Sei sulla pagina 1di 7

G.R. No.

114323 July 23, 1998 otherwise concerning the materials or the execution or failure to
OIL AND NATURAL GAS COMMISSION, petitioner, execute the same during stipulated/extended period or after the
vs. completion/ abandonment thereof shall be referred to the sole
COURT OF APPEALS and PACIFIC CEMENT COMPANY, INC., respondents. arbitration of the persons appointed by Member of the
Commission at the time of dispute. It will be no objection to any
MARTINEZ, J.: such appointment that the arbitrator so appointed is a
Commission employer (sic) that he had to deal with the matter to
This proceeding involves the enforcement of a foreign judgment rendered by the which the supply or contract relates and that in the course of his
Civil Judge of Dehra Dun, India in favor of the petitioner, OIL AND NATURAL duties as Commission's employee he had expressed views on all
GAS COMMISSION and against the private respondent, PACIFIC CEMENT or any of the matter in dispute or difference.
COMPANY, INCORPORATED.
The arbitrator to whom the matter is originally referred being
The petitioner is a foreign corporation owned and controlled by the Government transferred or vacating his office or being unable to act for any
of India while the private respondent is a private corporation duly organized and reason the Member of the Commission shall appoint another
existing under the laws of the Philippines. The present conflict between the person to act as arbitrator in accordance with the terms of the
petitioner and the private respondent has its roots in a contract entered into by contract/supply order. Such person shall be entitled to proceed
and between both parties on February 26, 1983 whereby the private respondent with reference from the stage at which it was left by his
undertook to supply the petitioner FOUR THOUSAND THREE HUNDRED predecessor. Subject as aforesaid the provisions of the
(4,300) metric tons of oil well cement. In consideration therefor, the petitioner Arbitration Act, 1940, or any Statutory modification or re-
bound itself to pay the private respondent the amount of FOUR HUNDRED enactment thereof and the rules made there under and for the
SEVENTY-SEVEN THOUSAND THREE HUNDRED U.S. DOLLARS time being in force shall apply to the arbitration proceedings
($477,300.00) by opening an irrevocable, divisible, and confirmed letter of credit under this clause.
in favor of the latter. The oil well cement was loaded on board the ship MV
SURUTANA NAVA at the port of Surigao City, Philippines for delivery at Bombay The arbitrator may with the consent of parties enlarge the time,
and Calcutta, India. However, due to a dispute between the shipowner and the from time to time, to make and publish the award.
private respondent, the cargo was held up in Bangkok and did not reach its point
destination. Notwithstanding the fact that the private respondent had already The venue for arbitration shall be at Dehra dun. *
received payment and despite several demands made by the petitioner, the
private respondent failed to deliver the oil well cement. Thereafter, negotiations On July 23, 1988, the chosen arbitrator, one Shri N.N. Malhotra, resolved the
ensued between the parties and they agreed that the private respondent will dispute in petitioner's favor setting forth the arbitral award as follows:
replace the entire 4,300 metric tons of oil well cement with Class "G" cement cost
free at the petitioner's designated port. However, upon inspection, the Class "G" NOW THEREFORE after considering all facts of the case, the
cement did not conform to the petitioner's specifications. The petitioner then evidence, oral and documentarys adduced by the claimant and
informed the private respondent that it was referring its claim to an arbitrator carefully examining the various written statements, submissions,
pursuant to Clause 16 of their contract which stipulates: letters, telexes, etc. sent by the respondent, and the oral
arguments addressed by the counsel for the claimants, I, N.N.
Except where otherwise provided in the supply order/contract all Malhotra, Sole Arbitrator, appointed under clause 16 of the
questions and disputes, relating to the meaning of the supply order dated 26.2.1983, according to which the parties, i.e.
specification designs, drawings and instructions herein before M/S Oil and Natural Gas Commission and the Pacific Cement
mentioned and as to quality of workmanship of the items ordered Co., Inc. can refer the dispute to the sole arbitration under the
or as to any other question, claim, right or thing whatsoever, in provision of the Arbitration Act. 1940, do hereby award and direct
any way arising out of or relating to the supply order/contract as follows: —
design, drawing, specification, instruction or these conditions or
The Respondent will pay the following to the claimant: — Sir:
1. Amount received by the Respondent 1. We received your letter dated 28 April 1989 only last 18
against the letter of credit No. 11/19 May 1989.
dated 28.2.1983 US $ 477,300.00 2. Please inform us how much is the court fee to be paid.
