top coat of 4mm thick in CM (1:3) prop. with dubara sponge finish including cost and conveyance of
all materials and water to work site, all taxes, seigniorage and all operational incidental, labour charges such as scaffolding,
mixing mortar lift charges curing etc., including using Recron 3S @ 125gms /per 1 bag of cement in first coat, complete for
finished item of work for Internal Plastering (As per BLD-CSTN).
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:5), 8mm thick
a) Internal walls :
Rate for other Floors STILT/ GF FF SF TF
Rate as worked out above 2527.17 2527.17 2527.17 2527.17
Hire charges for Access
Scaffolding 9.90 9.90 9.90 9.90
Labour charges for scaffolding 58.70 58.70 83.00 107.40
Add for MA @ 0.00 0.00 0.00 0.00
Lift charges ( Page 131 of Std. 0.00 0.00 190.02 380.04
Data )
Add for MA @ 0.00 0.00 0.00 0.00
2595.77 2595.77 2810.09 3024.51
Over Heads & Contractor's profit 353.41 353.41 382.59 411.79
@ 13.615%
VAT @ 5% 129.79 129.79 140.50 151.23
Rate per 10 Sqm 3078.97 3078.97 3333.19 3587.52
Rate per 1 Sqm 307.90 307.90 333.32 358.75
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
b) External walls :
Rate for other Floors STILT/ GF FF SF TF
Rate as worked out above 2527.17 2527.17 2527.17 2527.17
Hire charges for Access
Scaffolding 9.90 9.90 19.80 29.70
Labour charges for scaffolding 58.70 58.70 141.70 249.10
Add for MA @ 0.00 0.00 0.00 0.00
Lift charges ( Page 131 of Std. 0.00 0.00 190.02 380.04
Data )
Add for MA @ 0.00 0.00 0.00 0.00
2595.77 2595.77 2878.69 3186.01
Over Heads & Contractor's profit 353.41 353.41 391.93 433.78
@ 13.615%
VAT @ 5% 129.79 129.79 143.93 159.30
Rate per 10 Sqm 3078.97 3078.97 3414.56 3779.09
Rate per 1 Sqm 307.90 307.90 341.46 377.91
Say 307.9 307.9 341.5 377.95
19 Plastering 20mm thick in 2 coats to Brick masonry walls using portland slag cement (conforming to IS:455-1989), 1st coat of
16mm thick in C.M (1:6) prop. using Recron 3s @ 125 gms per 1 bag of cement in first coat, 2nd coat of 4mm thick in C.M(1:4)
prop. with dubara sponge finishing and curing etc., including cost and conveyance of all materials, all taxes, seignourage
charges and all operational, incidental labour charges such as scaffolding, mixing mortar, curing etc., complete as per
specification and drawings for finished item of work for External surfaces of walls. (As per BLD-CSTN)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6), 16mm
thick
Cement 43.00 Kgs 5.35 1 Kgs 229.90
Fine aggregate (Sand) 0.18 Cum 2196.51 1 Cum 395.37
Recron 3s 107.50 Gms 40.00 125 Gms 34.40
Top coat in CM(1:4), 4mm thick
a) Internal walls :
Rate for other Floors STILT/ GF FF SF TF
Rate as worked out above 2725.25 2725.25 2725.25 2725.25
Hire charges for Access
Scaffolding 9.90 9.90 9.90 9.90
Labour charges for scaffolding 58.70 58.70 83.00 107.40
Add for MA @ 0.00 0.00 0.00 0.00
Lift charges ( Page 131 of Std. 0.00 0.00 190.02 380.04
Data )
Add for MA @ 0.00 0.00 0.00 0.00
2793.85 2793.85 3008.17 3222.59
Over Heads & Contractor's profit 380.38 380.38 409.56 438.76
@ 13.615%
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
b) External walls :
Rate for other Floors STILT/ GF FF SF TF
Rate as worked out above 2725.25 2725.25 2725.25 2725.25
Hire charges for Access
Scaffolding 9.90 9.90 19.80 19.80
Labour charges for scaffolding 58.70 58.70 141.70 249.10
Add for MA @ 0.00 0.00 0.00 0.00
Lift charges (Page 131 of Std. Data) 0.00 0.00 190.02 380.04
Add for MA @ 0.00 0.00 0.00 0.00
2793.85 2793.85 3076.77 3374.19
Over Heads & Contractor's profit 380.38 380.38 418.90 459.40
@ 13.615%
VAT @ 5% 139.69 139.69 153.84 168.71
Rate per 10 Sqm 3313.93 3313.93 3649.51 4002.30
Rate per 1 Sqm 331.39 331.39 364.95 400.23
Say 331.4 331.4 365 400.25
20 Impervious coat 20mm thick average over VRCC roof slab with C.M (1:3) prop. using Portland Slag Cement confirming to IS
455-1989, mixing with approved brand of water proofing compound at the rate of 1.0 kg per bag of cement and Recron 3S @
100gms per 1bag of cement and laid when the slab is green with thread lining and finished smooth with a floating cement of
neat cement as directed including cost and conveyance of all material to site, seigonarage fee, laying with maintaining proper
slope, curing and including all taxes and all labour charges for all operations etc., complete for finished item of work. (As per
BLD-CSTN)
Unit : 10 sqm
A.MATERIALS :
Cement Mortar (1:3) 0.21 Cum 4931.65 1 Cum 1035.65
Impervious Water proof compound 2.00 Kgs 52.00 1
Kgs
104.00
Recron 3s 201.60 Gms 40.00 125 Gms 64.51
B.LABOUR :
1st Class Mason 0.66 Nos. 385.00 1 Each 254.10
2nd Class Mason 1.54 Nos. 345.00 1 Each 531.30
Mazdoor (Unskilled) 3.70 Nos. 295.00 1 Each 1091.50
Add for MA @ 0.00 1876.90 0.00
Rate per 10 Sqm 3081.06
21 RCM non bearing wall 50mm thick in C.M(1:3) prop. using Portland Slag Cement confirming to IS 455-1989 and tying of
steel reinforcement and rabbit wire mesh on one side, including cost and conveyance of of all materials, all taxes and all labour
charges for all operations etc., with all lead and lifts, centering charges, fine finishing and curing, including all other operational
charges and incidental charges etc., complete but excluding cost of steel and its fabrication and binding wire for the finished
item of work. (As per BLD-CSTN)
Unit : 10 sqm
A)MATERIALS
Rabbit wire mesh 13.30 sqm 17.00 1 sqm 226.10
Cement 319.10 Kgs 5.35 1 Kgs 1706.06
Fine aggregate (Sand) 0.577 cu.m. 2134.51 1 Kgs 1231.61
Excluding HYSD steel/mild steel
& binding wire
B) LABOUR CHARGES
1st Class Mason 8.00 Nos. 385.00 1 Each 3080.00
Operator concrete mixer 1.00 Nos. 385.00 1 Each 385.00
Mazdoor (Unskilled) 10.00 Nos. 295.00 1 Each 2950.00
Add for MA @ 0.00 6415.00 0.00
C)Machinery :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 2.00 hours 328.60 1 hours 657.20
cum)capacity
Add for % MA on crew charges
0.00 189.80 0.00
Rate per 10 Sqm 10235.97
22 Flooring / Treads with polished Tandur stones slabs of 15 mm thick (457x304 mm) set over base coat of CM (1:8) over already
laid CC bed / RCC Roof Slab, including neat cement slurry of honey like consistency spread @ 3.3 kgs per sqm. & Jointed with
neat cement to full depth including cost and conveyance of all materials like cement (Portland Slag Cement confirming to IS
455-1989), sand, and water and flooring stones etc., complete, including seigniorage charges, labour charges for dressing of
flooring stones etc., complete for finished item of work. (As per BLD-CSTN)
Unit = 10 sqm.
A. MATERIALS:
Polished shahabad stone 15 to
18mm thick 11.00 Sqm 3115.46 10 Sqm 3427.01
Cement for CM(1:8) proportion for
base coat 21.60 Kgs 5.35 1 Kg 115.48
Cement for slurry 33.00 Kgs 5.35 1 Kg 176.43
Cement for jointing 20.00 Kgs 5.35 1 Kg 106.93
Sand for CM(1:8) 0.12 Cum 2134.51 1 Cum 256.14
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
a) Flooring :
Rate for other floors STILT/ GF FF SF TF
Flooring with Vertified tiles of 1st quality, of size not less than 400x400mm, 7mm thick normal colours, set over base coat of
cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching
20 shade, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., cost
and conveyance of all materials including all charegs for all operations etc., complete (BLD-CSTN-9-5)
Unit = 10 sqm.
