Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Program of work for the construction of 1 unit two (2) Storey building
Multipurpose Hall of Brgy.Anahawan,Sibagat Agusan del Sur
Source of Fund :
Direct Cost:
Labor:
35 days for @ 230 / day = 8,050.00
a.) materials
1. FOR EXCAVATION:
Man-day Capability = 1.20 cu.m/day
No. of day Required = 50 / 1.20 = 41.66
S AY = 42 days
2. FOR HAULLING:
Man-day Capability = 3 cu.m/day
No. of Day Required = 50 / 3 = 16.66
S AY = 17 days
Direct Cost
a.) Labor for Excavation 42 days @ 150 /day = 6,300.00
b.) Labor for Haulling 17 days @ 150 /day = 2,550.00
SUB DIRECT COST 8,850.00
DEANNE P. PUDALAN
PPDO
Approved:
DATE:
NAME/ LOCATION OF PROJECT: Appropriation
Construction of Multi Purposed Hall
Extension of Brgy. Anahawan Sibagat, Agusan Source of fund:
del Sur. 1 115,000.00 PDF
2 80,000.00 MDF
Total 195,000.00
PROJECT CATEGORY :
Building
PROJECT DESCRIPTION :
1. Installation of conc. Footing/ Pedestall
2. Installation of conc. Flooring
3. Installation of CHB Wall Benches/with plaster finish
4. Installation of corr. G.l sht Roofing
100% 195,000.00
ESTIMATED COST:
A DIRECT COST:
1 Mobilization / Demobilization
2 Materials 76.08% 148,352.80
2. Iv 2.1 Supply/ Delivery / Freight & handling
2.2 Testing of Materials
3. Labor (Including fringe benefits) 23.92% 46,647.20
4. Equipment Expenses
4.1 Rental
4.2 Fuel & Oil
4.3 Quarry fee
B. INDIRECT COST
1. Overhead, Contingency, Miscellaneous
(7% to 12% A1 to A4 )
2. Profit (5% to 12% of A1 to A4)
3. Coprehensive All Risk Insurance
(1.5% A1 TO A4)
4 VAT ( 10% TO A3 TO A4)
SUB -TOTAL (CONTRACT COST)
FREIGHT AND HANDLING
II ESTIMATED GOVERNMENT EXPENDITURES
1. Engineering and Administrative Overhead
(3% of A1 to A4 )
2. ROW/ Site Acquision
3. Materials to up furnished by the Government
SUB-TOTAL
CHECKED/VERIFIED: Approved:
Direct cost;
a) Equipment Rental ( w/ operator oil and fuel)
1 unit Grader for 15.00 hrs. @ 1,553.00 /hr. = 23,295.00
Equipt. Cost = 23,295.00
b) Labor;
4 Laborer for 2 days @ 200 /day = 1,600.00
1 foreman for 2 days @ 450 /day = 900.00
Labor cost = 2,500.00
Sub-Direct Cost 25,795.00
d) Compaction:
Tasked rate for Roller = 180 m²/hr
No. of hrs. required = 6,000 / 180 = 33.30
Direct Cost:
a.) Materials:
QTY. Unit Description Unit Cost
1 Drum Chemical Road Pocker ( 200 Letter ) 580,000.00
3 pcs Emty Drum 559.00
Material Cost =
b.) Labor:
5 Laborer for 10 days @ 200 /day =
1 foreman for 10 days @ 450 /day =
Labor cost =
PR O J E CT C O ST
wan
hrs.
hrs.
hrs.
days
days
hrs.
Total
580,000.0
1,677.00
581,677.00
10,000.00
4,500.00
14,500.00
46,590
61,439
20,000
128,028.50
724,205.50
750,000.50
EDNA A. PERANG
MPDC
G. LAMANILAO,MD
Muncipal Mayor
6/7/2012
Repubic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
Estimates and Bill of Material for the Rehabilitation of Comfort Room of Day Care
Center of Brgy. Anahawan Sibagat Agusan del Sur
S AY , , , , P 5,000.00
FELIPE S. TINDUGAN
Brgy. Secretary SOTERO B. APAT, JR
Municipal Engineer
Approved by:
JOEL S. QUETORIANO
Brgy. Captain
Repubic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
Program of Work for the Rehabilitation, Using R-T 20 Soil stabilizer from station ( km 0+50 to km 1+50 )
in Brgy. Anahawan Farm to Market Road Sibagat, Agusan del Sur
Source of Fund: 20% MDF
Amount: P 750,000.00
ITEM I - EXCAVATION
a) Scrapping/Clearing/Spreading
Road Dimension: Length = 1,000 meters
Width = 4 m
Depth = 0.18 m
QTY. = 1,000 m x 4 = 4,000
Tasked Rate of Grader Scarifier = 180 sq.m/hr
No. of hrs Required = 4,000 / 180 = 22.22
S AY = 22 hrs.