2. Re-imbursement of expenditure incurred Your letter did not mention the amount to be paid.
by the claimant on the inspection team's 3. Kindly give us 15 days from receipt of your letter advising
visit to Philippines in August 1985 US $ 3,881.00 us how much to pay to comply with the same.
3. L.C. Establishment charges incurred
by the claimant US $ 1,252.82 Thank you for your kind consideration.
4. Loss of interest suffered by claimant Pacific Cement Co., Inc.
from 21.6.83 to 23.7.88 US $ 417,169.95
Total amount of award US $ By: Jose Cortes, Jr.
899,603.77 President

In addition to the above, the respondent would also be liable to Without responding to the above communication, the foreign court refused to
pay to the claimant the interest at the rate of 6% on the above admit the private respondent's objections for failure to pay the required filing fees,
amount, with effect from 24.7.1988 up to the actual date of and thereafter issued an Order on February 7, 1990, to wit:
payment by the Respondent in full settlement of the claim as
awarded or the date of the decree, whichever is earlier. ORDER
Since objections filed by defendant have been rejected through
I determine the cost at Rs. 70,000/- equivalent to US $5,000 Misc. Suit No. 5 on 7.2.90, therefore, award should be made
towards the expenses on Arbitration, legal expenses, stamps Rule of the Court.
duly incurred by the claimant. The cost will be shared by the
parties in equal proportion. ORDER
Pronounced at Dehra Dun to-day, the 23rd of July 1988. Award dated 23.7.88, Paper No. 3/B-1 is made Rule of the
Court. On the basis of conditions of award decree is passed.
To enable the petitioner to execute the above award in its favor, it filed a Award Paper No. 3/B-1 shall be a part of the decree. The plaintiff
Petition before the Court of the Civil Judge in Dehra Dun. India shall also be entitled to get from defendant (US$ 899,603.77
(hereinafter referred to as the foreign court for brevity), praying that the (US$ Eight Lakhs ninety nine thousand six hundred and three
decision of the arbitrator be made "the Rule of Court" in India. The point seventy seven only) along with 9% interest per annum till
foreign court issued notices to the private respondent for filing objections the last date of realisation.
to the petition. The private respondent complied and sent its objections
dated January 16, 1989. Subsequently, the said court directed the Despite notice sent to the private respondent of the foregoing order and several
private respondent to pay the filing fees in order that the latter's demands by the petitioner for compliance therewith, the private respondent
objections could be given consideration. Instead of paying the required refused to pay the amount adjudged by the foreign court as owing to the
filing fees, the private respondent sent the following communication petitioner. Accordingly, the petitioner filed a complaint with Branch 30 of the
addressed to the Civil judge of Dehra Dun: Regional Trial Court (RTC) of Surigao City for the enforcement of the
aforementioned judgment of the foreign court. The private respondent moved to
The Civil Judge dismiss the complaint on the following grounds: (1) plaintiffs lack of legal capacity
Dehra Dun (U.P.) India to sue; (2) lack of cause of action; and (3) plaintiffs claim or demand has been
Re: Misc. Case No. 5 of 1989 waived, abandoned, or otherwise extinguished. The petitioner filed its opposition
M/S Pacific Cement Co., to the said motion to dismiss, and the private respondent, its rejoinder thereto.