A. MATERIALS:
Vertified Tiles 10.50 Sqm 631.00 1 Sqm 6625.50
Cement for CM(1:8)proportion for
base coat 21.60 Kgs 5.35 1 Kg 115.48
Cement for slurry 33.00 Kgs 5.35 1 Kg 176.43
Cement for jointing 20.00 Kgs 5.35 1 Kg 106.93
Sand for CM(1:8) 0.12 Cum 2134.51 1 Cum 256.14
Add water charges 1% 0.01 7280.49 72.80
B .LABOUR
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
a) Flooring :
Rate for other floors Stilt/GF FF SF
Rate as worked out above 9179.99 9179.99 9179.99
Lift charges ( Page 131 of Std. 0.00 0.00 182.67
Data )
Add for MA @ 0.00 0.00 0.00
Rate per 10 Sqm 9179.99 9179.99 9362.66
Rate per 1 Sqm 918.00 918.00 936.27
Add 13.615% overhead charges, 124.99 124.99 127.47
Contractor profit
VAT @ 5% 45.90 45.90 46.81
Rate per 1 Sqm 1088.89 1088.89 1110.55
Providing skirting to internal walls to 10cm height/ risers of steps with Vitrified tiles of 8-10mm thick length equal to flooring
stones, set over base coat of CM (1:3), 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost all taxes and
conveyance of all materials like Tandur stone, cement (Portland Slag Cement confirming to IS 455-1989), sand and water etc.,
complete including seigniorage charges, all incidental, operation and labour etc., complete for finished item of work. (As per
BLD-CSTN)
Unit = 10 sqm
A.MATERIALS :
Cost Vitrified Tile 8-10 mm thick 10.50 sqm 631.00 1 sqm 6625.50
Sand for CM(1:3) base coat 0.12 cum 2134.51 1 cum 256.14
Cement for CM(1:3) base coat 34.56 Kgs 5.35 1 Kg 184.77
Cement for slurry 33.00 Kgs 5.35 1 Kg 176.43
White Cement for Jointing and 2.00 Kgs 29.00 1 Kg
Poiting 58.00
Add water charges 1% 0.01 7300.84 73.01
B.LABOUR
Mason 1st class 0.96 Nos. 385.00 1 Each 369.60
Mason 2nd class 2.24 Nos. 345.00 1 Each 772.80
Mazdoor(unskilled) 3.30 Nos. 295.00 1 Each 973.50
2115.90 0.00
Rate for 10 sqm 9489.75
23 Flooring with 7.3mm thick Ceramic floor tiles of approved brand colour shade and design of size 400 x 400 mm laid over floor
bed /VRCC slab set over 12.0 mm th.in CM (1:8 ) prop. base coat and neat grey cement slurry of honey like consistence spread
at the rate of 3.3 kg of cement per Sqm and jointed with neat white cement paste mixed with pigment of matching shade
including cost all taxes and conveyance of all materials to site seignorage fee including all mixing mortar and watering, leveling
to proper slope and curing including all labour charges etc., for finished item of work. (As per BLD-CSTN)
Unit = 10 sqm.
A. MATERIALS:
Ceramic tiles 7.3mm thick of 1st
quality 10.50 Sqm 465.00 1 Sqm 4882.50
Cement for CM(1:8)proportion for
base coat 21.60 Kgs 5.35 1 Kg 115.48
Cement for slurry 33.00 Kgs 5.35 1 Kg 176.43
White Cement 2.00 Kgs 29.00 1 Kg 58.00
Sand for CM(1:8) 0.12 Cum 2134.51 1 Cum 256.14
Add water charges 1% 0.01 5488.55 54.89
B .LABOUR
Mason 1st class 0.96 Nos 385.00 1 Each 369.60
Mason 2nd class 2.24 Nos 345.00 1 Each 772.80
Mazdoor(un skilled) 3.30 Nos 295.00 1 Each 973.50
Add for MA @ 0.00 2115.90 0.00
Rate for 10sqm 7659.34
24 Granolithic Concrete Flooring, 20 mm thick with M20 Design mix using maximun size of aggregate(MSA) 10mm HBG
machine crushed, laid over CC bed already laid or RCC roof slab, in alternate panels of size not exceeding 1.50 m x 1.50 m and
finishing the top surface to required smoothness and slopes and thread lining including cost of all materials like cement
(Portland Slag Cement confirming to IS 455-1989), metal, sand and water etc., complete, including seigniorage charges, all
taxes and all labour charges for all operations etc., complete for finished item of work. (As per BLD-CSTN)
Unit : 10sqm
A.MATERIALS :
6mm to 12 mm H.G. Metal
(Machine crushed) 0.17 Cum 1416.16 1 Cum 240.75
Cement 120.00 Kgs 5.35 1 Kgs 641.58
Sand 0.085 Cum 2134.51 1 Cum 181.43
Add water charges 1% 0.01 1063.76 10.64
B. LABOUR
Mason 1st class 1.25 Nos. 385.00 1 Each 481.25
Mason 2nd class 0.06 Nos. 345.00 1 Each 20.70
Mazdoor (unskiled) 3.00 Nos. 295.00 1 Each 885.00
Add for MA @ 0.00 1386.95 0.00
Rate for 10 sqm 2461.35
Over Heads & Contractor's profit 13.62% 2461.35
@ 13.615% 335.11
VAT @ 5% 5.00% 2461.35 123.07
Rate for 10 sqm 2919.53
Rate for 1 sqm 291.95
Say 292
25 Providing skirting to internal walls to 15cm height/ risers of steps with polished Tandur stone 15mm thick, length equal to
flooring stones, set over base coat of CM (1:3), 12 mm thick with cement slurry of honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost all
taxes and conveyance of all materials like Tandur stone, cement (Portland Slag Cement confirming to IS 455-1989), sand and
water etc., complete including seigniorage charges, all incidental, operation and labour etc., complete for finished item of work.
(As per BLD-CSTN)
Unit = 10 sqm
A.MATERIALS :
Cost polished Tandur stone 15 mm 10.50 sqm 3115.46 10 sqm
thick 3271.23
Sand for CM(1:3) base coat 0.12 cum 2134.51 1 cum 256.14
Cement for CM(1:3) base coat 57.60 Kgs 5.35 1 Kg 307.96
Cement for slurry 33.00 Kgs 5.35 1 Kg 176.43
Add water charges 1% 0.01 4011.76 40.12
B.LABOUR
Mason 1st class 0.77 Nos. 385.00 1 Each 296.45
Mason 2nd class 2.24 Nos. 0.00 1 Each 0.00
Mazdoor(unskilled) 3.10 Nos. 295.00 1 Each 914.50
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
26 Providing dadooing to walls with glazed coloured tiles 1st quality of size approved by Engineer-in-Charge set over base coat of
CM(1:5) 12mm thick with cement slurry of honey like consistency spread at the rate of 3.30kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and
water, all taxes etc., complete including seigniorage charges all lbaour charges for all operations complete for finished item of
work. (As per BLD-CSTN)
Unit = 10 sqm
A.MATERIALS :
Cost of glazed coloured tiles 10.50 sqm 413.00 1 sqm 4336.50
Sand for CM(1:5) base coat 0.12 cum 2134.51 1 cum 256.14
Cement for CM(1:5) base coat 34.56 Kgs 5.35 1 Kg 184.77
Cement for slurry 33.00 Kgs 5.35 1 Kg 176.43
White cement for jointing & 6.00 Kgs 29.00 1 Kg
pointing 174.00
Add water charges 1% 0.01 5127.84 51.28
B.LABOUR
Mason 1st class 0.77 Nos. 385.00 1 Each 296.45
Mazdoor(unskilled) 0.80 Nos. 295.00 1 Each 236.00
Add for MA @ 0.00 532.45 0.00
Rate for 10 sqm 5711.57
27 Supply and fixing of 110mm dia. ISI mark PVC rain water spouts of 4mm thick including cost of necessary PVC bends, shoes
and PVC clamps and all other accessories and fixing in position including cost and conveyance of all materials to site,
seigniorage charges sales and other taxes on all materials, all operational , incidental and labour charges such as fixing in
alingment etc., complete for finished item of work. (As per BLD-CSTN)
28 Painting to exterior surface of walls with Trump or other equivalent cement paints of approved brand, shade, two coats, over
primer coat, total three coats in all, to give an even shade after throughly brushing the surface to remove all dirt and remains of
loose powdered materials, including cost, all taxes and conveyance of all material to site, using brushes and including all
required material, all labour charges, curing, scaffolding etc., complete for finished item of work. (As per BLD-CSTN)
Unit 10Sqm
Cost of cement primer grade-I 1.00 Kgs 144.00 1
Kgs
144.00
Painter 1st class 0.21 Nos. 440.00 1 Each 92.40
Painter 2nd class 0.49 Nos. 345.00 1 Each 169.05
Water proof cement paint 3.50 Kgs 50.00 1 Kgs 175.00
Painter 1st class 0.15 Nos. 440.00 1 Each 66.00
Painter 2nd class 0.35 Nos. 345.00 1 Each 120.75
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
29 Painting to Internal surface of walls with Plastic Emulsion or other equivalent quality of approved shade two coats over primer
coat total three coats in all to give an even shade after throughly brushing the surface to remove all dirt and remains of loose
powdered materials, including cost and conveyance of all material to site, using brushes and including cost and conveyance of
all required material, all taxes and all labour charges for all operations, curing, scaffolding etc., complete for finished item of
work. (As per BLD-CSTN)
Painting to New Walls , over a primary coat and painting two coats of synthetic enamel paint 1st grade of approved brand
and shade including cost and conveyance of all materials to site cost of primer coat and all labour charges etc. complete
including applying sand paper on lappam coats for neat finish including sales & other taxes on cost of all materials etc.complete
(APSS No.1200, 1207 & 1211) in all floors
Unit : 10 sqm
A.MATERIALS :
Cement primer 0.70 Ltr 144.00 1 Ltr 100.80
B.LABOUR :
1st Class Painter 0.21 Nos. 440.00 1 Each 92.40
2nd Class Painter 0.49 Nos. 345.00 1 Each 169.05
Add for MA @ 0.00 261.45 0.00
Cost of Synthetic Enamel Paint 1.20 Ltr 253.00 1
Ltr
303.60
B.LABOUR :
1st Class Painter 0.36 Nos. 440.00 1 Each 158.40
2nd Class Painter 0.84 Nos. 345.00 1 Each 289.80
Sundries including brushes ,
ladders etc., @ 1% 1% 1114.05 11.14
Rate per 10 sqm 1125.19
112.52
Over Heads & Contractor's profit 13.615% 112.52
@ 13.615% 15.32
VAT @ 5% 5.00% 112.52 5.63
Rate per 1 sqm 133.47
Say 133.5
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
30 Painting to new wood work and flush shutters with lappam finish , over a primary coat and painting two coats of synthetic
enamel paint 1st grade of approved brand and shade including cost and conveyance of all materials to site cost of primer coat
and all labour charges etc. complete including applying sand paper on lappam coats for neat finish including sales & other taxes
on cost of all materials etc.complete (APSS No.1200, 1207 & 1211) in all floors
Unit : 10 sqm
A.MATERIALS :
Cost of Putty for Wood work 1.00 Kg 145.00 1.00 Kg 145.00
Wood primer 0.70 Ltr 145.00 1 Ltr 101.50
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
B.LABOUR :
1st Class Painter 0.21 Nos. 440.00 1 Each 92.40
2nd Class Painter 0.49 Nos. 345.00 1 Each 169.05
Add for MA @ 0.00 261.45 0.00
Cost of Synthetic Enamel Paint 1.20 Ltr 253.00 1
Ltr
303.60
B.LABOUR :
1st Class Painter 0.36 Nos. 440.00 1 Each 158.40
2nd Class Painter 0.84 Nos. 345.00 1 Each 289.80
Add for MA @ 0.00 448.20 0.00
Sundries including brushes ,
ladders etc., @ 1% 1% 1114.75 11.15
Rate per 10 sqm 1270.90
127.09
Over Heads & Contractor's profit 13.62% 127.09
@ 13.615% 17.30
VAT @ 5% 5.00% 127.09 6.35
Rate per 1 sqm 150.74
Say 150.75
31 Flush pointing to CRS/Brick Masonary in Cement Mortar (1:3) Prop. using portland slag cement (conforming to IS:455-1989)
including cost and conveyance of all materials to site, cost of seigniorage charges on all materials, all taxes, labour charges on
all materials, curing etc., complete for finished item of work. (As per BLD-CSTN)
Unit = 10 sqm
A. MATERIALS:
Cement 14.40 Kg 5.35 1 Kg 76.99
Fine aggregate (Sand) 0.03 cum 2134.51 1 cum 64.04
B. LABOUR:
Mason 2nd class 0.50 day 345.00 1 no 172.50
Mazdoor (unskilled) 0.74 day 295.00 1 no 218.30
Add for MA @ 0.00 390.80 0.00
531.83
Over Heads & Contractor's profit 13.62% 531.83
@ 13.615% 72.41
VAT @ 5% 5.00% 531.83 26.59
say 630.83
Rate per 1 Sqm 63.1
32 Pebble dash exterior plaster on walls upto a height of 10 metres above ground level with a mixture of washed pebble or crushed
stone graded from 6 mm to 12 mm nominal size dashed over and including fresh cement plaster in two coats using Portland
Slag Cement confirming to IS 455-1989 backing coat 10mm cement plaster (1:3) (1cement : 3sand) and finishing coat 10mm
cement plaster (1:3) (1cement : 3sand) mixed with 10% finely grounded hydrated lime by volume of cement including arrises,
chamfers and/or rounded angles not exceeding 80 mm in girth including cost and conveyance of allmaterials to site, all taxes,
seigniorage charges and labour charges for all operational incidental charges etc., comnplete for finished item of work. (As per
BLD-CSTN)
33 Collection and supply of 65 mm HBG metal including cost and conveyance of all materials, all taxes, seigniorage charges and
stacking to departmental Gauge including all labour charges, spreading etc., complete for finishd item of work.
