C PRODUCTION
( C.P / B.P / Quarry Permission / Testing for R.C.C)
■ Upper Cisokan PSPP 10/15/2019
Duration
Description (Days) M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 REMARK
8. Mix design evaluation and select best candidate for full scale trial
: Strength test, density, 20 days
9. Full scale trial embankment RCC Class C15/38 and RCC Class C25/38
Workability check, compactability, segregation etc. (FIRST TRIAL)
: First trial RCC Class C25/38 10 days
: First trial RCC Class C15/38 10 days
10. Full scale trial embankment RCC Class C15/38 and RCC Class C25/38
Compressive test up to 90day, (SECONDARY)
: First trial RCC Class C25/38 110 days
: First trial RCC Class C15/38 110 days
11. Construction method evaluation
: Water-stop and drainage hole installation 30 days
: Cutting of contraction joint and insertion of inducer material 30 days
: GE-RCC and Reinforcement in GE-RCC against formworks 30 days
: Liftjoint curing and atmosphere humidity control 30 days
: Lift joint treatment bedding mortar 30 days
12. Further Testing (Core at least D=150mm & D= 3m)
: To check actual lift joint bond during trial embankment 20 days
: Take photograph of core immediately of extraction cores 20 days
: Protect the cores sample from drying until reach testing laboratory 20 days
13. Further Training - If requried
: To reach an acceptable level of workmanship for RCC placement 20 days
: Final two RCC trial layers can not proceed until reach an acceptable level of work 20 days
14. Further Full Scale Trial Emb. (800m3 & 2 layers)
(2weeks prior to the commencement of placing RCC)
: Workability and compactibility analisis 20 days
: Density test 20 days
: Behavior of mix during roller process 20 days
: Compressive Strength 20 days
: Construction method analysis 20 days
15. Trial mx report making and Submit
: Within 1 week after completing the trial embankment 10 days
: With later long term strength test result to follow 10 days
16. Mix design approved by The Engineer
: Written approval reveived form Engineer 10 days
RCC Plan
■ Upper Cisokan PSPP
Test Days
NO Work Item Unit Remarks
Normal Minimum
3 Water testing (after COD) - Parallel No.1 & 2 Day - - No impaction to procedure
period
4 Cement, Fly-ash and Admixture test (after COD) Day - - (30 days)
5 Material approval processing (after all test finish) Day 30 30 Engineer's review