cost of chemical ( RT - 20 Soil stabilizer ) 200 liters @ 3,000 /liter = 600,000.00
b) Compaction:
QTY. = 1,000 x 5 m
= 5000 m²
c) Water sprinkling
QTY. = 1,000 x 4 = 4,000
Water Sprinkler truck capability = 400 sq.m/hr.
No. of hrs. required = 4,000 / 400 = 10
S AY , , , , , , , , 750,000.00
+50 to km 1+50 )
Sq.m
hrs.
hrs.
sq.m
hrs.
NA A. PERANG
MPDC
G. LAMANILAO,MD
Muncipal Mayor
Repubic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
Program of Work for Rehabilitation of Road of Brgy. Anahawan, Sibagat, Agusan del Sur
b) Compaction:
Quantity = 1,848 sq.m.
Tasked rate for Roller = 168 sq.m./hr
No. of hrs. Required = 1,848 / 168 = 11
Direct Cost:
EQUIPT. RENTAL ( w/ operator oil and fuel )
1 Unit Grader for 12 hrs. @ 1,553.00 /hr. = 18,636.00
1 Unit Roller for 11 hrs. @ 1,845.00 /hr. = 20,295.00
PR O J E CT C O ST 40,000.00
n del Sur
hrs.
hrs.
ng Approval :
NA A. PERANG
MPDC
G. LAMANILAO,MD
Muncipal Mayor
10/12/2012
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
ITEM I - EXCAVATION;
b. Contingency = 1.9
APPROVED;
JOEL S. QUITORIANO
Brgy. Captain
1/15/2014
Repubic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
b) Compaction:
QTY. = 3,200.00 x 5 m
= 16,000.00 m²
Tasked rate of roller / Compacto = 150.00 m²/hr.
No. of hrs. Required = 3,200.00 / 150
= 21.33 hrs. @
EQUIPT. RENTAL COST:
1 unit Grader for hrs. @ 21
2,000.00 /hr. = 42,666.67
1 unit Roller/compactor for
hrs. @ 21
2,400.00 /hr. = 51,200.00
EQUIPTMENT RENTAL COST 93,866.67
b, ) MOBILIZATION ……………………………………………………………………. 15,000.00
TOTAL EQUIPT.RENTAL COST 108,866.67
a) Spreading:
Tasked Rate of Grader = 50.00 cu.m/hr
No. of hrs Required = 745.20 / 50
S AY = 14.90 hrs.
b) Compaction:
= 745.20 cu.m
Tasked rate of roller / Compacto = 75.00 m3/hr.
No. of hrs. Required = 745.20 / 75.00
= 9.94 hrs. @
I.) EQUIPT. RENTAL COST:
1 unit Grader for 15 hrs. @ 2,000.00 /hr. = 29,808.00
1 unit Roller/compactor for 10 hrs. @ 2,400.00 /hr. = 23,846.40
EQUIPTMENT RENTAL COST 53,654.40
ii.) MATERIALS COST :
a) Spreading:
Tasked Rate of Grader = 50.00 cu.m/hr
No. of hrs Required = 621.00 / 50
S AY = 12.42 hrs.
b) Compaction:
= 621.00 cu.m
Tasked rate of roller / Compacto = 75.00 m3/hr.
No. of hrs. Required = 621.00 / 75.00
= 8.28 hrs. @
I.) EQUIPT. RENTAL COST:
1 unit Grader for 12 hrs. @ 2,000.00 /hr. = 24,840.00
1 unit Roller/compactor for 8 hrs. @ 2,400.00 /hr. = 19,872.00
EQUIPTMENT RENTAL COST: 44,712.00
ii.) MATERIALS COST :
i.) Excavation :
Volume = 0.8 m x 0.5 m x
400 m
= 160 cu.m
Tasked Rate of Labor :
Manual for 10 Laborer : 15 cu.m/day
a.) Materials
QTY. UNIT DESCRIPTION UNIT COST TOTAL
250 bags Portland Cement 260.00 65,000.00
40 cu.m Fine Sand 690.00 27,600.00
30 cu.m Gravel Mixed 780.00 23,400.00
335 length 10mm x 6m RSB Def. 222.00 74,370.00
5000 pcs. CHB # 4 12.00 60,000.00
40 kls. G.I Tie Wire 100.00 4,000.00
MATERIAL COST : 254,370.00
b.) Labor : 39.840% of the Total Materials Cost 101,344.27
TOTAL ITEM COST 382,380.94
Estimates & Bill of Materials for the Construction of Multi-Purpose Hall Building ( PHASE II )
BRGY. ANAHAWAN,SIBAGAT,AGUSAN DEL SUR.