34 Collection and supply of 40-45 mm HBG metal including cost and conveyance of all materials, seigniorage charges, all taxes,
stacking to deptl. Gauge and labour charges including spreading etc., complete for finishd item of work.
Cost of 40-45 mm metal 1.00 Cum 1011.97 1 cum 1011.97
Over Heads & Contractor's profit 13.62% 1011.97
@ 13.615% 137.78
VAT @ 5% 5.00% 1011.97 50.60
Cost per 1 cum 1200.35
Say 1200.35
35 Collection and supply of 19-22 mm HBG metal including cost and conveyance of all materials, seigniorage charges, all taxes,
stacking to deptl. Gauge and labour charges including spreading etc., complete for finishd item of work. (As per BLD-CSTN).
36 Collection and supply of coarse sand including cost and conveyance of all materials to work site, seigniorage charges, all taxes
and stacking to deptl. Gauge, and labour charges etc.complete for finished item of work. (As per BLD-CSTN).
37 Collection and supply of brick bats including cost and conveyance of all materials, seigniorage charges, all taxes and stacking to
deptl. gauge and labour charges including spreading etc., complete for finishd item of work. (As per BLD-CSTN)
38 Providing and fixing of M.S hand railing 150mm height made out of 40mm dia. (OD) MS Pipe medium class supported with
20mm dia. (OD) MS pipe of medium class as verticals at 3m intervals, including fixing in position line, cutting, welding,
painting two coats with Anti corrosive bitumen paint (black) grade-1 over a primary coat of red oxide paint of grade-II to new
steel works, including cost and conveyance of all material to site, all taxes and all labour charges for all operations etc.,
complete for finished item of work. (As per BLD-CSTN)
39 Painting two coats with Anti corrosive bitumen paint (black) grade 1 over a primary coat of red oxide paint of grade-II to new
steel works after the surface are thoroughly cleaned and scrapped including primary coat item of work ,cost and conveyance of
all materials ,labourcharges etc.as per SS and directed by the departmental authorities for finished item of work. (As per BLD-
CSTN)
Unit = 10 sqm
Primary coat
Red oxide primer 0.70 Lts 130.00 1 Lt 91.00
Painter 1st class 0.21 Nos 440.00 1 each 92.40
Painter 2nd class 0.49 Nos 345.00 1 each 169.05
Bitumen paint
Anti corrosive bitumen paint
(black) grade 1 Sl No.397 BMT- 535.70
J.28 1.10 Lts 487.00 1 Lt
Painter Ist class 0.33 Nos 440.00 1 each 145.20
Painter 2nd class 0.77 Nos 345.00 1 each 265.65
Rate per 10 Sqm 1299.00
Over Heads & Contractor's profit
@ 13.615% 13.62% 1299.00 176.86
40 Soling with 150 mm cubes hard stone including 25% of Metal of 40 to 80 mm. size for packing and 20% Gravel for filling
interstices and compacting with 80 - 100 kN Power Roller including hire charges of Power Roller, watering, including cost of
soling stone, seigniorage charges, all taxes and all labour charges for all operations etc., complete for finished item of work
RBR-SBBS-5. (As per BLD-CSTN)
Unit = cum
Taking output = 1 cum
a) Labour
Men Mazdoor for conveyance &
packing 1.10 day 295.00 1 day 324.50
41 Gravel Backing for Revetments as per APSS including cost and conveyance of all materials to site, cost of seigniorage charges
on all materials, all taxes, labour charges on all materials, curing etc., complete for finished item of work. (As per RBR-
PTWK-7-ii).
Unit = cum
(a) Material
Gravel 1.16 cum 265.44 1 cum 307.91
(b) Labour
Mazdoor (Unskilled) 1.10 day 295.00 1 cum 324.50
Add for MA @ 0.00 324.50 0.00
632.41
Over Heads & Contractor's profit
@ 13.615% 13.62% 632.41 86.10
42 Providing and laying pitching on slopes using Stone/Boulder with minimum size of 300mm (25Kg. min) and using stone
spalls of 25mm minimum size laid over prepared filter media including cost and conveyance of all materials, seigniorage
charges, all taxes and all labour charges for all operations etc., complete as per drawing and technical specifications Clause 1302
MORD / 2504 MORTH (As per RBR-PTWK-5 (i))
Unit 1Cum
(a) Material
Boulder with minimum size of 300
mm for Pitching (25 kg min.) 1.00 Cum 629.97 1 Cum 629.97
/(MORTH - 40 kg)
Stone spalls of minimum 25 mm
size 0.20 Cum 462.97 1 Cum 92.59
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
(b) Labour
Mate - day
Mason 1st Class 0.35 day 385.00 1 day 134.75
Mazdoor (Unskilled) 0.79 day 295.00 1 day 233.05
Add for MA @ 0.00 367.80 0.00
1090.36
Over Heads & Contractor's profit 13.62%
@ 13.615% 148.45
1090.36
VAT @ 5% 5.00% 1090.36 54.52
Rate per cum 1293.33
Say 1293.35
bridge/culvert and construction joint, admixtures as approved, curing of concrete slabs for 14 days, curing compound (where
specified) and water finishing to lines and grade as per drawing and technical specification clause 1501.22 including cost of all
materials, labour, conveyance, hire charges of machinaries, royalties, all taxes etc., complete as per direction of Engineer in
charge.
Unit = cum
Taking output 75Cum 172.50 t
(100x3.75 x 0.200)
a) Labour
Mason (1st class) 5.00 day 385.00 1 day 1925.00
Mason (2nd class) 5.00 day 345.00 1 day 1725.00
Mazdoor (unskilled) 150.00 day 295.00 1 day 44250.00
Mazdoor(skilled) 6.00 day 295.00 1 day 1770.00
Surveyor 2.00 day 500.00 1 day 1000.00
Mazdoor (semi-skilled) 6.00 day 295.00 1 day 1770.00
Black smith for cutting of dowel 385.00
bars including removal of burrs,
fabrications & fixing of dowel bars 1.00 day 1 day 385.00
19,425.10
c) Material
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
44 Construction of stone aggregate sub-base using dust & Sand by providing well graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three
wheel 80-100 KN static roller / Vibratory Roller 80-100 KN capacity to achieve the desired density, complete as per Technical
Specification Clause 402 MORD, including cost and conveyane of all materials, seigniorage charges, all taxes, all labour
charges, T&P, etc., complete (RBR-SBBS-2).
c) Material
Well graded granular sub-base
material as per table 400.2
Cost of materials
Quarry spall finer than 3mm@
66% (Dust) 237.60 cum 265.44 1 cum 63067.93
Centre fixed both side openable shutter window 5’0”x4’0” (1524mm x1219.2mm). Outer frame section size of 72x50mm.