Inc. vs. ONGC Case On January 3, 1992, the RTC issued an order upholding the petitioner's legal
capacity to sue, albeit dismissing the complaint for lack of a valid cause of action. the RTC's ruling that the arbitrator did not have jurisdiction over the dispute
The RTC held that the rule prohibiting foreign corporations transacting business between the parties, thus, the foreign court could not validly adopt the arbitrator's
in the Philippines without a license from maintaining a suit in Philippine courts award. In addition, the appellate court observed that the full text of the judgment
admits of an exception, that is, when the foreign corporation is suing on an of the foreign court contains the dispositive portion only and indicates no findings
isolated transaction as in this case. Anent the issue of the sufficiency of the of fact and law as basis for the award. Hence, the said judgment cannot be
petitioner's cause of action, however, the RTC found the referral of the dispute enforced by any Philippine court as it would violate the constitutional provision
between the parties to the arbitrator under Clause 16 of their contract erroneous. that no decision shall be rendered by any court without expressing therein clearly
According to the RTC, and distinctly the facts and the law on which it is based. The appellate court ruled
further that the dismissal of the private respondent's objections for non-payment
[a] perusal of the shove-quoted clause (Clause 16) readily shows of the required legal fees, without the foreign court first replying to the private
that the matter covered by its terms is limited to "ALL respondent's query as to the amount of legal fees to be paid, constituted want of
QUESTIONS AND DISPUTES, RELATING TO THE MEANING notice or violation of due process. Lastly, it pointed out that the arbitration
OF THE SPECIFICATION, DESIGNS, DRAWINGS AND proceeding was defective because the arbitrator was appointed solely by the
INSTRUCTIONS HEREIN BEFORE MENTIONED and as to the petitioner, and the fact that the arbitrator was a former employee of the latter
QUALITY OF WORKMANSHIP OF THE ITEMS ORDERED or gives rise to a presumed bias on his part in favor of the petitioner.
as to any other questions, claim, right or thing whatsoever, but
qualified to "IN ANY WAY ARISING OR RELATING TO THE A subsequent motion for reconsideration by the petitioner of the appellate court's
SUPPLY ORDER/CONTRACT, DESIGN, DRAWING, decision was denied, thus, this petition for review on certiorari citing the following
SPECIFICATION, etc.," repeating the enumeration in the as grounds in support thereof:
opening sentence of the clause.
RESPONDENT COURT OF APPEALS GRAVELY ERRED IN
The court is inclined to go along with the observation of the AFFIRMING THE LOWER COURT'S ORDER OF DISMISSAL
defendant that the breach, consisting of the non-delivery of the SINCE:
purchased materials, should have been properly litigated before A. THE NON-DELIVERY OF THE CARGO WAS A MATTER
a court of law, pursuant to Clause No. 15 of the Contract/Supply PROPERLY COGNIZABLE BY THE PROVISIONS OF CLAUSE
Order, herein quoted, to wit: 16 OF THE CONTRACT;
"JURISDICTION B. THE JUDGMENT OF THE CIVIL COURT OF DEHRADUN,
INDIA WAS AN AFFIRMATION OF THE FACTUAL AND LEGAL
All questions, disputes and differences, arising FINDINGS OF THE ARBITRATOR AND THEREFORE
under out of or in connection with this supply ENFORCEABLE IN THIS JURISDICTION;
order, shall be subject to the EXCLUSIVE C. EVIDENCE MUST BE RECEIVED TO REPEL THE EFFECT
JURISDICTION OF THE COURT, within the OF A PRESUMPTIVE RIGHT UNDER A FOREIGN
local limits of whose jurisdiction and the place JUDGMENT.
from which this supply order is situated."