THELMA G. LAMANILAO,MD
EDNA A. PERANG Muncipal Mayor
MPDC
Repubic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
1/15/2014
MUNICIPAL ENGINEERING OFFICE
DIRECT COST :
a.) MATERIALS
QTY. UNIT DESCRIPTION UNIT COST TOTAL
4,860.00 bags Portland Cement 260.00 1,263,600.00
204.75 cu.m Fine Sand 690.00 141,277.50
409.50 cu.m Gravel 3/4 900.00 368,550.00
100 length 12mm x 6m RSB Def. 280.00 28,000.00
45 pcs. 12mm x 6m RSB Plain Bars 280.00 12,600.00
600 bdft 2 x 6 x 12 Form Lumber 30.00 18,000.00
4 bandle 1 x 2 x 8 - Lumber Stick 300.00 1,200.00
5 pcs. Hack Saw Blade 85.00 425.00
40 kls. Assorted Nails 100.00 4,000.00
MATERIAL COST : 1,837,652.50
b.) LABOR : 39.40% of the Total Materials Cost 724,035.09
TOTAL ITEM COST 2,561,687.59
SPL - I LINE CANAL :
i.) Excavation :
Volume = 0.8 m x 0.5 m x
500 m
= 200 cu.m
Tasked Rate of Labor :
Manual for 10 Laborer 15 cu.m/day
= 200 cu.m / 15 cu.m/day
= 13.33333 days
LABOR COST :
10.00 Laborers (manual Excavation) 13 x 250.00 = 33,333.33
LABOR COST . . .P 33,333.33
ii.) CHB LAYING:
Volume = 0.4 m x 0.1 m x
500 m
= 20 cu.m
DIRECT COST :
a.) MATERIALS
QTY. UNIT DESCRIPTION UNIT COST TOTAL
250 bags Portland Cement 260.00 65,000.00
40 cu.m Fine Sand 690.00 27,600.00
30 cu.m Gravel Mixed 780.00 23,400.00
335 length 10mm x 6m RSB Def. 222.00 74,370.00
5000 pcs. CHB # 4 12.00 60,000.00
40 kls. G.I Tie Wire 100.00 4,000.00
MATERIAL COST : 254,370.00
b.) LABOR : 39.840% of the Total Materials Cost 100,221.78
TOTAL ITEM COST 387,925.11
Estimates and Bill of Materials for the Construction of Multi-Purposed Tribal Hall
of Barangay Anahawan Sibagat Agusan del Sur
Direct Cost:
a.) Materials
Quantity Unit Description Unit Cost TOTAL
180 bd.ft 6'' x 6'' x 10' ( 6 pcs Post) Tugas 28.00 5,040.00
96 bd.ft 2'' x 6'' x 12' ( 8 pcs Girts ) Gimilina / Equivalent 20.00 1,920.00
56 bd.ft 2'' x 6'' x 14' ( 4 pcs Girts ) Gimilina / Equivalent 20.00 1,120.00
84 bd.ft 2'' x 6'' x 14' ( 6 pcs B-Chord ) Gimilina / Equivalent 20.00 1,680.00
72 bd.ft 2'' x 6'' x 12' ( 6 pcs T-Chord ) Gimilina / Equivalent 20.00 1,440.00
80 bd.ft 2'' x 6'' x 10' ( 8 pcs B-Chord & H.T ) Gimilina / Equivalen 20.00 1,600.00
56 bd.ft 2'' x 6'' x 14' ( 4 pcs T-Chord & H.T ) Gimilina / Equivalent 20.00 1,120.00
12 bd.ft 6'' x 6'' x 12' ( 1 pcs K-Post) Gimilina / Equivalent 20.00 240.00
100 bd.ft 2'' x 6'' x 10' ( 10 pcs W-Member ) Gimilina / Equivalent 20.00 2,000.00
42 bd.ft 2'' x 3'' x 14' ( 6 pcs Purlins ) Gimilina / Equivalent 20.00 840.00
72 bd.ft 2'' x 3'' x 12' ( 12 pcs Purlins ) Gimilina / Equivalent 20.00 1,440.00
16 bd.ft 2'' x 3'' x 16' ( 2 pcs Purlins ) Gimilina / Equivalent 20.00 320.00
20 bd.ft 2'' x 3'' x 10' ( 4 pcs Purlins ) Gimilina / Equivalent 20.00 400.00
24 bd.ft 2'' x 6'' x 8' ( 3 pcs Door Jamb ) Gimilina / Equivalent 20.00 480.00
16 bd.ft 2'' x 6'' x 8' ( 3 pcs W- Jamb ) Gimilina / Equivalent 20.00 320.00