Shutter frame section size of 48 x 25 mm. Mullion section size of 72x50mm. Fixed beading section size of 12 x 12 mm. For
windows
Unit : 1 Sqm
Taking output :1Sqm
Cost of Windows 1.00 sqm 6300.00 1 Sqm 6300.00
Rate per 1 sqm 6300.00
Over Heads & Contractor's profit 13.62%
@ 13.615% 882.00
46 Providing and fixing 1.80 m high GI Barbed wire fencing with 2.40 m angle iron posts 50mmx50 mmx6 mm placed at every 3
m center to center founded in M15 grade concrete ,0.60m below ground level every 15 th post,last but one end post and corner
port shall be strutted on both sided and end post on one side only and provided with 121 horizontal wires,fixed with GI
staples,turn buckles etc complete as per clause 807 of MORTH
Unit : 1 Sqm
Taking output :1Sqm
SSR Rate 1.00 sqm 2503.00 1 Sqm 2503.00
Rate per 1 sqm 2503.00
Over Heads & Contractor's profit 13.62%
@ 13.615% 350.42
Add for MA @ % 0%
Over Heads & Contractor's profit @ 13.615%
13.615%
VAT @ 5% 5%
Cost of Materials :
12 Sal wood scantlings of any length BMT-E.15 51994.00 1 Cum
13 Sal wood planks of any thickness BMT-E.16 69327.00 1 Cum
14 Medium Teak wood scantlings upto 2.00
mts BMT-E.01 76280.00 1 Cum
15 Medium Teak wood scantlings 2.00 to
3.00 mts BMT-E.02 84756.00 1 Cum
16 Medium Teak wood scantlings above
3.00 mts BMT-E.03 93232.00 1 Cum
17 Medium Teak wood planks of any
thickness BMT-E.04 152561.00 1 Cum
18 35mm thick solid bond wood block
board type with commercial ply on both
faces confirming to IS 2202 flush shutter
BMT-N.17 1158.00 1 Sqm
19 Cost of Al. tower bolt 75 mm long BMT-G.06 75.00 1 No
20 Cost of Al. tower bolt 100 mm long BMT-G.07 92.00 1 No
21 Cost of Al. tower bolt 150 mm long BMT-G.08 111.00 1 No
22 Cost of Al. tower bolt 200 mm long BMT-G.09 137.00 1 No
23 Cost of Al. tower bolt 250 mm long BMT-G.10 165.00 1 No
24 Cost of Al. Butt hinges 75 mm long BMT-G.23 108.00 1 No
25 Cost of Al. Butt hinges 100 mm long BMT-G.24 128.00 1 No
26 Cost of Al. Butt hinges 125 mm long BMT-G.25 154.00 1 No
27 Cost of Al. Butt hinges 150 mm long BMT-G.26 160.00 1 No
28 Cost of Al. handle 75 mm long BMT-G.31 73.00 1 No
29 Cost of Al. handle 100 mm long BMT-G.32 82.00 1 No
30 Cost of Al. handle 125 mm long BMT-G.33 122.00 1 No
31 Cost of Al. handle 150 mm long BMT-G.34 136.00 1 No
32 Cost of Al. aldrop 200 mm long BMT-G.40 319.00 1 No
28 Cost of Al. aldrop 250 mm long BMT-G.41 380.00 1 No
29 Cost of Al. aldrop 300 mm long BMT-G.42 413.00 1 No
30 Cost of heavy duty Al. door stopper BMT-G57 61.00 1 No
31 Cost of deluxe Al. window stay BMT-G56 140.00 1 No
Supply and fixing of ornamental grill made of 25mm x 5mm MS flats for fixing in the fixed panels of door cum
windows as per the approved drawing including cutting the flat to required length, welding, painting with red oxide single
coat including cost and
DATA
1 Providing and fixing of single shutter door of size 2.00 x 2.10 m made with frame of Sal wood of size 75mm x 100mm
with 6 Nos. of hold fasts (3 on each side) and painted with liquid bitumen on wall side and with flush shutter of hard
wood solid bond wood block board type of 35mm thick commercial ply on both sides confirming to IS 2202 including 3
Nos Parlimentary Aluminium butt Hinges (150mm), 1 No. Aluminium Tower bolt (250mm) at top, 1 No. Aluminium
Aldrop (250mm long), 1 No Aluminium Handle (100 mm long), 1 No Al. heavy duty door stopper and 1 No. rubber bush
on wall face of door including cost and conveyance of all materials, all taxes, labour charges for making, fixing of
fixtures and door frame and shutter in position and all incidental charges etc., complete for finished item of work.
Quantity analysis
Frame :
Outer frame - Vertical 2.00 x 2.1 0
4.2 Rmt x 0.10 x 0.075 0.0315 cum
Cost analysis
Material :
Cost of Sal wood frame (BMT-E.15) 0.04650 cum 51994.00 1 cum 2417.72
Cost of 35 mm thick flush shutter 3.82 sq.m 1158.00 1 sq.m 4423.56
(BMT-N-17)
Cost of MS Z hold fasts 6 Nos. 15.00 Each 90.00
Cost of Al. tower bolt 250 mm long 1 Nos. 165.00 Each 165.00
(BMT-G.10)
Cost of Al. Butt hinges 125 mm long 3 Nos. 154.00 Each 462.00
(BMT-G.25)
Cost of Al. aldrop 250mm long (BMT- 1 No. 380.00 Each 380.00
G.41)
Cost of Al. handle 100mm long (BMT- 1 Nos. 82.00 Each 82.00
G.32)
Cost of heavy duty Al. door stopper 1 Nos. 61.00 Each 61.00
(BMT-G57)
Cost of rubber bush 1 Nos. 14.00 Each 14.00
Labour charges :
Labour charges for frame work 0.04650 cum 8914.90 1 cum 414.54
Labour charges for fixing flush door 3.820 sq.m 324.00 1 sq.m 1237.68
shutter to the frame , fixing the fixtures
to the shutter (BMM-V-23)
Add for MA @ % 0.00% 1652.22 0.00
Add for nails & screws etc. 14.85
Rate for 2.21 sq.m 9762.35
Rate for 1 sq.m 2324.37
Over Heads & Contractor's profit @ 13.62% 2324.37 316.46
13.615%
VAT @ 5% 5.00% 2324.37 116.22
2757.05
Rate for 1 sq.m Say 2757.10
2 Providing and fixing of single shutter door of size 1.20 x 2.10 m made with frame of Sal wood of size 75mm x 100mm
with 6 Nos. of hold fasts (3 on each side) and painted with liquid bitumen on wall side and with flush shutter of hard
wood solid bond wood block board type of 35mm thick commercial ply on both sides confirming to IS 2202 including 3
Nos Parlimentary Aluminium butt Hinges (150mm), 1 No. Aluminium Tower bolt (250mm) at top, 1 No. Aluminium
Aldrop (250mm long), 1 No Aluminium Handle (100 mm long), 1 No Al. heavy duty door stopper and 1 No. rubber bush
on wall face of door including cost and conveyance of all materials, all taxes, labour charges for making, fixing of
fixtures and door frame and shutter in position and all incidental charges etc., complete for finished item of work.
Quantity analysis
Frame :
Outer frame - Vertical 2.00 x 2.1 0
4.2 Rmt x 0.10 x 0.075 0.0315 cum
Cost analysis
Material :
Cost of Sal wood frame (BMT-E.15) 0.04050 cum 51994.00 1 cum 2105.76
Cost of 35 mm thick flush shutter 2.19 sq.m 1158.00 1 sq.m 2536.02
(BMT-N-17)
Cost of MS Z hold fasts 6 Nos. 15.00 Each 90.00
Cost of Al. tower bolt 250 mm long 1 Nos. 165.00 Each 165.00
(BMT-G.10)
Cost of Al. Butt hinges 125 mm long 3 Nos. 154.00 Each 462.00
(BMT-G.25)
Cost of Al. aldrop 250mm long (BMT- 1 No. 380.00 Each 380.00
G.41)
Cost of Al. handle 100mm long (BMT- 1 Nos. 82.00 Each 82.00
G.32)
Cost of heavy duty Al. door stopper 1 Nos. 61.00 Each 61.00
(BMT-G57)
Cost of rubber bush 1 Nos. 14.00 Each 14.00
Labour charges :
Labour charges for frame work 0.04050 cum 8914.90 1 cum 361.05
Labour charges for fixing flush door 2.190 sq.m 324.00 1 sq.m 709.56
shutter to the frame , fixing the fixtures
to the shutter (BMM-V-23)
Add for MA @ % 0.00% 1070.61 0.00
Add for nails & screws etc. 14.85
Rate for 2.21 sq.m 6981.24
Rate for 1 sq.m 2770.33
Over Heads & Contractor's profit @ 13.62% 2770.33 377.18
13.615%
VAT @ 5% 5.00% 2770.33 138.52
3286.03
Rate for 1 sq.m Say 3286.05
3 Providing and fixing of single shutter door of size 1.05 x 2.10 m made with frame of Sal wood of size 75mm x 100mm
with 6 Nos. of hold fasts (3 on each side) and painted with liquid bitumen on wall side and with flush shutter of hard
wood solid bond wood block board type of 35mm thick commercial ply on both sides confirming to IS 2202 including 3
Nos Parlimentary Aluminium butt Hinges (150mm), 1 No. Aluminium Tower bolt (250mm) at top, 1 No. Aluminium
Aldrop (250mm long), 1 No Aluminium Handle (100 mm long), 1 No Al. heavy duty door stopper and 1 No. rubber bush
on wall face of door including cost and conveyance of all materials, all taxes, labour charges for making, fixing of
fixtures and door frame and shutter in position and all incidental charges etc., complete for finished item of work.
