Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
The tests are carried out by independent Fabricated junctions occur in both copper
testers, using pumps that adequately and steel pipe systems. Early copper pipe
simulate the performance of a fire authority systems used prefabricated joints and later
pump. Verification that reasonable vehicle systems were fabricated on-site. Fabricated
access is available will also be required. steel pipe systems were typically above-
ground systems and used square elbows.
These tests also enable confirmation that the
maximum friction loss of 150 kPa in the Where no test duration is specified in the
pipework between the booster connection Table above, the time should be sufficient to
and the most hydraulically disadvantaged allow all joints in the system to be inspected
hydrant is not exceeded. and should not be less than 2 hours.
Some sources in the table above use terms
Commissioning and testing – such as 'no significant leakage' or 'no
Alterations to existing installation leakage'. In practice, it is very difficult to
Test criteria for new installations may not be achieve complete water tightness.
appropriate for an existing installation. However, leaks should be monitored, as they
Where alterations to an existing installation have the potential to affect the maintenance
are carried out, the RBS should ensure that and reliability of the system. Minor leakage
independent testing has been carried out that does not affect the performance of the
and that it demonstrates compliance with system during a flow test will not impact on
appropriate test criteria, or that the Chief operational firefighting. If the rate of leakage
Officer has granted consent under regulation increases with time, the source of the leak
129 to non-compliance with some or all of should be located and repair work carried
the required testing. out before system failure occurs.
This process must be completed before If the leakage rate is constant and reduces
issuing an occupancy permit or certificate of with a reduction in pressure, the leak is likely
final inspection. to be through a valve bonnet, or similar. In
Where a new booster connection is installed, this case, 'topping up' during a test to
the test criteria applicable to a new system maintain the pressure is acceptable,
must be applied to the whole system served provided that the leakage rate is less than 15
by the booster connection. L/minute.
Where an existing booster connection serves If the hydrostatic test criteria applicable at
new pipework extended from existing the time of installation cannot be
pipework, only the new pipework must meet established, an alternative is to determine
the test criteria applicable to a new system. the working pressure by testing.
However, in order to apply these test criteria Multiply the result by a factor of 1.5 to give a
to the new pipework, some existing hydrostatic test pressure which provides a 50
pipework may need to be upgraded. Refer to per cent safety margin, including an
Appendix 1 -Hydrostatic test allowance for water hammer.
Notes: Where operation dates of legislation
overlap, the highest requirements should be
applied.
Appendix One –
Hydrostatic test
Operation dates of Source Hydrostatic test pressure
legislation requirements – greater of
1 May 2006 to present AS 2419.1-2005 1700 kPa or 1.5 x highest
working pressure for at least 2
Published 26 November 2006.
hours
Called up in Building Code of
Australia 2006.
1 Nov 1994 AS 2419.1-1994 1700 kPa or 1.5 x highest
working pressure for at least 2
to 1 May 2006 Published 18 July 1994. Called
hours.
up in Building Code of Australia
1990, 1996, 2004 and 2005.
8 April 1991 to AS 2419.1-1988 1400 kPa or 1.5 x highest
working pressure for 2 hours.
31 Oct 19941 Published 17 June 1988. Called
up in Building Code of Australia
1990.
1 Feb 1987 to Victoria Water Supply and System with fabricated branch
Sewerage Plumbing Regulations junctions2 - 1700 kPa.
1 July 19941
1986 (S.R. 330/1986) Other pipework - 700 kPa or
mains pressure.
29 June 1983 Melbourne and Metropolitan System with fabricated branch
Board of Works Act 1958 By- junctions2 - 1700 kPa.
to 1 Feb 1987
Law No. 193: Water Supply (S.R. Other pipework - 700 kPa or
116/1983). mains pressure.
Not called up in AS 2419 - 1980 1400 kPa or 400 kPa greater than
legislation highest working pressure where
Published 31 December 1980.
the working pressure is greater
than 1000 kPa.