FAJAR ERATIMUR SDN BHD

KERJA-KERJA MENAIKTARAF DI DEWAN UNDANGAN NEGERI PULAU PINANG.

ID Task Task Name Cost Duration Start Finish % %Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021
Mode Complete
Schedule F M A M J J A S O N D J F M A M J J A S O N D J F
1 KERJA-KERJA MENAIKTARAF DI DEWAN UNDANGAN RM3,673,000.00 599.63 days Wed 3/13/19 Mon 1/11/21 44% 52%
NEGERI PULAU PINANG.
2 MILIK TAPAK RM0.00 0 days Wed 3/13/19 Wed 3/13/19 100% 100% 3/13
3 PRELIMINARIES RM160,073.00 481.25 days Wed 3/13/19 Tue 9/1/20 59% 87%
4 Initial (Insurance & Others) RM8,000.00 14 days Wed 3/13/19 Thu 3/28/19 100% 100%
5 Setting Out & Survey RM8,000.00 14 days Thu 3/28/19 Fri 4/12/19 100% 100%
6 Temporary Site Access RM4,773.00 14 days Thu 3/28/19 Fri 4/12/19 100% 100%
7 Hoarding & Project Signages RM8,000.00 14 days Thu 3/28/19 Fri 4/12/19 100% 100%
8 Site Office & Facilities RM12,000.00 14 days Thu 3/28/19 Fri 4/12/19 100% 100%
9 Contractor's Temporary Accomodation & Facilities
RM23,800.00 14 days Thu 3/28/19 Fri 4/12/19 100% 100%
10 Site Recurring (Services & Maintenances) RM95,500.00 453.25 days Sat 4/13/19 Tue 9/1/20 51% 83%
11 Appointment of NSC RM0.00 0 days Mon 7/1/19 Mon 7/1/19 100% 100% 7/1
12 CONSERVATION WORKS RM2,498,027.00 599.63 days Wed 3/13/19 Mon 1/11/21 45% 44%
13 Design Process, Method of Statement & PE Endorsement
RM3,000.00 21 days Wed 3/13/19 Fri 4/5/19 100% 100%
14 Review and Approval RM0.00 9 days Fri 4/5/19 Mon 4/15/19 100% 100%
15 Historical Architecture Building Survey, HABS RM153,540.00 585.63 days Thu 3/28/19 Mon 1/11/21 34% 34%
16 HABS 1 RM41,000.00 84 days Thu 3/28/19 Sat 6/29/19 100% 100%
17 Zone Left 1 RM5,000.00 14 days Thu 3/28/19 Fri 4/12/19 100% 100%
18 Zone Left 2 RM5,000.00 14 days Sat 4/13/19 Mon 4/29/19 100% 100%
19 Zone Centre RM5,000.00 14 days Mon 4/29/19 Tue 5/14/19 100% 100%
20 Zone Right 2 RM5,000.00 14 days Tue 5/14/19 Thu 5/30/19 100% 100%
21 Zone Right 1 RM5,000.00 14 days Thu 5/30/19 Fri 6/14/19 100% 100%
22 Report RM16,000.00 14 days Fri 6/14/19 Sat 6/29/19 100% 100%
23 HABS 2 RM61,000.00 436.38 days Tue 5/14/19 Mon 9/14/20 30% 30%
24 Zone Left 1 RM9,000.00 235.63 days Tue 5/14/19 Sat 2/1/20 86% 86%
25 Zone Left 2 RM9,000.00 236.38 days Tue 5/14/19 Mon 2/3/20 0% 0%
26 Zone Centre RM9,000.00 70 days Mon 2/3/20 Tue 4/21/20 0% 0%
27 Zone Right 2 RM9,000.00 60 days Tue 4/21/20 Sat 6/27/20 0% 0%
28 Zone Right 1 RM9,000.00 50 days Sat 6/27/20 Sat 8/22/20 0% 0%
29 Report RM16,000.00 20 days Sat 8/22/20 Mon 9/14/20 0% 0%
30 HABS 3 RM51,540.00 82 days Sun 10/11/20 Mon 1/11/21 0% 0%
31 Zone Left 1 RM6,000.00 10 days Sun 10/11/20 Thu 10/22/20 0% 0%
32 Zone Left 2 RM6,000.00 10 days Thu 10/22/20 Tue 11/3/20 0% 0%
33 Zone Centre RM6,000.00 10 days Tue 11/3/20 Fri 11/13/20 0% 0%
34 Zone Right 2 RM6,000.00 10 days Fri 11/13/20 Wed 11/25/20 0% 0%
35 Zone Right 1 RM6,000.00 10 days Wed 11/25/20 Sat 12/5/20 0% 0%
36 Draft Report RM5,000.00 14 days Sat 12/5/20 Tue 12/22/20 0% 0%
37 Review and Comment By Architect RM0.00 10 days Tue 12/22/20 Sat 1/2/21 0% 0%
38 Final Draft Report RM5,000.00 7 days Sat 1/2/21 Sat 1/9/21 0% 0%
39 Submit Hard Cover Report RM11,540.00 1 day Sat 1/9/21 Mon 1/11/21 0% 0%
40 Scientific Testing and Analysis RM13,700.00 107 days Thu 3/28/19 Fri 7/26/19 100% 100%
41 Collect Sample & Analyse RM0.00 15 days Thu 3/28/19 Sat 4/13/19 100% 100%
42 Materials Approval RM2,000.00 21 days Mon 4/15/19 Wed 5/8/19 100% 100%
43 X-Ray Fluorescence & Rebound Hammer Test RM5,000.00 21 days Thu 5/9/19 Sat 6/1/19 100% 100%
44 Ion Chromatography Test RM5,000.00 21 days Thu 5/9/19 Sat 6/1/19 100% 100%
45 Paint Scheme Analysis RM1,000.00 21 days Tue 6/25/19 Thu 7/18/19 100% 100%

