Sei sulla pagina 1di 3

ESTIMATE

CHB Length 130.8 m


Height 2.4 m
Area = Length x Height 313.92 sq m
Quantity = Area x 12.50 3924 pcs

Mortar Cement = Area x 1.018 319.5706 bags


= RoundUp(Cement,0) 320 bags
Sand = Area x 0.0844 26.49485 cu m
= RoundUp(Sand,0) 27 cu m

Plaster Length 130.8 m


Height 2 m
Area = Length x Height x 2 523.2 sq m
Cement = Area x 0.225 117.72 bags
= RoundUp(Cement,0) 118 bags
Sand = Area x 0.025 13.08 cu m
= RoundUp(Sand,0) 14 cu m

SUMMARY
CHB 5" =total number of CHB 3924 pcs
Cement =total number of Cement 438 bags
Sand =total number of Sand 41 cu m

Masonry Reinforcement

ESTIMATE
VERTICAL REINFORCEMENT(10mm dia)
60 cm spacing
Height 2.4 m
Length 130.8 m
Area = Length x Height 313.92 sq m
Length = Area x 2.13 668.6496 m
No. of Bars = Length / 5.5m 121.5727 pcs
= RoundUp(No. of Bars,0) 122 pcs
HORIZONTAL REINFORCEMENT(10mm)
Height 2.4 m
Length 130.8 m
Area = Length x Height 313.92 sq m
Length = Area x 2.15 674.928 m
No. of Bars = Length / 5.5m 122.7142 pcs
= RoundUp(No. of Bars,0) 123 pcs

SUMMARY
10mm dia RSB =total number of 10mm dia RSB 245 pcs
CONCRETING (CLASS B MIX)

ESTIMATE
COLUMN
Length 0.2 m
Width 0.2 m
Height 2.4 m
Volume =LxWxH 0.096 cu m
Total Volume = Volume x No. of columns(34) 3.264 cu m
Cement = Volume x 7.5 24.48 bags
= RoundUp(Cement,0) 25 bags
Sand = Volume x 0.5 1.632 cu m
= RoundUp(Sand,0) 2 cu m
Gravel = Volume x 1 3.264 cu m
= RoundUp(Gravel,0) 4 cu m
WALL FOOTING
Length 130.8 m
Width 0.25 m
Thickness 0.2 m
Volume = L x W x Thickness 6.54 cu m
Cement = Volume x 7.5 49.05 bags
= RoundUp(Cement,0) 50 bags
Sand = Volume x 0.5 3.27 cu m
= RoundUp(Sand,0) 4 cu m
Gravel = Volume x 1 6.54 cu m
= RoundUp(Gravel,0) 7 cu m
COLUMN FOOTING
Length 0.25 m
Width 0.25 m
Thickness 0.1 m
Volume = L x W x Thickness 0.00625 cu m
Total Volume = Volume x No. of footing 0.2125 cu m
Cement = Volume x 7.5 1.59375 bags
= RoundUp(Cement,0) 2 bags
Sand = Volume x 0.5 0.10625 cu m
= RoundUp(Sand,0) 1 cu m
Gravel = Volume x 1 0.2125 cu m
= RoundUp(Gravel,0) 1 cu m

SUMMARY
Cement =total number of cement 77 bags
Sand =total number of sand 7 cu m
Gravel =total number of gravel 12 cu m
REBAR

ESTIMATE
WALL FOOTING
MAIN BAR
Length = Width - (2 x 0.025) 0.2 m
Spacing 0.3 m
No. of Bars = Length / Spacing + 1 437 pcs
L of 10mm Main Bar = No. of Bars x Length 87.4 m
No. of 10mm Main Bar = Length of Bars / 6 14.56667 pcs
= RoundUp(No. of 10mm bar,0) 15 pcs

TEMPERATURE BARS
Length = L of wall - (2 x 0.025) 130.75 m
Total Length = Length x 3 392.25 m
Effective Length of 6mm = 6 - 0.5 5.5 m
Number of 10mm Bar = Total L / Effective L 71.31818 pcs
= RoundUp(No. of 10mm bars,0) 72 pcs
COLUMN
MAIN BAR (12mm dia)
No. of Columns 34
No. of Rebars per Column 4
Height 2.4 m
Total Length of Rebar = 34 x 4 x 2.40 326.4 m
No. of 12mm Bar = Length / 6 54.4 pcs
= RoundUp(No. of 12mm bar,0) 55 pcs
COLUMN FOOTING
MAIN BAR (12mm dia)
Length of 1 Bar = 1 - (2 x 0.075) 0.85 m
No. of Rebars per Column = 5 x 2 10 pcs
Total Length of Rebar = No. of bars x footing(34) 340 m
No. of 12mm Bar = Length / 6 56.66667 pcs
= RoundUp(No. of 12mm bar, 0) 57 pcs
LATERAL TIES
Spacing = 16 x Longitudinal Bar(12mm) 192 mm
Least Dimension of Column 200 mm
No. of L Ties in 1column = (Height / .192) + 1 13.5 pcs
Total no. of L Ties =No. of L ties x Column(34) 459 pcs
Length = 1.20m x Total no. of L ties 550.8 m
No. of 10mm Bar = Length / 6 91.8 pcs
= RoundUp(No. of 10mm bars,0) 92 pcs

SUMMARY
10mm Bars =total number of 10mm Bars 179 pcs
12mm Bars =total number of 12mm Bars 112 pcs

Potrebbero piacerti anche