The RTC characterized the erroneous submission of the dispute to the The threshold issue is whether or not the arbitrator had jurisdiction over the
arbitrator as a "mistake of law or fact amounting to want of jurisdiction". dispute between the petitioner and the private respondent under Clause 16 of the
Consequently, the proceedings had before the arbitrator were null and contract. To reiterate, Clause 16 provides as follows:
void and the foreign court had therefore, adopted no legal award which
could be the source of an enforceable right. Except where otherwise provided in the supply order/contract all
questions and disputes, relating to the meaning of the
The petitioner then appealed to the respondent Court of Appeals which affirmed specification designs, drawings and instructions herein before
the dismissal of the complaint. In its decision, the appellate court concurred with mentioned and as to quality of workmanship of the items ordered
or as to any other question, claim, right or thing whatsoever, in or is equally susceptible of various meanings, its correct construction may be
any way arising out of or relating to the supply order/contract made clear and specific by considering the company of the words in which it is
design, drawing, specification, instruction or these conditions or found or with which it is associated, or stated differently, its obscurity or doubt
otherwise concerning the materials or the execution or failure to may be reviewed by reference to associated words. A close examination of
execute the same during stipulated/extended period or after the Clause 16 reveals that it covers three matters which may be submitted to
completion/abandonment thereof shall be referred to the sole arbitration namely,
arbitration of the persons appointed by Member of the
Commission at the time of dispute. It will be no objection to any (1) all questions and disputes, relating to the meaning of the specification
such appointment that the arbitrator so appointed is a designs, drawings and instructions herein before mentioned and as to quality of
Commission employer (sic) that he had to deal with the matter to workmanship of the items ordered; or
which the supply or contract relates and that in the course of his (2) any other question, claim, right or thing whatsoever, in any way arising out of
duties as Commission's employee he had expressed views on all or relating to the supply order/contract design, drawing, specification, instruction
or any of the matter in dispute or difference. or these conditions; or
(3) otherwise concerning the materials or the execution or failure to execute the
The dispute between the parties had its origin in the non-delivery of the 4,300 same during stipulated/extended period or after the completion/abandonment
metric tons of oil well cement to the petitioner. The primary question that may be thereof.
posed, therefore, is whether or not the non-delivery of the said cargo is a proper
subject for arbitration under the above-quoted Clause 16. The petitioner The first and second categories unmistakably refer to questions and disputes
contends that the same was a matter within the purview of Clause 16, particularly relating to the design, drawing, instructions, specifications or quality of the
the phrase, ". . . or as to any other questions, claim, right or thing whatsoever, in materials of the supply/order contract. In the third category, the clause,
any way arising or relating to the supply order/contract, design, drawing, "execution or failure to execute the same", may be read as "execution or failure
specification, instruction . . .". It is argued that the foregoing phrase allows to execute the supply order/contract". But in accordance with the doctrine
considerable latitude so as to include non-delivery of the cargo which was a of noscitur a sociis, this reference to the supply order/contract must be construed
"claim, right or thing relating to the supply order/contract". The contention is in the light of the preceding words with which it is associated, meaning to say, as
bereft of merit. First of all, the petitioner has misquoted the said phrase, shrewdly being limited only to the design, drawing, instructions, specifications or quality of
inserting a comma between the words "supply order/contract" and "design" the materials of the supply order/contract. The non-delivery of the oil well cement
where none actually exists. An accurate reproduction of the phrase reads, ". . . or is definitely not in the nature of a dispute arising from the failure to execute the
as to any other question, claim, right or thing whatsoever, in any way arising out supply order/contract design, drawing, instructions, specifications or quality of the
of or relating to the supply order/contract design, drawing, specification, materials. That Clause 16 should pertain only to matters involving the technical
instruction or these conditions . . .". The absence of a comma between the words aspects of the contract is but a logical inference considering that the underlying
"supply order/contract" and "design" indicates that the former cannot be taken purpose of a referral to arbitration is for such technical matters to be deliberated
separately but should be viewed in conjunction with the words "design, drawing, upon by a person possessed with the required skill and expertise which may be
specification, instruction or these conditions". It is thus clear that to fall within the otherwise absent in the regular courts.
purview of this phrase, the "claim, right or thing whatsoever" must arise out of or
relate to the design, drawing, specification, or instruction of the supply This Court agrees with the appellate court in its ruling that the non-delivery of the
order/contract. The petitioner also insists that the non-delivery of the cargo is not oil well cement is a matter properly cognizable by the regular courts as stipulated
only covered by the foregoing phrase but also by the phrase, ". . . or otherwise by the parties in Clause 15 of their contract:
concerning the materials or the execution or failure to execute the same during
the stipulated/extended period or after completion/abandonment thereof . . .". All questions, disputes and differences, arising under out of or in
The doctrine of noscitur a sociis, although a rule in the construction of statutes, is connection with this supply order, shall be subject to
equally applicable in the ascertainment of the meaning and scope of vague the exclusive jurisdiction of the court, within the local limits of
contractual stipulations, such as the aforementioned phrase. According to the whose jurisdiction and the place from which this supply order is
maxim noscitur a sociis, where a particular word or phrase is ambiguous in itself situated.
