KEMENTERIAN KESIHATAN MALAYSIA Task No.

: E31036
HOSPITAL ENGINEERING PLANNED PREVENTIVE MAINTENANCE
(HEPPM) Page : 1 of 5

Electrical Supply, Emergency,


Asset Category Workgroup Electrical
Generator Set
Work Request No. Frequency Annually

CAUTION:
Ensure the stipulated safety procedures are followed while carrying Estimated
out the PM activities PM hours:

A Safety Precautions Prior to PM procedure: Comply


Remark
Yes No
1 Notify in writing to TNB/SESCO/SESB annual PPM is being carried
out if required. Follow-up verbally with TNB/SESCO/SESB prior to
shutdown.
2 Advance written notice on shutdown has been sent to effected
department
Notice ref No. ___________________
3 Alternative standby source of supply arranged, if necessary.
4 Permit to Work No. ______________ approved by
_____________________
5 Announcement / notice has been made to all departments one
hour before planned shutdown and 15 minutes before shutdown

B PRECAUTIONS BEFORE LOAD TEST: Comply


Remark
Yes No
1 Standby staff in position
2 Communications with standby / PPM personnel established
3 Ensure availability of circuit diagram, safety chart, first aid kit,
danger sign, fire extinguisher and rubber mat.
4 Apply lock out / tag out procedures
5 Ensure good housekeeping in generator room
6 Use appropriate PPE.
7 Announcement / notice on shutdown has been made to all
departments one hour before planned shutdown and 15 minutes
before shutdown

C BEFORE ENGINE START-UP: Comply


Remark
Yes No
1 Inspect the day tank diesel level.
2 Drain the lube oil and fill up with the recommended oil. Check oil
strainer and clean oil sump if necessary.
3 Replace lube oil filter, water filter, lube oil bypass filter (if installed)
and fuel filters.
4 Drain and flush radiator. Fill up with new coolant (water mixed with
anti corrosive agent in correct proportion).
5 Check battery voltage, electrolyte level, specific gravity and charge.
6 Inspect and clean battery terminals. Apply petroleum jelly if
required.
7 Check air filter element. Clean or Replace as necessary.
8 Inspect the fan belt and alternator belt condition and tension. Adjust
if necessary.
9 Inspect condition of all hoses. Replace if any cracks have
developed.

KKM/FEMS/E1104 Effective Date: 01/01/2009 Version: 2.0


KEMENTERIAN KESIHATAN MALAYSIA Task No. : E31036
HOSPITAL ENGINEERING PLANNED PREVENTIVE MAINTENANCE
(HEPPM) Page : 2 of 5

Electrical Supply, Emergency,


Asset Category Workgroup Electrical
Generator Set
Work Request No. Frequency Annually

C BEFORE ENGINE START-UP: Comply


Remark
Yes No
10 Clean crank case breather.
11 Clean the generator.
12 Drain the sediments from the fuel tank. Clean the tank if necessary.
13 Inspect fuel transfer pump operation
On the alternator side: Comply Remarks
Yes No
1 Inspect the rectifier assembly (rotating diodes) for loose connections
or over heating.
2 Inspect the surge suppressors (MOV - Metal Oxide Varistor) installed
in the diode plates.
3 Check generator connections for loose connections, arching,
overheating or damage.
4 Inspect voltage regulator card for any signs of damage.
5 Open the inspections cover of generator and check the exciter
windings. Clean the windings using vacuum cleaner.
6 Inspect the power distribution wiring, connections, transformers and
windings.

D BEFORE ENGINE START-UP: Comply


Remark
Yes No
1 START AND RUN THE GENERATOR SET

2 Adjust the trimmer in automatic voltage regulator if necessary.

3 Test high temperature trip, low lube oil pressure trip, over speed
trip, over voltage and over current trip.
4 STOP THE GENERATOR AND SIMULATE MAINS FAILURE AT
UNDER VOLTAGE RELAY / AMF PANEL OR PERFORM MAINS
SHUTDOWN
5 For sets running in parallel, synchronize the two generators on
‘Auto’ mode.
6 Run the engine “ON LOAD” for at least one (1) hour
7 Ensure emergency supply is provided to the appropriate areas.
8 Check operation of gauges and indicator lights.