Quantity analysis
Frame :
Outer frame - Vertical 2.00 x 2.1 0
4.2 Rmt x 0.10 x 0.075 0.0315 cum
Cost analysis
Material :
Cost of Sal wood frame (BMT-E.15) 0.039375 cum 51994.00 1 cum 2047.26
Cost of 35 mm thick flush shutter 1.88 sq.m 1158.00 1 sq.m 2177.04
(BMT-N-17)
Cost of MS Z hold fasts 6 Nos. 15.00 Each 90.00
Cost of Al. tower bolt 250 mm long 1 Nos. 165.00 Each 165.00
(BMT-G.10)
Cost of Al. Butt hinges 125 mm long 3 Nos. 154.00 Each 462.00
(BMT-G.25)
Cost of Al. aldrop 250mm long (BMT- 1 No. 380.00 Each 380.00
G.41)
Cost of Al. handle 100mm long (BMT- 1 Nos. 82.00 Each 82.00
G.32)
Cost of heavy duty Al. door stopper 1 Nos. 61.00 Each 61.00
(BMT-G57)
Cost of rubber bush 1 Nos. 14.00 Each 14.00
Labour charges :
Labour charges for frame work 0.03938 cum 8914.90 1 cum 351.02
Labour charges for fixing flush door 1.880 sq.m 324.00 1 sq.m 609.12
shutter to the frame , fixing the fixtures
to the shutter (BMM-V-23)
Add for MA @ % 0.00% 960.14 0.00
Add for nails & screws etc. 14.85
Rate for 2.21 sq.m 6453.29
Rate for 1 sq.m 2920.04
Over Heads & Contractor's profit @ 13.62% 2920.04 397.56
13.615%
VAT @ 5% 5.00% 2920.04 146.00
3463.61
Rate for 1 sq.m Say 3463.65
4 Providing and fixing of single shutter doors of size 0.90 x 2.10 m made with frame of Sal wood of size 75mm x 100mm
with 6 Nos. of hold fasts (3 on each side) and painted with liquid bitumen on wall side and with flush shutter of hard
wood solid bond wood block board type of 35mm thick commercial ply on both sides confirming to IS 2202 including 3
Nos Parlimentary Aluminium butt Hinges (150mm), 1 No. Aluminium Tower bolt (250mm) at top, 1 No. Aluminium
Aldrop (250mm long), 1 No Aluminium Handle (100 mm long), 1 No Al. heavy duty door stopper and 1 No. rubber bush
on wall face of door including cost and conveyance of all materials, all taxes, labour charges for making, fixing of
fixtures and door frame and shutter in position and all incidental charges etc., complete for finished item of work.
Quantity analysis
Frame :
Outer frame - Vertical 2.00 x 2.1 0
4.2 Rmt x 0.10 x 0.075 0.0315 cum
Material :
Cost analysis
Cost of Sal wood frame (BMT-E.15) 0.03825 cum 51994.00 1 cum 1988.77
Cost of 35 mm thick flush shutter 1.580 sq.m 1158.00 1 sq.m 1829.64
(BMT-N-17)
Cost of MS Z hold fasts 6 Nos. 15.00 Each 90.00
Cost of Al. tower bolt 250 mm long 1 Nos. 165.00 Each 165.00
(BMT-G.10)
Cost of Al. Butt hinges 125 mm long 3 Nos. 154.00 Each 462.00
(BMT-G.24)
Cost of Al. aldrop 250mm long (BMT- 1 No. 380.00 Each 380.00
G.41)
Cost of Al. handle 100mm long (BMT- 1 Nos. 82.00 Each 82.00
G.32)
Cost of heavy duty door stopper (BMT- 1 Nos. 61.00 Each 61.00
G57)
Cost of rubber bush 1 Nos. 14.00 Each 14.00
Labour charges :
Labour charges for frame work 0.0383 cum 8914.90 1 cum 340.99
Labour charges for fixing flush door 1.580 sq.m 265.00 1 sq.m 418.70
shutter to the frame , fixing the fixtures
to the shutter (BMM-V-23)
Add for MA @ % 0.00% 759.69 0.00
Add for nails & screws etc. 13.07
Rate for 1.89 sq.m 5845.17
Rate for 1 sq.m 3092.68
Over Heads & Contractor's profit @ 13.62% 3092.68 421.07
13.615%
VAT @ 5% 5.00% 3092.68 154.63
3668.39
Rate for 1 sq.m Say 3668.40
5 Supply and fixing of single shutter door of size 0.65x2.10m, frame and shutters made of rigid PVC extruded hollow
section (Nandi or equivalent) of 40mm x 57mm duly reinforced with seasoned wood plank at the hinges side (The
door frame top 2 corners shall be metri-cut/ welded) with the wall thickness of 2.0mm +/- 0.2mm equally divided into
4 No's with tongue and groove locking arrangements and door shutters made of rigid PVC extruded hollow section
(Nandi or equivalent) of 20mm X 200mm with the wall thickness of 1.0mm +/- 0.1mm equally divided into 4 no's
with tongue and groove locking arrangements shutter frame is made of 30mm x 79mm with the wall thickness of
1.5mm +/-0.15mm section miter-cut and joined at 4 corners with 125mm x 225mm plastic brackets. The shutter shall be
horizontally reinforced with 2 no's of 8mm PVC rods. Teak wood batons shall be reinforced inside the door shutter during
the fabrication of the door shutter at those points wherever the hardware is fixed onto the door shutter including fixing 3
Nos. of
Aluminium hinges 75mm long, 1 No. MS powder coated Al. Aldrop 150mm long, 1 No. Aluminium Tower bolt 100mm
long and 1No 75mm long Al. door handle including cost and conveyance of all materials, all taxes and labour charges for
making, fixing in position including all incidental charges etc., complete for finished item of work
Quantity analysis
Outer frame - Vertical 2x2.10
=4.20 Rmt 4.20 RM
Cost analysis
Supply and fixing of door frame made of 4.85 Rmt 254.00 1 Rmt 1231.90
hollow extruded PVC section (Nandi or
equivalent) having dimensions of 40 X
57mm BMT- N.46
Supply and fixing of door shutters made 1.170 sq.m 1923.00 1 sq.m 2249.91
of rigid PVC extruded hollow section
(Nandi or equivalent) of 20mm X
200mm (BMT-N.45)
Cost of Al. tower bolt 100 mm long 1 Nos. 92.00 Each 92.00
(BMT-G.07)
Cost of Al. Butt hinges 75 mm long 3 Nos. 108.00 Each 324.00
(BMT-G.23)
Cost of Al. aldrop 200mm long (BMT- 1 No. 319.00 Each 319.00
G.40)
Cost of Al. handle 75mm long (BMT- 1 Nos. 73.00 Each 73.00
G.31)
Rate for 1.575 sq.m 4289.81
Rate for 1 sq.m 3142.72
Over Heads & Contractor's profit @ 13.62% 3142.72 427.88
13.615%
VAT @ 5% 5.00% 3142.72 157.14
3727.74
Rate for 1 sq.m Say 3727.75
4 Providing and fixing 2 shutter Window of size 1.20x1.50m with with 1 central mullion with the following
specifications including cost and conveyance of all materials, all taxes and labour charges for making and fixing in
position, painting with black bitumen on wall side of frame and all incidential charges complete for finished item of work
etc., complete. 1) Frame made of sal wood of size 100 x 75mm, 2) Shutters with sal wood planks outer frame 75 x 35 mm
thick size and planks - 12mm thick, 2 Nos hold fasts, 3) 16mm dia. MS rods fixed to the frame @ 30cm interval
horizontally, 4) 2 Nos 75mm Aluminium hinges for shutter, 5) 2 Nos Aluminium tower bolts 75mm for shutter,6) 1No
Aluminium Handle for each shutter. (As per BLD-CSTN)
Quantity analysis
Frame :
Outer frame - Vertical 3 x 1.50
4.50 Rmt x 0.10 x 0.075 0.03375 Cum
Quantity analysis
Shutters frame Vertical = 4x (1.50-0.075-0.075+0.025) x0.075 x0.035 0.0144 Cum
Shutters frame Horiozontal =2x (1.20-0.075-0.075-0.075+0.025+0.025)0.505x 0.075x 0.035
0.00538 Cum
0.01982 Cum
Total frame 0.07157 Cum
1) Frame made of sal wood of size 100 x 0.07157 Cum 51994.00 1 Cum
75mm 3721.15
2) Shutters with sal wood planks outer 0.01193 Cum 69327.00 1 Cum
frame 75 x 35 mm thick size and planks
- 12mm thick, 2 nos hold fasts . 827.35
3) 16mm rods fixed to the frame @
30cm interval 17.06 kg 41555.71 1000 Kg 709.11
Cost of Al. Butt hinges 75 mm long
(BMT-G.23) 6 Nos. 89.00 Each 534.00
Cost of Al. tower bolt 100 mm long
(BMT-G.07) 6 Nos. 76.00 Each 456.00
Cost of Al. handle 75mm long (BMT-
G.31) 3 Nos. 60.00 Each 180.00
Cost of MS Z hold fasts 4 Nos. 15.00 Each 60.00
Labour charges 0.0835 cum 8914.90 1 Cum 744.42
7232.03
4017.79
Over Heads & Contractor's profit @ 4017.79
13.615% 13.62% 547.02
VAT @ 5% 5.00% 4017.79 200.89
4765.70
Rate for 1 sq.m Say 4765.75
6 Providing and fixing ventilators of size 0.60 x 0.60 m with frame made of Sal wood of size 75mm x 100mm and painting
with black bitumen on wall side with fixing of 16mm rods (2 Nos) in frame horizontally and Glass Louvers of 5mm thick
-2no.s including cost and conveyance of all materials, all taxes, labour charges for making and fixing in position
including all incidental charges etc., complete for finished item of work.
Quantity analysis
Outer frame - Vertical 2x 0.6
= 1.20 Rmt x 0.10 x 0.075 0.009 cum
Cost analysis
Cost of Sal wood frame (BMT-E.15) 0.0180 cum 51994.00 1 cum 935.89
Cost of MS Z hold fasts 2 Nos. 15.00 1 Each 30.00
Labour charges for frame work 0.0180 cum 8914.90 1 cum 160.47
2Nos - 16mm dia MS rods fixed to the 1.896 kg 41555.71 1000 Kgs 78.79
frame horizontally
Cost of glass 5mm thick for Louvers 0.120 Sqm 558.00 1 Sqm 66.96
Construction of MPCS (Type I-7.50T) at VADAPALEM Village, RAMBILLI Mandal of VISAKHAPATNAM District.
2 Wiring BLD-ELEC-2
2.1 Copper Wiring BLD-ELEC-2-1
67 2.1.1 Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire
Retardant (FR) P.V.C. insulated flexible copper cable
(ISI MARK) in existing pipe with 6A (Modular) switch
and G I Matel Conceld box to switch control box
including all labour charges etc.(For light,fan,exhaust
fan points )
Taking Output 6 Points
a) Material
14/0.3mm PVC FR flexible copper wire ELEC-1.5.1 100 Mt 1 1051.00 1051.00
6A Switch ELEC-1.9.1 each each 6 92.00 552.00
6A 2 way Ceiling Rose ELEC-1.7.15 each each 6 21.00 126.00
6 Module Metal Boxes ELEC-1.3.4 each each 1 130.00 130.00
6 Modular Cover Frame of GM each each 1 130.00 130.00
b) Labour charges :
Skilled Electrician day day 0.6 440.00 264.00
Semi skilled Electrician day day 1.2 375.00 450.00
Helpers day day 0.6 345.00 207.00
C) Cost for 6 Points 2910.0
Rate per Point = C/6 485.00
Over Heads & Contractor's profit @ 13.615% 66.03
VAT @ 5% 24.25
Rate per 1 RM 575.28
575.30
2 Wiring BLD-ELEC-2
2.1 Copper Wiring BLD-ELEC-2-1
69 3.1.2 Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C.
insulated flexible copper cable in existing pipe for earth
continuity including all labour charges etc., complete.