Task External Tasks Manual Task Finish-only Baseline Milestone


Split External Milestone Duration-only Deadline Baseline Summary
Project: CPM rev 0.1
Date: Fri 12/27/19 Milestone Inactive Task Manual Summary Rollup Critical Progress
Summary Inactive Milestone Manual Summary Critical Split Manual Progress
Project Summary Inactive Summary Start-only Baseline

Page 1
FAJAR ERATIMUR SDN BHD

KERJA-KERJA MENAIKTARAF DI DEWAN UNDANGAN NEGERI PULAU PINANG.

ID Task Task Name Cost Duration Start Finish % %Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021
Mode Complete
Schedule F M A M J J A S O N D J F M A M J J A S O N D J F
46 Report RM700.00 7 days Thu 7/18/19 Fri 7/26/19 100% 100%
47 Restoration & Renovation of Existing Roofing RM810,634.00 432.75 days Mon 4/15/19 Tue 8/11/20 37% 35%
48 Clear Interial of Existing Building RM3,000.00 14 days Mon 4/15/19 Wed 5/1/19 100% 100%
49 Zone Left 1 RM130,526.80 262 days Mon 4/15/19 Mon 2/3/20 88% 88%
50 Temporary Roof RM20,400.00 14.75 days Mon 4/15/19 Wed 5/1/19 100% 100%
51 Roof Construction RM35,574.80 220 days Wed 5/1/19 Thu 1/2/20 98% 98%
52 Roof Finishes RM53,392.00 14 days Thu 1/2/20 Fri 1/17/20 0% 0%
53 Strengthening Works RM21,160.00 14 days Sat 1/18/20 Mon 2/3/20 0% 0%
54 Zone Left 2 RM130,526.80 265.38 days Mon 4/15/19 Wed 2/5/20 6% 0%
55 Temporary Roof RM20,400.00 15.5 days Mon 4/15/19 Wed 5/1/19 100% 0%
56 Roof Construction RM35,574.80 220.75 days Wed 5/1/19 Fri 1/3/20 0% 0%
57 Roof Finishes RM53,392.00 14.5 days Sat 1/4/20 Mon 1/20/20 0% 0%
58 Strengthening Works RM21,160.00 14.63 days Mon 1/20/20 Wed 2/5/20 0% 0%
59 Zone Centre RM130,526.80 60 days Wed 2/5/20 Mon 4/13/20 0% 0%
60 Temporary Roof RM20,400.00 15 days Wed 2/5/20 Sat 2/22/20 0% 0%
61 Roof Construction RM35,574.80 15 days Sat 2/22/20 Tue 3/10/20 0% 0%
62 Roof Finishes RM53,392.00 15 days Tue 3/10/20 Fri 3/27/20 0% 0%
63 Strengthening Works RM21,160.00 15 days Fri 3/27/20 Mon 4/13/20 0% 0%
64 Zone Right 2 RM130,526.80 60 days Mon 4/13/20 Fri 6/19/20 0% 0%
65 Temporary Roof RM20,400.00 15 days Mon 4/13/20 Wed 4/29/20 0% 0%
66 Roof Construction RM35,574.80 15 days Wed 4/29/20 Sat 5/16/20 0% 0%
67 Roof Finishes RM53,392.00 15 days Sat 5/16/20 Tue 6/2/20 0% 0%