The following fundamental principles in the interpretation of contracts The petitioner then asseverates that granting, for the sake of argument, that the
and other instruments served as our guide in arriving at the foregoing non-delivery of the oil well cement is not a proper subject for arbitration, the
conclusion: failure of the replacement cement to conform to the specifications of the contract
is a matter clearly falling within the ambit of Clause 16. In this contention, we find
Art. 1373. If some stipulation of any contract should admit of merit. When the 4,300 metric tons of oil well cement were not delivered to the
several meanings, it shall be understood as bearing that import petitioner, an agreement was forged between the latter and the private
which is most adequate to render it effectual. respondent that Class "G" cement would be delivered to the petitioner as
replacement. Upon inspection, however, the replacement cement was rejected
Art. 1374. The various stipulations of a contract shall be as it did not conform to the specifications of the contract. Only after this latter
interpreted together, attributing the doubtful ones that sense circumstance was the matter brought before the arbitrator. Undoubtedly, what
which may result from all of them taken jointly. was referred to arbitration was no longer the mere non-delivery of the cargo at
the first instance but also the failure of the replacement cargo to conform to the
Sec. 11. Instrument construed so as to give effect to all specifications of the contract, a matter clearly within the coverage of Clause 16.
provisions. In the construction of an instrument, where there are The private respondent posits that it was under no legal obligation to make
several provisions or particulars, such a construction is, if replacement and that it undertook the latter only "in the spirit of liberality and to
possible, to be adopted as will give effect to all. foster good business relationship". Hence, the undertaking to deliver the
replacement cement and its subsequent failure to conform to specifications are
Thus, this Court has held that as in statutes, the provisions of a contract should not anymore subject of the supply order/contract or any of the provisions thereof.
not be read in isolation from the rest of the instrument but, on the contrary, We disagree.
interpreted in the light of the other related provisions. The whole and every part
of a contract must be considered in fixing the meaning of any of its harmonious As per Clause 7 of the supply order/contract, the private respondent undertook to
whole. Equally applicable is the canon of construction that in interpreting a deliver the 4,300 metric tons of oil well cement at "BOMBAY (INDIA) 2181 MT
statute (or a contract as in this case), care should be taken that every part and CALCUTTA 2119 MT". The failure of the private respondent to deliver the
thereof be given effect, on the theory that it was enacted as an integrated cargo to the designated places remains undisputed. Likewise, the fact that the
measure and not as a hodge-podge of conflicting provisions. The rule is that a petitioner had already paid for the cost of the cement is not contested by the
construction that would render a provision inoperative should be avoided; private respondent. The private respondent claims, however, that it never
instead, apparently inconsistent provisions should be reconciled whenever benefited from the transaction as it was not able to recover the cargo that was
possible as parts of a coordinated and harmonious whole. unloaded at the port of Bangkok. First of all, whether or not the private
respondent was able to recover the cargo is immaterial to its subsisting duty to
The petitioner's interpretation that Clause 16 is of such latitude as to contemplate make good its promise to deliver the cargo at the stipulated place of delivery.
even the non-delivery of the oil well cement would in effect render Clause 15 a Secondly, we find it difficult to believe this representation. In its Memorandum
mere superfluity. A perusal of Clause 16 shows that the parties did not intend filed before this Court, the private respondent asserted that the Civil Court of
arbitration to be the sole means of settling disputes. This is manifest from Clause Bangkok had already ruled that the non-delivery of the cargo was due solely to
16 itself which is prefixed with the proviso, "Except where otherwise provided in the fault of the carrier. It is, therefore, but logical to assume that the necessary
the supply order/contract . . .", thus indicating that the jurisdiction of the arbitrator consequence of this finding is the eventual recovery by the private respondent of
is not all encompassing, and admits of exceptions as may be provided elsewhere the cargo or the value thereof. What inspires credulity is not that the replacement
in the supply order/contract. We believe that the correct interpretation to give was done in the spirit of liberality but that it was undertaken precisely because of
effect to both stipulations in the contract is for Clause 16 to be confined to all the private respondent's recognition of its duty to do so under the supply
claims or disputes arising from or relating to the design, drawing, instructions, order/contract, Clause 16 of which remains in force and effect until the full
specifications or quality of the materials of the supply order/contract, and for execution thereof.