Taking Output 100 Mt
a) Material
14/0.3mm FR PVC copper wire ELEC-1.5.1 100 Mt 1 1051.00 1051.00
b) Labour charges :
Skilled Electrician day day 0.34 440.00 149.60
Semi Skilled Electrician day day 1 375.00 375.00
Helpers day day 0.34 345.00 117.30
Sundries 0
C) Cost for 100 RM 1692.90
Rate per Metre = C/100 16.93
Over Heads & Contractor's profit @ 13.615% 2.31
VAT @ 5% 0.85
Rate per 1 RM 20.08
20.10
Note : Labour Charges considered for 150 M / day
70 3.1.5 Supply and run of 2 of 56/0.3mm (4 Sq.mm) FR P.V.C.
insulated flexible copper cable in existing pipe for mains
inlcuding all labour charges etc., complete.
Taking Output 100 Mt
a) Material
56 /0.3mm (4 sqmm)FR PVC flexible copper wire. ELEC-1.5.4 100 Mt 2 3833.00 7666.00
b) Labour charges :
Skilled Electrician day day 1 440.00 440.00
Semi Skilled Electrician day day 3 375.00 1125.00
Helpers day day 1 345.00 345.00
Sundries
C) Cost for 100 RM 9576.00
Rate per Metre = C/100 95.76
Over Heads & Contractor's profit @ 13.615% 13.04
VAT @ 5% 4.79
Rate per 1 RM 113.59
Note : Labour Charges considered for 100 M / day 113.60
72 2.1.5 Supply and fixing of 16A 3pin / 6A 3pin plug socket with
indicator lamp and 16Amps fuse unit and 16 Amps switch
control (5 in one) on decolam sheet covered board including
earth connection and all labour charges etc., complete on
wall.
Taking Output 1 No
a) Material
20 x 15 cms (8" x6") Decolam sheet covered board ELEC-1.4.11 each each 1 44.00 44.00
16A 3 pin / 6A 3pin Plug socket with indicator lamp, fuse each each 1
ELEC-1.9.12
unit (5 in 1) 196.00 196.00
b) Labour charges :
Skilled Electrician day day 0.1 440.00 44.00
Helpers day day 0.1 345.00 34.50
Rate per each 318.50
Over Heads & Contractor's profit @ 13.615% 43.36
VAT @ 5% 15.93
Rate per 1 no 377.79
377.80
a) Material
Earth Work Excavation of Hard gravel Soil with small
boulder for trench 1st step of size 1.5 x 0.6 x 0.9 m ELEC-8.1.52 cum cum 0.85 220.00 187.00
(5'x2'x3')
Excavation of Hard disteggrated rocks and boulders for
trench 2nd Step of size 1.2 x 0.6 x 1.2 m (Civil SSR) ELEC-8.1.52 cum cum 0.9 220.00 198.00
(4'x2'x4')
25% extra for narrow trench & pit and back filling with
cum cum 0.25 385.00 96.25
Sand, Coke, Salt etc., and leveling
PCC(1:4:8) civil item cum cum 0.64 4966.58 3178.61
Brick Masonry (1:6) Pit of size 2' x 2' civil item cum cum 0.168 4289.65 720.66
Plastering with CM(1:4) 12 mm thick civil item sqm sqm 4.48 2527.17 1132.17
40mm dia 'B' Class G.I pipe ELEC-8.1.58 Mtr Mtr 2.5 381.00 952.50
25 x 6 mm (1"X 1/4") G.I Flat duly drilled 12mm holes (4 Each Each 1 61.60
Nos) of 200 mm (8") length ELEC-8.1.45 61.60
Drilling of 16 Nos through holes of 12mm dia to G.I pipe ELEC-8.1.63 Each Each 1 5.00 5.00
G.I Nuts, Bolts an Washers ELEC-8.1.64 Set Set 4 10.00 40.00
18" dia hume pipe ring ELEC-8.1.62 Each Each 1 275.00 275.00
Hard Coke ELEC-8.1.13 Kg Kg 40 9.00 360.00
Salt ELEC-8.1.14 Kg Kg 20 4.00 80.00
b) labour charges for fixing pipe ring and connections
Semi skilled Electrician Nos Nos 0.5 345.00 172.50
Helpers Nos Nos 0.5 345.00 172.50
Sundries 0.00
Rate per each 7631.79
Over Heads & Contractor's profit @ 13.615% 1039.07
VAT @ 5% 381.59
Rate per 1 no 9052.45
9052.45
a) Material
1 x 40W WP flourscent street light fitting. ELEC-3.1.2 each each 1 1300.00 1300.00
Lamp cost of 40W ELEC-3.7.16 each each 1 45.00 45.00
25mm dia G.I pipe ELEC-8.1.56 M M 1 242.00 242.00
23/0060 twin core flexible copper cable ELEC-1.6.8 M M 2 10.40 20.80
Pipe bending charges LS LS 20.00
M.S flat and welding charges LS LS 25.00
b) Labour charges
Skilled Electrician/carpenter day day 0.2 440.00 88.00
Mason day day 0.2 375.00 75.00
Semi skilled Electrician / Helper day day 0.2 375.00 75.00
Rate per each 1890.80
Over Heads & Contractor's profit @ 13.615% 257.43
VAT @ 5% 94.54
Rate per 1No 2242.77
Say 2242.80
Construction of MPCS (Type I-7.50T) at VADAPALEM Village, RAMBILLI Mandal of
VISAKHAPATNAM District.
Over Heads & Contractor's profit @ 13.615% 13.615%
VAT @ 5% 5%
Orissa Pan white glazed W.C 1st quality BMW-D.04 1 Each 1440.00 1
PVC low level systern parry ware, slim line 10 BMW-G.08 1 Each 1455.00 1
Litres capacity Single flush.
Providing brick masonry seat BMW-D 09 1 No 298.00 1 No
Add LA chrges - Labour charges only for fixing BMW-D 03 100.00%
Indian pattern W.C with "P" or "S" trap 281.00
Over Heads & Contractor's profit @ 13.615% 13.62% 3193.00
VAT @ 5% 5.00% 3193.00
Total rate per each 1.00
100. Task Code WS--961: - multi floor trap with Jali- UPVC/SWR Pipe fittings
4" (101.6 mm ) multi floor trap with Jali- BMW-G.119 1 Each 144.00 1 No
UPVC/SWR Pipe fittings (Prince/ Sudhakar or any
ISI Brand)
Over Heads & Contractor's profit @ 13.615% 13.62% 144.00
VAT @ 5% 5.00% 144.00
Total rate per each 1
Say
a) 110 mm dia
110 mm dia 3 M Single Socket PVC/SWR pipe - 4 BMW-G.13 1 Each 484.00 1 No
Kg/sq.cm
Over Heads & Contractor's profit @ 13.615% 13.62% 484.00
VAT @ 5% 5.00% 484.00
Total rate per 3 mt each 1
Rate per Rmt
b) 75 mm dia
75 mm dia 3 M Single Socket PVC/SWR pipe - 4 BMW-G.11 1 Each 255.00 1 No
Kg/sq.cm
Over Heads & Contractor's profit @ 13.615% 13.62% 255.00
VAT @ 5% 5.00% 255.00
Total rate per 3 mt each 1
Rate per Rmt
25mm OD
KITEC (PE-AL-PE) composite pressure pipes of BMW-I.203 1 RM 244 1 RM
25mm OD
Over Heads & Contractor's profit @ 13.615% 13.62% 244.00
VAT @ 5% 5.00% 244.00
Total rate per 1 Rmt 1
Say
20mm OD
KITEC (PE-AL-PE) composite pressure pipes of BMW-I.204 1 RM 195.00 1 RM
20 mm dia OD
Over Heads & Contractor's profit @ 13.615% 13.62% 195.00
VAT @ 5% 5.00% 195.00
Total rate per 1 Rmt 1 1
Say
16mm OD
KITEC (PE-AL-PE) composite pressure pipes of BMW-I.204 1 RM 157.00 1 RM
20 mm dia OD
Over Heads & Contractor's profit @ 13.615% 13.62% 157.00
VAT @ 5% 5.00% 157.00
Total rate per 1 Rmt 1 1
Say
RCC terrazzo finished sink 609.6 x 457.2 x 254 BMW-D.40 1 Each 719.00 1 No
mm
Add LA 0.00% 184.00
Over Heads & Contractor's profit @ 13.615% 13.62% 719.00
VAT @ 5% 5.00% 719.00
Total rate per Each 1
Material
Supply of SWG SP-1 pipe conforming to ISI 651 -
4" dia (101.6mm) BMW-A.15 1 Rm 181.00 1 Rm
labour charges BMW-A.05 1 Rm 216.00 1 Rm
Over Heads & Contractor's profit @ 13.615% 13.62% 397.00
VAT @ 5% 5.00% 397.00
Total per 1.00 Rm 1
Say
22 Supply & fixing European water closet of I st quality confirming to IS:2556-part-2-1973 of Hindusthan
/Neycer or Parryware make white Glazed with P Trap complete.for finished item of work.
BMW-D.13 Supplying & Fixing European water closet 1st Each 1691.00 1.000 1691.00 ###
quality ISI marked conforming to IS:2556-Part-2-
1973 with "P"
(BMW-D 15)labour charges for fixing European water closet Each 246.00 1.00 246.00
with P or S trap as per Standard Practice
BMW-D16 Supply &fixing best Indian make plastic lid for Each 461.00 1.00 461.00
EWC with rubber or Plastic buffer
BMW-D17 labour charges for fixing Plastic lid forEuropean Each 71.00 1.00 71.00
water closet
BMW-G08 PVC low level systern parry ware, slim line 10 Each 1455.00 1.000 1455.00
Litres capacity Single flush.