68 Strengthening Works RM21,160.00 15 days Tue 6/2/20 Fri 6/19/20 0% 0%
69 Zone Right 1 RM130,526.80 60 days Mon 4/13/20 Fri 6/19/20 0% 0%
70 Temporary Roof RM20,400.00 15 days Mon 4/13/20 Wed 4/29/20 0% 0%
71 Roof Construction RM35,574.80 15 days Wed 4/29/20 Sat 5/16/20 0% 0%
72 Roof Finishes RM53,392.00 15 days Sat 5/16/20 Tue 6/2/20 0% 0%
73 Strengthening Works RM21,160.00 15 days Tue 6/2/20 Fri 6/19/20 0% 0%
74 Maintenance Platform RM155,000.00 418 days Wed 5/1/19 Tue 8/11/20 44% 44%
75 Design Process & Shop Drawing RM20,000.00 14 days Wed 5/1/19 Thu 5/16/19 100% 100%
76 Review and Approval By Architect RM0.00 14 days Thu 5/16/19 Sat 6/1/19 100% 100%
77 Demolish Work RM20,000.00 7 days Tue 6/2/20 Wed 6/10/20 0% 0%
78 Fabricate RM75,000.00 14 days Wed 6/10/20 Thu 6/25/20 0% 0%
79 Installation RM40,000.00 14 days Mon 7/27/20 Tue 8/11/20 0% 0%
80 Remedial Works including Damp-proofing RM1,517,153.00 257 days Wed 5/8/19 Wed 2/19/20 75% 75%
works and Salt treatment
81 External Wall and Finishes RM1,508,653.00 257 days Wed 5/8/19 Wed 2/19/20 85% 85%
82 Growth and Vegetation RM30,000.00 21 days Wed 5/8/19 Fri 5/31/19 100% 100%
83 Dehumidfying Rendering system RM1,103,672.00 100 days Sat 6/1/19 Sat 9/21/19 100% 100%
84 Zone Left 1 RM220,734.40 20 days Sat 6/1/19 Mon 6/24/19 100% 100%
85 External Wall RM110,367.20 10 days Sat 6/1/19 Wed 6/12/19 100% 100%
86 Internal Wall RM110,367.20 10 days Wed 6/12/19 Mon 6/24/19 100% 100%
87 Zone Left 2 RM220,734.40 20 days Mon 6/24/19 Tue 7/16/19 100% 100%
88 External Wall RM110,367.20 10 days Mon 6/24/19 Thu 7/4/19 100% 100%
89 Internal Wall RM110,367.20 10 days Fri 7/5/19 Tue 7/16/19 100% 100%
90 Zone Centre RM220,734.40 20 days Tue 7/16/19 Wed 8/7/19 100% 100%

Task External Tasks Manual Task Finish-only Baseline Milestone


Split External Milestone Duration-only Deadline Baseline Summary
Project: CPM rev 0.1
Date: Fri 12/27/19 Milestone Inactive Task Manual Summary Rollup Critical Progress
Summary Inactive Milestone Manual Summary Critical Split Manual Progress
Project Summary Inactive Summary Start-only Baseline

Page 2
FAJAR ERATIMUR SDN BHD

KERJA-KERJA MENAIKTARAF DI DEWAN UNDANGAN NEGERI PULAU PINANG.