Clause 15 to cover all other claims or disputes.
We now go to the issue of whether or not the judgment of the foreign court is
enforceable in this jurisdiction in view of the private respondent's allegation that it
is bereft of any statement of facts and law upon which the award in favor of the Court of Appeals adopted the findings and disposition of the Court of
petitioner was based. The pertinent portion of the judgment of the foreign court Agrarian Relations in this wise:
reads:
ORDER We have, therefore, carefully reviewed the evidence and made a
Award dated 23.7.88, Paper No. 3/B-1 is made Rule of the re-assessment of the same, and We are persuaded, nay
Court. On the basis of conditions of award decree is passed. compelled, to affirm the correctness of the trial court's factual
Award Paper No. 3/B-1 shall be a part of the decree. The plaintiff findings and the soundness of its conclusion. For judicial
shall also be entitled to get from defendant (US$ 899,603.77 convenience and expediency, therefore, We hereby adopt by
(US$ Eight Lakhs ninety nine thousand six hundred and three way of reference, the findings of facts and conclusions of the
point seventy seven only) along with 9% interest per annum till court a quo spread in its decision, as integral part of this Our
the last date of realisation. decision.

As specified in the order of the Civil Judge of Dehra Dun, "Award Paper No. 3/B- Hence, even in this jurisdiction, incorporation by reference is allowed if
1 shall be a part of the decree". This is a categorical declaration that the foreign only to avoid the cumbersome reproduction of the decision of the lower
court adopted the findings of facts and law of the arbitrator as contained in the courts, or portions thereof, in the decision of the higher court. This is
latter's Award Paper. Award Paper No. 3/B-1, contains an exhaustive discussion particularly true when the decision sought to be incorporated is a lengthy
of the respective claims and defenses of the parties, and the arbitrator's and thorough discussion of the facts and conclusions arrived at, as in
evaluation of the same. Inasmuch as the foregoing is deemed to have been this case, where Award Paper No. 3/B-1 consists of eighteen (18) single
incorporated into the foreign court's judgment the appellate court was in error spaced pages.
when it described the latter to be a "simplistic decision containing literally, only
the dispositive portion". Furthermore, the recognition to be accorded a foreign judgment is not
necessarily affected by the fact that the procedure in the courts of the country in
The constitutional mandate that no decision shall be rendered by any court which such judgment was rendered differs from that of the courts of the country
without expressing therein dearly and distinctly the facts and the law on which it in which the judgment is relied on. This Court has held that matters of remedy
is based does not preclude the validity of "memorandum decisions" which adopt and procedure are governed by the lex fori or the internal law of the forum. Thus,
by reference the findings of fact and conclusions of law contained in the if under the procedural rules of the Civil Court of Dehra Dun, India, a valid
decisions of inferior tribunals. In Francisco v. Permskul, this Court held that the judgment may be rendered by adopting the arbitrator's findings, then the same
following memorandum decision of the Regional Trial Court of Makati did not must be accorded respect. In the same vein, if the procedure in the foreign court
transgress the requirements of Section 14, Article VIII of the Constitution: mandates that an Order of the Court becomes final and executory upon failure to
pay the necessary docket fees, then the courts in this jurisdiction cannot
MEMORANDUM DECISION invalidate the order of the foreign court simply because our rules provide
After a careful perusal, evaluation and study of the records of otherwise.
this case, this Court hereby adopts by reference the findings of
fact and conclusions of law contained in the decision of the The private respondent claims that its right to due process had been blatantly
Metropolitan Trial Court of Makati, Metro Manila, Branch 63 and violated, first by reason of the fact that the foreign court never answered its
finds that there is no cogent reason to disturb the same. queries as to the amount of docket fees to be paid then refused to admit its
objections for failure to pay the same, and second, because of the presumed
WHEREFORE, judgment appealed from is hereby affirmed in bias on the part of the arbitrator who was a former employee of the petitioner.