(BMW-D 12)labour charges only for fixing low down porcelin Each 491.00 1.00 491.00
flushing tank with internal components
4415.00
Over Heads & Contractor's profit @ 13.615% 4415.00 14.00% 618.10
VAT @ 5% 4415.00 5.00% 220.75
Total rate per each 1 5253.85
Manufacture, supply, & delivery of 40mm dia 8kg/sqcm HDPE pipes conforming to IS 4984 - 1995
including transportation to any where in A.P, excluding specials etc., complete.including cost and
conveyance of all materila, all labour charges, and all taxes.
Code Material Unit Rate CoefficientAmount
Cost of 40mm dia HDPE pipe as per table 17 ( I) of SSR Rmt 59.00 1 59.00
(PH)
Add CED at 16.32% on PVC pipe 9.63
68.63
Supply of 2.5 Sqmm 3/20 WPSC (Weather Proof Single Core ) ISI Alluminium Wire Finolex /
Polycab / Gold Medal / Million / Payal / Power Flex make for service mains including cost of material
and labour charges and taxes etc., complete.
Supply of 2.5 Sqmm 3/20 WPSC (Weather Proof Single 7.37
ELEC-1.6.1 Core ) Rmt 7.37 1
Supply of 3 Core 1.5 Sqmm Flat Copper cable of ISI for Submersible Motors of makes Finolex /
Polycab / Gold Medal / Million / Payal / Power Flex / Fortune Art make including cost of material and
labour charges and taxes etc., complete.
ELEC-1.6.9 Supply of 3 Core 1.5 Sqmm Flat Copper cable Rmt 57.17 1 57.17
24 supply & fixing indian make flat back wash hand basin (HSW/parry ware/Neycer) 1 st quality confirming to
IS:2556-part-4-1972 with waste fittings like rubber plug ,chain,32mm nominal size CP fittings with parallel
pipe thread conforming to IS:2963-1979 and fitted with 15mm nominal bore Chromium plated pillar tap of 1
st quality Indian make 400 grams seiko/senior/nice or Equivalent complete with standard CI brakets including
wooden block:550x400 mm -Single CP Pillar Cock complete for finished item of work.
BMW-D.24 Supply & fixing low down porcelin flushing tank Each 1620 1.000 1620.00
10 lit capacity Hindustan sanitary w
(BMW-D 28 labour charges for fixing indian make flat back Each 351 1.00 351.00
wash hand basin with waste fittings like rubber
plug,chain,32mm nominal size CP fitting pillar
taps complete with standard CI brakets
incl.Wooden block.
1971.00
Over Heads & Contractor's profit @ 13.615% 1971.00 14.00% 275.94
VAT @ 5% 1971.00 5.00% 98.55
Total rate per each 1 2345.49
Supply and erecting, ISI mark submersible pumpset of 1.00HP suitable for 4" Bore well. Makes:
Kirloskar / Crompton / CRI / L&T / Texmo / Varsha with high quality water resistant and dynamically
balanced bronze impeller with stainless steel shaft sleeves, pump coupling and pivot of Single phase
250V, 50Hz.. A.C. power supply copper winding with water proof insulation and high precision strength
not to be effected by chemical in water and suitable bronze bearings with nut and bolts etc., with
necessary H-type clamp of suitable size and strength.
Add 13.615% overhead charges Cum Contractor profit 17587.50 0.13615 2394.54
19982.04
VAT : 5.00% 19982.04 0.05 999.10
20981.14
Total per 1.00 No 1 20981.14
0T) at VADAPALEM Village, RAMBILLI Mandal of
KHAPATNAM District.
1440.00
1455.00
298.00
281.00
434.73
159.65
4068.38
258.00
0.00
35.13
12.90
306.03
144.00
19.61
7.20
170.81
170.85
484.00
65.90
24.20
574.10
191.40
255.00
34.72
12.75
302.47
100.85
568.00
77.33
28.40
673.73
673.75
5396.00
734.67
269.80
6400.47
6400.50
244.00
33.22
12.20
289.42
289.45
195.00
26.55
9.75
231.30
231.30
157.00
21.38
7.85
186.23
186.25
621.00
0.00
84.55
31.05
736.60
914.00
0.00
124.44
45.70
1084.14
719.00
0.00
97.89
35.95
852.84
451.00
0.00
61.40
22.55
534.95
26.00
3.54
1.30
30.84
30.85
4500.00
612.68
225.00
5337.68
355.85
499.00
81.44
81.26
29.02
690.72
690.75
5145.00
102.90
192.50
345.00
220.00
817.64
300.27
7123.31
7123.35
181.00
216.00
54.05
19.85
470.90
470.90
DATA SHEET ( 2014 - 15 )
842.22
Over hed charges @ 13.615%
7028.22
Vat 5% 351.41
7379.64
Total 7379.64
597.15
Over hed charges @ 13.615%
4983.15
Vat 5% 249.16
5232.31
Total kgs
Total
Add contractors profit & Over heads @ 13.615%
Add VAT @5%
Rate per 1 sqm
7.137
0.720
0.4416
0.552
13.873
4453.23
400
500
1092.00
780
1861.2
100
200
80
2001.6
11468.03
6371.13
133.60
359.49
119.72
119.72
307.39
347.22
322.22
128.47
6.65
350.00
8565.62
1166.209
428.28
10160.11
RATE ANALYSIS FOR ROAD FURNITURE(SSR 2014-15)
S.
Description of item Unit Qty Rate Amount
No.
RBR-FNDN-1
Excavation of structures
1 Earth work in excavation for foundation of structures upto 3m depth as per drawings &
technical specification clause 300/305/1104 of MoRD including setting out, construction of
shoring, shuttering & bracing removal of stumps & bottom & back filling with approved
excavated suitable material including royalty and all taxes etc complete as per direction of
Engineer-in-Charge (RBR-FNDN-1 / RBR - PCVT - 1)
1 Ordinary soil
Manual Means
Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64 295.00 1073.80
sub Total 1073.80
Add for Over head charges & Contractors profit 13.615%
146.2
@
Add VAT @ 5% 7.31
Seignorge charges 10.00 20.95 209.50
Cost for 10 cum = a+b+c+d 1436.81
Rate per cum 143.68
RBR-SBST-6
2 Supplying, fitting and placing HYSD bar reinforcement of Fe 500 grade TMT steel coated
with cement slurry in substructure complete as per drawings and technical specification
Clauses 1002, 1005, 1010 & 1202 MORD/Sections 1600 & 2200 MORTH for bars below
36mm dia. including over laps and wastage, where they are not welded including cost of all
materials, labour, conveyance, hire charges of machinary, royalties, all taxes etc., complete as
per direction of Engineer in charge (RBR-SBST-6).
Unit 1t
a) Materials
HYSD bars including 5% over laps and wastage MT 1.050 40055.71 42058.50
Binding wire (sl. No.172 of R&B ssr) Kgs 6.00 70.00 420.00
b) Labour
Mate day
Blackmith day 2.00 385.00 770.00
Mazdoor (Un-skilled) day 6.84 295.00 2017.80
Rate per 1 MT 45266.30
c) Add for Over head charges & Contractors profit 13.615% 6163.01
@
Add VAT @ 5% 308.15
Rate per 1 MT 51737.46
RBR-TSRA-9
Painting on Cobcreta/Steel surfaces with epoxy
3 Painting two coats including prime coat with epoxy paint of approved brand on concrete/steel
surfaces after through cleaning of surface to give an even shade as per drawing and Technical
Specification Clause 1701 MORD including over laps and wastage, where they are not
welded including cost of all materials, labour, conveyance, hire charges of machinary,
royalties, all taxes etc., complete as per direction of Engineer in charge (RBR-TSRA-9).
Unit 1 sqm
10
Taking output
sqm
a) Labour
Mate day
Painter (1st class) day 0.60 440.00 264.00
Mazdoor (Un-skilled) day 0.65 295.00 191.75
b) Materials
Epoxy primer/red oxide (BMT-J-03) ltr 0.60 105.00 63.00
Epoxy paint ltr 1.25 152.00 190.00
Total (a+b) 708.75
Rate per 1 Sqm 70.88
70.88
RBR-TSRA-6
Painting two coats on New Concrete Surfaces
4 Painting two coats including prime coat after filling the surface with synthetic enamel paint in
all shades on new plastered/concrete surfaces as per drawing and technical specification
clause 1701 of MORD including cost of all materials, labour, conveyance, hire charges of
machinary, royalties, all taxes etc., complete as per direction of Engineer in charge (RBR-
TSRA-6).
Unit 1 sqm
40
Taking output
sqm
a) Labour
Mate day 0.00
Painter (1st class) day 3.00 440.00 1320.00
Painter Assistant day 0.00
Mazdoor (Un-skilled) day 2.20 295.00 649.00
b) Materials
Cement primer as per specification ltr 3.00 117.00 351.00
Paint conforming to requirement of Clause 1701.3.8 ltr 6.00 152.00 912.00
RBR-TSRA-13
RBR-TSRA-4 B
NCRMP Information board of size 1500mm x 900mm
6 Providing and erecting direction and place identification of semi reflective sign boards as per
as per IRC 67 made of 2 mm thick MS sheet duly stove enameled paint white colour in front
and grey colour on back with reflective border of 70mm width& required message letters &
figures with reflective tape engineering grade as per MoRD specifications of required shade
& colour supported & welded on two numbers 47mmX47mmX12SWG sheet tube of 3050
mm height including MS angle of 50 x 50 x 6 mm for lugs duly strengthened by 25 mm x 5
mm MS flat alround on edges on back firmly fixed to ground by mean of property designed
foundation with M-20 grade cement concrete 450mmX600mmX600mm below ground level
as per approved drawing clause 1701 including cost, conveyance, taxes of all materials
required & fixing at site as per approved drawing & direction of Engineering in charge for
NCRMP Information board of size 1500mm x 900mm (RBR-TSRA-4 B).