ID Task Task Name Cost Duration Start Finish % %Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021
Mode Complete
Schedule F M A M J J A S O N D J F M A M J J A S O N D J F
91 External Wall RM110,367.20 10 days Tue 7/16/19 Sat 7/27/19 100% 100%
92 Internal Wall RM110,367.20 10 days Sat 7/27/19 Wed 8/7/19 100% 100%
93 Zone Right 2 RM220,734.40 20 days Wed 8/7/19 Thu 8/29/19 100% 100%
94 External Wall RM110,367.20 10 days Wed 8/7/19 Mon 8/19/19 100% 100%
95 Internal Wall RM110,367.20 10 days Mon 8/19/19 Thu 8/29/19 100% 100%
96 Zone Right 1 RM220,734.40 20 days Fri 8/30/19 Sat 9/21/19 100% 100%
97 External Wall RM110,367.20 10 days Fri 8/30/19 Tue 9/10/19 100% 100%
98 Internal Wall RM110,367.20 10 days Tue 9/10/19 Sat 9/21/19 100% 100%
99 Chemical Barrier for Uprising Dampness RM261,505.00 80 days Sat 9/21/19 Thu 12/19/19 100% 100%
100 Zone Left 1 RM52,301.00 16 days Sat 9/21/19 Wed 10/9/19 100% 100%
101 Zone Left 2 RM52,301.00 16 days Wed 10/9/19 Sat 10/26/19 100% 100%
102 Zone Centre RM52,301.00 16 days Sat 10/26/19 Thu 11/14/19 100% 100%
103 Zone Right 2 RM52,301.00 16 days Thu 11/14/19 Mon 12/2/19 100% 100%
104 Zone Right 1 RM52,301.00 16 days Mon 12/2/19 Thu 12/19/19 100% 100%
105 Painting RM113,476.00 35 days Sat 1/11/20 Wed 2/19/20 0% 0%
106 Zone Left 1 RM22,695.20 7 days Sat 1/11/20 Sat 1/18/20 0% 0%
107 Zone Left 2 RM22,695.20 7 days Sat 1/18/20 Mon 1/27/20 0% 0%
108 Zone Centre RM22,695.20 7 days Mon 1/27/20 Tue 2/4/20 0% 0%
109 Zone Right 2 RM22,695.20 7 days Tue 2/4/20 Tue 2/11/20 0% 0%
110 Zone Right 1 RM22,695.20 7 days Wed 2/12/20 Wed 2/19/20 0% 0%
111 External Door and Windows RM8,500.00 42 days Fri 12/20/19 Wed 2/5/20 17% 17%
112 Door Type D1, D2, D3 & D4 RM5,700.00 21 days Fri 12/20/19 Sat 1/11/20 35% 35%
113 Window Type W1, W2, W3 & W4 RM2,800.00 21 days Mon 1/13/20 Wed 2/5/20 0% 0%
114 PROVISIONAL SUMS RM350,000.00 476.63 days Sat 4/13/19 Mon 9/28/20 25% 25%
115 Upgrading Dewan Persidangan RM350,000.00 476.63 days Sat 4/13/19 Mon 9/28/20 25% 25%
116 Propose Interior Design Concept RM5,000.00 21 days Sat 4/13/19 Mon 5/6/19 100% 100%
117 Shop Drawing & Quotation RM5,000.00 21 days Tue 5/7/19 Thu 5/30/19 100% 100%
118 Review & Approval RM0.00 15 days Thu 5/30/19 Sat 6/15/19 100% 100%
119 Demolish Work RM85,000.00 28 days Tue 6/2/20 Fri 7/3/20 0% 0%
120 Ceiling Work RM30,000.00 7 days Tue 6/2/20 Wed 6/10/20 0% 0%
121 Wall Panel RM25,000.00 7 days Wed 6/10/20 Thu 6/18/20 0% 0%
122 Platform RM5,000.00 7 days Thu 6/18/20 Thu 6/25/20 0% 0%
123 Carpet work RM25,000.00 7 days Thu 6/25/20 Fri 7/3/20 0% 0%
124 Fabricate RM170,000.00 15 days Wed 6/10/20 Fri 6/26/20 0% 0%
125 Ceiling Work RM55,000.00 15 days Wed 6/10/20 Fri 6/26/20 0% 0%
126 Wall Panel RM55,000.00 15 days Wed 6/10/20 Fri 6/26/20 0% 0%
127 Platform RM10,000.00 15 days Wed 6/10/20 Fri 6/26/20 0% 0%
128 Carpet work RM50,000.00 15 days Wed 6/10/20 Fri 6/26/20 0% 0%
129 Installation & Finishes RM85,000.00 83 days Fri 6/26/20 Mon 9/28/20 0% 0%
130 Ceiling Work RM20,000.00 21 days Fri 6/26/20 Mon 7/20/20 0% 0%
131 Wall Panel RM20,000.00 20 days Mon 7/20/20 Wed 8/12/20 0% 0%
132 Platform RM5,000.00 20 days Wed 8/12/20 Thu 9/3/20 0% 0%
133 Carpet work RM20,000.00 15 days Thu 9/3/20 Sat 9/19/20 0% 0%
134 Miscellaneous Work RM20,000.00 7 days Sat 9/19/20 Mon 9/28/20 0% 0%
135 PRIME COST SUMS RM648,900.00 186 days Wed 8/14/19 Mon 3/9/20 36% 73%