64 bd.ft 2'' x 6'' x 8' ( 8 pcs W- Jamb ) Gimilina / Equivalent 20.00 1,280.00
74.65 bd.ft 1'' x 8'' x 14' ( 8 pcs Facia Board ) Gimilina / Equivalent 20.00 1,493.00
213.3 bd.ft 2'' x 2'' x 8' ( 80 pcs Scafolding ) Gimilina / Equivalent 20.00 4,266.00
5 kgs C.W. Nails # 6 75.00 375.00
6 kgs C.W. Nails # 5 75.00 450.00
10 kgs C.W. Nails # 4 75.00 750.00
4 kgs C.W. Nails # 3 75.00 300.00
4 kgs C.W. Nails # 2 1/2 75.00 300.00
3 kgs C.W. Nails # 2 75.00 225.00
2 kgs C.W. Nails # 1 1/2 75.00 150.00
MATERIAL COST . . . . P 29,549.00
b.) Labor Cost: 35 % Material Cost . . . . . . . . . . . . . . . . 10,342.15
SUB-DIRECT COST . . . . . P 39,891.15
Approved:
JOEL S. QUITORIANO
Barangay Captain
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
3/10/2015
1.) STRIPPING
Quantity = 2,100.00 cu.m
2.) RESHAPING
Quantity = 3,600.00 cu.m
Where: Length = 3,000.00 m
Width = 6.00 m
Depth = 0.20 m
DIRECT COST :
a. ) Equipment Rental with operator fuel & oil
a.) SPREADING
Tasked rate for GRADER = 37.50 cu.m / hr
No.of Hour Required = 2,587.50 c.u.m = 69.00 Hours
37.50 c.u .m./hr
b.) COMPACTION
Tasked rate for ROLLER = 21 cu.m / hr
No.of Hour Required = 2587.5 c.u.m = 123.21 Hours
21 c.u .m./hr
DIRECT COST :
a.) Materials
QTY UNIT DESCRIPTION UNIT COST TOTAL COST
2,587.50 cu.m Aggregate Sub-Base Coarse 404.61 1,046,928.38
MATERIAL COST 1,046,928.38
c.) Equipment Rental with OPERATOR OIL & FUEL
1 unit GRADER for 69.00 @hour
2,100.00 per hour = 144,900.00
1 unit ROLLER for 123.21 @hour
2,800.00 per hour = 345,000.00
EQUIPMENT RENTAL COST 489,900.00
ITEM -105- SUB-GRADE PREPARATION ESTIMATED COST . . . P 1,536,828.38
S A Y . . . P 2,000,000.00
SUMMARY OF ESTIMATES
ITEM NO. DESCRIPTION MAT./HANDLING LABOR MATERIAL TOTAL
I-A Concrete Works 1,005.72 2,933.35 8,381.00 12,320.07
I-B Concrete Works 3,719.40 10,848.25 30,995.00 45,562.65
II- Pipe Laying 3,248.64 9,475.20 27,072.00 39,795.84
7,973.76 23,256.80 66,448.00 97,678.56
Approved:
JOEL S. QUITORIANO
Barangay Captain
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
DIRECT COST :
a.) Materials
QTY UNIT DESCRIPTION UNIT COST TOTAL COST
200.00 cu.m Aggregate Sub-Base Coarse 500.00 100,000.00
MATERIAL COST 100,000.00
b.) Labor: Man Power labor / barangay pahina
T O T A L P R O J E C T CO S T 100,000.00
Approved:
JOEL S. QUITORIANO
Barangay Captain
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
Source of Fund :
ITEM I-Earth work and Excavation
Quantity = 30.00 cu.m
man. Day Capability = 1 cu.m / day
6 laborer = 5 days
1 foreman = 5 days
Direct Cost:
Labor:
4 days for @ 250 / day for 5 laborer and foreman
5 Days Operation
6 laborer @ 250 per day 7500.00
1 foreman @ 450 per day 2250.00
Sub.Direct Cost 9,750.00
Total
45,360.00
31,320.00
79.72
76,759.72
26,865.90
₱ 103,625.62
Total
15,840.00
15,840.00
8,000.00
853.40
19,000.00
3,933.00
2,100.00
3,360.00
1,400.00
1,062.03
71,388.43
24,985.95
96,374.38
₱ 200,000.00
200,000.00