Unit 1Nos
Taking output 1Nos
i Excavation for foundation cum 0.324 125.87 40.78
ii Cement Concrete M20 grade cum 0.324 4966.58 1609.17
c) Machinery
Tractor with trolley hour 0.16 425.00 68.00
Total 8496.72
Add for Over head charges & Contractors profit 13.615%
d) 1156.83
@
9653.55
Add VAT @ 5% 482.6775
Cost for each 10136.228
Cost for each 10136.228
Deputy.Exe.Engineer Asst.Exe.Engineer
PIU YELLAMANCHILLI PIU YELLAMANCHILLI
b) Side walls 150mm thick - Sump and Septic tank 0.00 Sqm 2040.30 1 Sqm 0.00
c) Staircase waist slab - 150mm thkick 0.00 Sqm 1398.40 1 Sqm 0.00
S.No Description of Item Qnty Unit Rate Per Amount
d) Base Slab 150mm - Sump and Septic Tank 1.00 Sqm 1077.45 1 Sqm 1077.00
b) For Cattle Ramp basement upto GL 0.81 Sqm 624.25 1 Sqm 506.00
S.No Description of Item Qnty Unit Rate Per Amount
16 Flooring with 7.3mm thick Ceramic floor tiles of
approved brand colour shade and design of size 400 x
400 mm laid over floor bed /VRCC slab set over 12.0
mm th.in CM (1:8 ) prop. base coat and neat grey cement
slurry of honey like consistence spread at the rate of 3.3
kg of cement per Sqm and jointed with neat white cement
paste mixed with pigment of matching shade including
cost all taxes and conveyance of all materials to site
seignorage fee including all mixing mortar and watering,
leveling to proper slope and curing including all labour
charges etc., for finished item of work. (As per BLD-
CSTN)
For Sump & Septic tank 13.23 Sqm 365.50 1 Sqm 4836.00
S.No Description of Item Qnty Unit Rate Per Amount
23 Providing and fixing of single shutter door of size 1.05
x 2.00 m made with frame of Sal wood of size 75mm x
100mm with 6 Nos. of hold fasts (3 on each side) and
painted with liquid bitumen on wall side and with flush
shutter of hard wood solid bond wood block board type
of 35mm thick commercial ply on both sides confirming
to IS 2202 including 3 Nos Aluminium butt Hinges
(150mm), 1 No. Aluminium Tower bolt (250mm) at top,
1 No. Aluminium Aldrop (250mm long), 1 No
Aluminium Handle (100 mm long), 1 No Al. heavy duty
door stopper and 1 No. rubber bush on wall face of door
including cost and conveyance of all materials, all taxes,
labour charges for making, fixing of fixtures and door
frame and shutter in position and all incidental charges
etc., complete for finished item of work.
Total #REF!
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
Same as out side plastering + Plastering for elevation 280.00 Sqm 143.50 1 Sqm 40180.00
Dadooing in Gents and Ladies toilets and Kitchen platform 170.00 Sqm 677.50 1 Sqm 115175.00
For Doors, Windows and Ventilators 112.51 Sqm 150.75 1 Sqm 16961.00
Total #REF!
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
Same as out side plastering + Plastering for elevation 370.00 Sqm 143.50 1 Sqm 53095.00
Dadooing in Gents and Ladies toilets and Kitchen platform 160.00 Sqm 683.80 1 Sqm 109408.00
For Doors, Windows and Ventilators 64.19 Sqm 150.75 1 Sqm 9677.00
Total #REF!
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
Cyclone Shelter (Type - B)
Abstract Estimate - Head Room
S.No Description of Item Qty. Unit Rate Per
1 VRCC M30 Grade Design mix using well graded aggregate with
maximum nominal size of aggregate(MSA) of 20mm HBG machine
crushed and duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be not less than 325
Kg/cum, with maximum water-cement ratio of 0.45, including Super
plasticizer admixture IS marked as per 9103-1999 (as approved by
Engineer) including cost and conveyance of all materials to site,
seignorage fee, machine mixing, concrete laying, tamping, centering
using Steel scaffolding pipes , jack props , wallers , Foot plates ,
brackets , steel centering plates etc., weigh batching, vibrating,
watering, curing and all labour charges for all operations, all taxes, hire
and operational charges of machinery and water lead charges etc., but
excluding cost of steel and its fabrication complete for finished item of
work for Columns, Lintels, Water Tanks, RCC Walls in Buildings.
(As per BLD-CSTN)
2 VRCC M30 Grade Design mix using well graded aggregate with
maximum nominal size of aggregate(MSA) of 20mm HBG machine
crushed and duly down graded; cement (Portland Slag Cement
confirming to IS 455-1989) content in the mix to be not less than 325
Kg/cum, with maximum water-cement ratio of 0.45, including Super
plasticizer admixture IS marked as per 9103-1999 (as approved by
Engineer) including cost and conveyance of all materials to site,
seignorage fee, machine mixing, concrete laying, tamping, centering
using Steel scaffolding pipes , jack props , wallers , Foot plates ,
brackets , steel centering plates etc., weigh batching, vibrating,
watering, curing and all labour charges for all operations, all taxes, hire
and operational charges of machinery and water lead charges etc., but
excluding cost of steel and its fabrication complete for finished item of
work for RCC Slabs and Beams (As per BLD-CSTN)
11 Painting to New wood work with two coats of ready mixed first quality
synthetic enamel paint Grade I of approved quality, colour, brand and
shade over a primary coat of red oxide Grade II total three coats in all to
give an even shade after throughly brushing the surface to remove all
dirt and remains of loose powdered materials, using brushes, including
cost and conveyance of all material to site, all taxes, and including all
required material, all labour charges, curing, scaffolding etc., complete
for finished item of work. (As per BLD-CSTN)
14 Supply and fixing of 110mm dia. ISI mark PVC rain water spouts of
4mm thick including cost of necessary PVC bends, shoes and PVC
clamps and all other accessories and fixing in position including cost
and conveyance of all materials to site, seigniorage charges sales and
other taxes on all materials, all operational , incidental and labour
charges such as fixing in alingment etc., complete for finished item of
work. (As per BLD-CSTN)
120.00 Rmt 335.40 1 Rmt
Total
ter At VADAPALEM of Rambilli Mandal
one Shelter (Type - B)
ct Estimate - Head Room
Amount
29337.00 C
4807.00 C
21691.00 C
89079.00 C
51426.00 C
264119.00
Amount
104065.00
19834.00
13062.00
37310.00
11912.00
Amount
8728.00
13495.00
380.00
Amount
155800.00
300532.00
40248.00
1165825
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
Soak pit @ 20% of brick bats 2.00 Cum 843.60 1 Cum 1687.00
Total 38799
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
Abstract Estimate - Water Supply & Sanitary
Total 172216
Construction of Cyclone Shelter At VADAPALEM of Rambilli Mandal
2 Supply and Fixing of 25mm dia 1.5mm thick surface P.V.C. pipe (ISI
MARK) with all accessories fixing on chromium plated metallic base
saddles including all labour charges etc., complete for run of mains. 155.00 RM 71.60 One RM 11098.00
3 Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant (FR) P.V.C.
insulated flexible copper cable (ISI MARK) in existing pipe with 6A
switch, Ceiling rose and 3mm thick hylam sheet covering to switch control
box including all labour charges etc., complete for light, bell, fan and
exhaust fan points in Non-Residential Buildings
36.00 Point 575.30 One Point 20711.00
7 Supply and fixing of 6A 3 pin wall plug socket with 6A switch control on a
common switch board with earth continuity including wire leads, earth
connections along with all labour charges etc., complete. 13.00 Nos. 115.80 One Each 1505.00
8 Supply and fixing of 16A 3pin / 6A 3pin plug socket with indicator lamp
and 16Amps fuse unit and 16 Amps switch control (5 in one) on decolam
sheet covered board including earth connection and all labour charges etc.,
complete on wall.
4.00 Nos. 377.80 One Each 1511.00
9 Supply and fixing of 6A 3pin wall plug socket with 6 A switch control on a
industrial/separate switch board with earth continuity including wire leads,
earth connections along with all labour charges etc., complete on decolam
sheet/sunglass covered board.
8.00 Point 198.70 One Point 1590.00
10 Supply and erecting Stepped type electronic Regulator for ceiling fans
900/1200/1400mm sweep complete erected on existing board. 10.00 Nos 301.90 One No 3019.00
Sl. Amount
Description of Item Qty. Rate Unit
No. Rs.
11 Supply of 900 mm (36") / 1200 mm (48") / 1400 mm (56") sweep 230V,
A.C 50 Hz.Ceiling fan with 3 Blades and double ball bearings with all
standard accessories. 10.00 Nos 2420.00 One No 24200.00
13 Supply and transportation of 1x36/40W box type tube light luminaire with
copper/VPIT Choke, condenser, starters, tube etc., complete as per IS
standards. 26.00 Nos 962.00 One No 25012.00
14 Fixing of 40W tube light luminaire on wall / ceiling with T.W. round
blocks with all accessories including giving connections and all labour
charges etc., complete. 26.00 Nos 126.50 One No 3289.00
15 Supply of IS make fresh air exhaust fan of light duty 250V A.C. 50Hz
300mm size (12") 1350 RPM Metallic body plastic blades, wire mesh, etc.,
complete 2.00 Nos 3168.74 One No 6337.00
16 Labour charges for fixing of Exhaust fan in all with necessary connections
and masonry work of making hole, finishing etc., complete.
2.00 Nos 534.15 One No 1068.00
17 Supply and fixing of 3-Phase Meter Board with 18" x30" size Peta Board
with 3 No. of 32A, 415 V Fuse Unit and 32A Standard make including
giving internal connections 1.00 No 3027.30 One No 3027.00
21 Supply and fixing TPN Distribution board with IP-20 protection suitable
for 3 phase ELCB / RCCB / FP Isolator as incomer and 10kA SP MCBs as
outing going including internal connection and labour charges for surface /
flush mounting etc., complete.
1 No 6756.35 One No 6756.00