Task External Tasks Manual Task Finish-only Baseline Milestone


Split External Milestone Duration-only Deadline Baseline Summary
Project: CPM rev 0.1
Date: Fri 12/27/19 Milestone Inactive Task Manual Summary Rollup Critical Progress
Summary Inactive Milestone Manual Summary Critical Split Manual Progress
Project Summary Inactive Summary Start-only Baseline

Page 3
FAJAR ERATIMUR SDN BHD

KERJA-KERJA MENAIKTARAF DI DEWAN UNDANGAN NEGERI PULAU PINANG.

ID Task Task Name Cost Duration Start Finish % %Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021
Mode Complete
Schedule F M A M J J A S O N D J F M A M J J A S O N D J F
136 Electrical Work RM298,700.00 186 days Wed 8/14/19 Mon 3/9/20 36% 74%
137 Site Possession RM0.00 0 days Wed 8/14/19 Wed 8/14/19 100% 100% 8/14
138 Preliminaries RM10,700.00 51 days Wed 8/14/19 Wed 10/9/19 100% 100%
139 Insurance RM5,000.00 31 days Wed 8/14/19 Tue 9/17/19 100% 100%
140 Contract Documents RM5,700.00 51 days Wed 8/14/19 Wed 10/9/19 100% 100%
141 Dewan Persidangan RM278,000.00 179 days Wed 8/14/19 Sat 2/29/20 5% 63%
142 Remove Existing fittings, cable and trunkingRM10,000.00 7 days Wed 8/14/19 Wed 8/21/19 100% 100%
143 Prepare Point & Install RM48,000.00 50 days Tue 9/17/19 Tue 11/12/19 0% 100%
144 L-Bracket Installation RM10,000.00 15 days Tue 9/17/19 Fri 10/4/19 0% 100%
145 Trunking installation RM28,000.00 15 days Fri 10/4/19 Mon 10/21/19 0% 100%
146 PVC Pipe Installation RM10,000.00 20 days Mon 10/21/19 Tue 11/12/19 0% 100%
147 Cabling Works RM105,000.00 47 days Tue 11/12/19 Fri 1/3/20 0% 87%
148 S/S/0 13 A RM20,000.00 12 days Tue 11/12/19 Tue 11/26/19 0% 100%
149 Lamps RM10,000.00 10 days Tue 11/26/19 Fri 12/6/19 0% 100%
150 A/C RM40,000.00 8 days Sat 12/7/19 Mon 12/16/19 0% 100%
151 PA System RM25,000.00 8 days Mon 12/16/19 Wed 12/25/19 0% 100%
152 CCTV RM10,000.00 9 days Wed 12/25/19 Fri 1/3/20 0% 31%
153 Fittings Works RM115,000.00 51 days Sat 1/4/20 Sat 2/29/20 0% 0%
154 S/S/0 13 A RM10,000.00 20 days Sat 1/4/20 Sat 1/25/20 0% 0%
155 Lamps RM10,000.00 12 days Mon 1/27/20 Sat 2/8/20 0% 0%