GARLIT, CE
EDWARD G. PLAZA
vincial Governor
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
MUNICIPAL ENGINEERING OFFICE
100.00% 200,000.00
12. Breakdown of Estimated Expenditures % of Total TOTAL AMOUNT
A. DIRECT COST ;
1. Mobilization
2. Materials
2.1 Supply / Delivery 74.07% 148,148.15
2.2 Freight & Handling 0.00%
3. Labor
3.1 Direct Labor 25.93% 51,851.85
4. Equipment Expenses
5.Pre- Engineering
6. Supervision
7.Miscellaneous
SUB-TOTAL 100.00% 200,000.00
TOTAL DIRECT COST 100.00% 200,000.00
6 laborer = 5 days
1 foreman = 5 days
Direct Cost:
Labor:
4 days for @ 250 / day for 5 laborer and foreman
5 Days Operation
6 laborer @ 250 per day
1 foreman @ 450 per day
Sub.Direct Cost
Approved :
JOEL S. QUITORIANO
Barangay Captain
POSE HALL BUILDING
AN DEL SUR
7500.00
2250.00
9,750.00
Total
56,280.00
10,880.00
17,850.00
10,200.00
95,210.00
33,323.50
128,533.50
Total
36,400.00
19,440.00
3,746.89
59,586.89
20,855.41
₱ 80,442.30
218,725.80
218,725.80
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
PROGRAM OF WORKS FOR THE CONSTRUCTION OF STREET LIGHT ALONG NATIONAL HIGHWAY
OF BRGY.POBLACION,SIBAGAT,AGUSAN DEL SUR.
SOURCE OF FUND:
Direct Cost :
a.) Materials Cost :
Direct Cost :
a.) Materials Cost :
Qty. Unit Description Unit Cost
20.00 pcs 1/4 Marine Plywood 410.00
433.33 bd.ft 2'' x 2'' x 10' ( 130 pcs ) 20.00
2.00 kgs C.W.Nails # 1 70.00
3.00 kgs C.W.Nails # 3 70.00
2.00 kgs Concrete Nails # 3 110.00
26.00 pcs Moulding 1/2 x 10 80.00
MATERIAL COST . . . . .
Direct Cost :
a.) Materials Cost :
Direct Cost :
a.) Materials Cost :
Direct Cost :
a.) Materials Cost :
67,800.00
23,730.00
91,530.00
Total Cost
8,200.00
8,666.60
140.00
210.00
220.00
2,080.00
19,516.60
6,830.81
26,347.41
Total Cost
7,200.00
3,600.00
9,800.00
2,040.00
1,400.00
160.00
795.00
255.00
950.00
17,000.00
2,800.00
300.00
260.00
17,000.00
46,560.00
16,296.00
62,856.00
Total Cost
3,500.00
130.00
225.00
220.00
75.00
55.00
1,300.00
1,900.00
75.00
125.00
7,605.00
2,661.75
7,605.00
Total Cost
6,600.00
3,750.00
2,250.00
960.00
9,800.00
5,600.00
2,440.00
5,700.00
300.00
195.00
400.00
1,050.00
39,045.00
13,665.75
39,045.00
Total Cost
750.00
2,700.00
560.00
360.00
300.00
1,750.00
2,300.00
700.00
150.00
600.00
450.00
1,400.00
1,500.00
150.00
40.00
1,500.00
420.00
15,630.00
5,470.50
15,630.00
Total Cost
1,350.00
120.00
40.00
60.00
80.00
15.00
80.00
1,745.00
610.75
1,745.00
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
a.) SPREADING:
b.) COMPACTION:
Aggregates :
Hauling:
1,380.00000 cu.m
1,380.00 cu.m x 322.00 per cu.m. P 444,360.00
Total
21,280.00
6,000.00
6,400.00
5,760.00
1,380.00
10,200.00
160.00
160.00
320.00
1,520.00
1,750.00
7,600.00
62,530.00
21,885.50
₱ 84,415.50
Total
7,500.00
540.00
800.00
40.00
115.00
120.00
1,100.00
900.00
180.00
40.00
70.00
50.00
35.00
35.00
11,525.00
4,059.50
15,584.50
₱ 100,000.00
100,000.00
Approved :
MARLON V. SERRANO
Barangay Captain
