LIBERACIONES EDIFICIO 24/02/2020-25/02/2020

Partida
PISO 1
PISO 1
PISO 1
PISO 1
PISO 1
2/24/2020 PISO 2
PISO 2
PISO 3
PISO 3
PISO 3
PISO 2
PISO 1
PISO 2
2/25/2020 PISO 3
PISO 1
PISO 2
LIBERACIONES EDIFICIO 24/02/2020-25/02/2020
Partida
DESCARGA DE MATERIAL
TRAZOS PARA ZAPATA 1B/2J
ACERO ZAPATA 1B/2J
PERFILADO DE EXCAVACION PARA FALSA ZAPATA 1A´-1B/2I-2J
LIBERACION DE EXCAVACION PARA FALSA ZAPATA 1A´- 1B/ 2I - 2J
LIBERACION DE ACERO EN TECHO 1ER PISO 2H - 2I´/1A-1B
LIBERACION DE ENCOFRADO DE TECHO 1ER PISO 2H-2I´/1A-1B
LIBERACIONTRAZOS 2DO PISO 2F-2G/1B-1C
LIBERACION DE ACERO 2DO PISO 2F-2G/1B-1C
LIBERACION DE ENCOFRADO 2 PISO 2F-2G/1B-1C
LIBERACION PARA ENCOFRADO COLUMNA 2DO PISO 2G/1A
CONCRETO PARA ZAPATA 1B/2J
CONCRETO PARA TECHO 1ER PISO 2H - 2I´/1A-1B
CONCRETO PARA TECHO 1ER PISO 2F-2G/1B-1C
CONCRETO PARA COLUMNA 2DO PISO 2G/1A
CONCRETO PARA FALSA ZAPATA 1A´-1B/2I-2J
Horario aprox.
10:30 - 13:00
11:00 - 11:30
17:00
17:00
17:00
14:00PM
15:00PM
12:00
14:00 PM
16:00 PM
12:00
0:30
1:00
3:00
4:30
5:00