156 A/C RM45,000.00 9 days Sat 2/8/20 Wed 2/19/20 0% 0%
157 PA System RM30,000.00 5 days Wed 2/19/20 Mon 2/24/20 0% 0%
158 CCTV RM20,000.00 5 days Tue 2/25/20 Sat 2/29/20 0% 0%
159 Testing RM10,000.00 7 days Sat 2/29/20 Mon 3/9/20 0% 0%
160 Mechanical Work RM350,200.00 186 days Wed 8/14/19 Mon 3/9/20 35% 72%
161 Site Possession RM0.00 0 days Wed 8/14/19 Wed 8/14/19 100% 100% 8/14
162 Preliminaries RM52,000.00 51 days Wed 8/14/19 Wed 10/9/19 100% 100%
163 Insurance RM6,000.00 31 days Wed 8/14/19 Tue 9/17/19 100% 100%
164 Contract Documents RM20,000.00 51 days Wed 8/14/19 Wed 10/9/19 100% 100%
165 Dewan Persidangan RM283,200.00 179 days Wed 8/14/19 Sat 2/29/20 0% 60%
166 Remove Existing ducting and etc RM30,000.00 14 days Wed 8/14/19 Thu 8/29/19 0% 100%
167 Air Conditioning (Air-Cooled Package) RM205,000.00 113 days Thu 10/10/19 Thu 2/13/20 0% 63%
168 Refrigerant piping RM50,000.00 18 days Thu 10/10/19 Wed 10/30/19 0% 100%
169 Ducting RM45,000.00 30 days Wed 10/30/19 Mon 12/2/19 0% 100%
170 Outdoor RM50,000.00 15 days Tue 12/3/19 Thu 12/19/19 0% 100%
171 Drain water piping RM5,000.00 15 days Thu 12/19/19 Sat 1/4/20 0% 52%
172 Indoor RM25,000.00 14 days Sat 1/4/20 Tue 1/21/20 0% 0%
173 Wiring RM30,000.00 21 days Tue 1/21/20 Thu 2/13/20 0% 0%
174 Air Curtain RM48,200.00 15 days Thu 2/13/20 Sat 2/29/20 0% 0%
175 Testing RM15,000.00 7 days Sat 2/29/20 Mon 3/9/20 0% 0%
176 TESTING AND COMMISSIONING RM16,000.00 13 days Mon 9/28/20 Sun 10/11/20 0% 0%
177 Make Good RM16,000.00 11 days Mon 9/28/20 Sat 10/10/20 0% 0%
178 Pre Inspection RM0.00 1 day Sat 10/10/20 Sat 10/10/20 0% 0%
179 Final Inspection RM0.00 1 day Sat 10/10/20 Sun 10/11/20 0% 0%
180 HANDOVER RM0.00 0 days Sun 10/11/20 Sun 10/11/20 0% 0% 10/11

Task External Tasks Manual Task Finish-only Baseline Milestone


Split External Milestone Duration-only Deadline Baseline Summary
Project: CPM rev 0.1
Date: Fri 12/27/19 Milestone Inactive Task Manual Summary Rollup Critical Progress
Summary Inactive Milestone Manual Summary Critical Split Manual Progress
Project Summary Inactive Summary Start-only Baseline