9 Periodically check all the gauges, while running.


10 Check whether readings are within the limits.
11 Check for excessive vibration when engine is running. Tighten the
anti vibrating pads hold down bolts.
12 Inspect the condition of exhaust manifold insulation

13 Inspect for signs of leakages of: fuel, lube oil, engine oil, exhaust
and coolant/water.
14 Check the exhaust smoke appearance.
15 If any engine alarm is on while running, identify the faults and stop
the engine.
16 Check alternator battery charging operations.
17 Check operation of ventilation fans.

KKM/FEMS/E1104 Effective Date: 01/01/2009 Version: 2.0


KEMENTERIAN KESIHATAN MALAYSIA Task No. : E31036
HOSPITAL ENGINEERING PLANNED PREVENTIVE MAINTENANCE
(HEPPM) Page : 3 of 5

Electrical Supply, Emergency,


Asset Category Workgroup Electrical
Generator Set
Work Request No. Frequency Annually

E QUANTITATIVE CHECKS : Comply


Remark
Yes No
1 Record running hours
2 Record delay time in mains failure relay, time to reach full voltage.
3 Record the details in generator logbook (take the readings after 20 minutes
of running): AMP, LUBE OIL PRESSURE, WATER TEMP, OUTPUT
VOLTAGE, FREQUENCY, SPEED. Carry out the necessary adjustment to
governor, AVR as necessary.
4 Check and record the insulation value of main windings.

5 Check alternator voltage and charging current.

6 Inspect starter motor.

7 Record voltages and specific gravity of each battery cells.

8 Test earth electrodes resistance.

9 Perform insulation resistance tests using mega ohm meter in accordance


with IEEE, Recommended Practice for Testing Insulation Resistance of
Rotating Machinery on the stator and rotor of both generator and exciter.

F SAFETY PROCEDURES ON COMPLETION OF PPM : Comply


Remark
Yes No
1 Remove lock out / tag out.
2 Emergency stop button if any, released
3 Normal supplies to effected areas restored.
4 Ensure that the duty selector switch is in “AUTO” position and
generator supply breaker is in ‘ON’ condition
5 Check availability and normal operation of fire fighting systems.
6 Inspect condition and security of doors.
7 Ensure good housekeeping in generator room
8 Update Plant Log Book entry.
9 Open Corrective Maintenance Work Order for remedial works.

G QUANTITATIVE/ INSPECTION CHECKLIST (If applicable, record all measured data for the various
parameters in space provided below):
Parameter: Lubrication Water Engine Output Voltage Hour Run Voltage
Oil Pressure Temperature speed Frequency Battery Meter Generator
(psi) (rpm) (Hertz) (Volt) (Volt)
Set Limits: - <90 deg 1500-1520 50 Hz 24 V - 400 V
Celcius (+10%/-6%)
Data:
Parameter: Load
Current
(Amp)
Data:

KKM/FEMS/E1104 Effective Date: 01/01/2009 Version: 2.0


KEMENTERIAN KESIHATAN MALAYSIA Task No. : E31036
HOSPITAL ENGINEERING PLANNED PREVENTIVE MAINTENANCE
(HEPPM) Page : 4 of 5

Electrical Supply, Emergency,


Asset Category Workgroup Electrical
Generator Set
Work Request No. Frequency Annually

H. Consumables used during maintenance: I. Part Replaced:

J. Tools/Equipment used:
Multimeter

PPM has been performed in compliance to the checklist and the plant/equipment functions satisfactory to the
intended purpose.

Remarks: ___________________________________________________________________________________

___________________________________________________________________________________

Performed By :

Signature : _____________________________

Name :

Designation :

Company :

Date :

KKM/FEMS/E1104 Effective Date: 01/01/2009 Version: 2.0


KEMENTERIAN KESIHATAN MALAYSIA Task No. : E31036
HOSPITAL ENGINEERING PLANNED PREVENTIVE MAINTENANCE
(HEPPM) Page : 5 of 5

Electrical Supply, Emergency,


Asset Category Workgroup Electrical
Generator Set
Work Request No. Frequency Annually

BATTERY READING RECORDS


CELL SPECIFIC ELECTROLYTE LEVEL (H- High,
CELL VOLTAGE ( V ) REMARKS
No. GRAVITY M- Medium ,L- Low )

Done by 1: ____________________

Note : Please add page if required

KKM/FEMS/E1104 Effective Date: 01/01/2009 Version: 2.0