toto. Time and again this Court has held that the essence of due process is to be
found in the reasonable opportunity to be heard and submit any evidence one
This Court had occasion to make a similar pronouncement in the earlier may have in support of one's defense or stated otherwise, what is repugnant to
case of Romero v. Court of Appeals, where the assailed decision of the due process is the denial of opportunity to be heard. Thus, there is no violation of
due process even if no hearing was conducted, where the party was given a jurisdiction to pronounce the same is presumptive evidence of a
chance to explain his side of the controversy and he waived his right to do so. right as between the parties and their successors-in-interest by a
In the instant case, the private respondent does not deny the fact that it was subsequent title. The judgment may, however, be assailed by
notified by the foreign court to file its objections to the petition, and subsequently, evidence of want of jurisdiction, want of notice to the party,
to pay legal fees in order for its objections to be given consideration. Instead of collusion, fraud, or clear mistake of law or fact. Also, under
paying the legal fees, however, the private respondent sent a communication to Section 3 of Rule 131, a court, whether of the Philippines or
the foreign court inquiring about the correct amount of fees to be paid. On the elsewhere, enjoys the presumption that it was acting in the lawful
pretext that it was yet awaiting the foreign court's reply, almost a year passed exercise of jurisdiction and has regularly performed its official
without the private respondent paying the legal fees. Thus, on February 2, 1990, duty.
the foreign court rejected the objections of the private respondent and proceeded
to adjudicate upon the petitioner's claims. We cannot subscribe to the private Consequently, the party attacking a foreign judgment, the private
respondent's claim that the foreign court violated its right to due process when it respondent herein, had the burden of overcoming the presumption of its
failed to reply to its queries nor when the latter rejected its objections for a clearly validity which it failed to do in the instant case.
meritorious ground. The private respondent was afforded sufficient opportunity to
be heard. It was not incumbent upon the foreign court to reply to the private The foreign judgment being valid, there is nothing else left to be done than to
respondent's written communication. On the contrary, a genuine concern for its order its enforcement, despite the fact that the petitioner merely prays for the
cause should have prompted the private respondent to ascertain with all due remand of the case to the RTC for further proceedings. As this Court has ruled
diligence the correct amount of legal fees to be paid. The private respondent did on the validity and enforceability of the said foreign judgment in this jurisdiction,
not act with prudence and diligence thus its plea that they were not accorded the further proceedings in the RTC for the reception of evidence to prove otherwise
right to procedural due process cannot elicit either approval or sympathy from are no longer necessary.
this Court.
WHEREFORE, the instant petition is GRANTED, and the assailed decision of the
The private respondent bewails the presumed bias on the part of the arbitrator Court of Appeals sustaining the trial court's dismissal of the OIL AND NATURAL
who was a former employee of the petitioner. This point deserves scant GAS COMMISSION's complaint in Civil Case No. 4006 before Branch 30 of the
consideration in view of the following stipulation in the contract: RTC of Surigao City is REVERSED, and another in its stead is hereby rendered
ORDERING private respondent PACIFIC CEMENT COMPANY, INC. to pay to
. . . . It will be no objection any such appointment that the petitioner the amounts adjudged in the foreign judgment subject of said case.
arbitrator so appointed is a Commission employer (sic) that he SO ORDERED.
had to deal with the matter to which the supply or contract
relates and that in the course of his duties as Commission's
employee he had expressed views on all or any of the matter in
dispute or difference.

Finally, we reiterate hereunder our pronouncement in the case of Northwest


Orient Airlines, Inc. v. Court of Appeals that:

A foreign judgment is presumed to be valid and binding in the


country from which it comes, until the contrary is shown. It is also
proper to presume the regularity of the proceedings and the
giving of due notice therein.

Under Section 50, Rule 39 of the Rules of Court, a judgment in


an action in personam of a tribunal of a foreign country having

Potrebbero piacerti anche