R SUPPLY
N DEL SUR
Total
1,960.00
1,780.00
1,580.00
1,440.00
150.00
320.00
160.00
80.00
760.00
368.00
8,598.00
3,009.30
₱ 11,607.30
Total
1,050.00
335.00
8,823.38
1,380.00
60.00
11,648.38
4,076.93
15,725.31
Total
2,800.00
2,670.00
2,370.00
936.00
4,140.00
300.00
13,216.00
4,625.60
₱ 17,841.60
Total
680.00
360.00
1,550.00
120.00
1,115.79
3,825.79
₱ 49,000.00
49,000.00
BACK - UP COMPUTATION
DIRECT COST
A.LABOR
1 Foreman for 1 day @ P 450.00 = P 450.00
8 Laborer for 1 days @ P 230.00 = P 1,840.00
P 2,290.00
INDIRECT COST
Pre-Engineering = P
Contingency = P 183.20
Taxes = P 274.80
Hand Tools = P
Material Testing = P
Supervision Cost = P 22.90
Contractor's Profit = P 274.80
755.70
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Item No. : 103(3)
Item Description : FOUNDATION FILL
DIRECT COST
A.MATERIALS
2.00 cu.m Mixed Sand and Gravel @ P 500.00 = P 1,000.00
P 1,000.00
A.LABOR
1 Foreman for 1 day @ P 450.00 = P 450.00
2 Laborer for 1 days @ P 230.00 = P 460.00
P 910.00
INDIRECT COST
Pre-Engineering = P
Contingency = P 152.80
Taxes = P 229.20
Hand Tools = P
Material Testing = P
Supervision Cost = P 19.10
Contractor's Profit = P 229.20
630.30
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Item No. : 105
Item Description : SUBGRADE PREPARATION
B.EQUIPMENT
1 Road Grader for 1 day @ P 9,688.80 = P 9,688.80
1 Road Roller for 1 day @ P 9,571.10 = P 9,688.80
120 Liters Diesel @ P 45.00 = P 5,400.00
2 Liters Oil 40 @ P 75.00 = P 150.00
1 Liters Oil 10 @ P 125.00 = P 125.00
P 25,052.60
B.LABOR
1 Foreman for 1 day @ P 450.00 = P 450.00
1 Road Grader Ope. for 1 day @ P 320.00 = P 320.00
1 Helper for 1 days @ P 230.00 = P 230.00
P 1,000.00
INDIRECT COST
Pre-Engineering = P
Contingency = P 2,084.21
Taxes = P 3,126.31
Mobilization = P 260.53
Material Testing = P
Supervision Cost = P 260.53
Contractor's Profit = P 3,126.31
8,857.88
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Item No. : 200
Item Description : AGGREGATE SUBBASE COURSE
DIRECT COST
A.MATERIALS
2,760 cu.m Mixed Sand and Gravel @ P 500.00 = P 1,380,000.00
P 1,380,000.00
B.EQUIPMENT
1 Road Grader for 6.00 day @ P 9,688.80 = P 58,132.80
1 Road Roller for 7.00 day @ P 9,571.10 = P 67,821.60
1280 Liters Diesel @ P 45.00 = P 57,600.00
26 Liters Oil 40 @ P 75.00 = P 1,950.00
13 Liters Oil 10 @ P 125.00 = P 1,625.00
P 187,129.40
B.LABOR
1 Foreman for 7 day @ P 450.00 = P 3,150.00
1 Road Grader Ope. for 7 day @ P 320.00 = P 2,240.00
1 Road Roller Ope. for 7 day @ P 280.00 = P 1,960.00
2 Helper for 7 days @ P 230.00 = P 3,220.00
P 10,570.00
INDIRECT COST
Pre-Engineering = P 4,500.00
Contingency = P 126,215.95
Taxes = P 189,323.93
Mobilization = P 15,776.99
Material Testing = P
Supervision Cost = P 15,776.99
Contractor's Profit = P 189,323.93
540,917.80
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Item No. : 201
Item Description : BASE COURSE
DIRECT COST
A.MATERIALS
1,380 cu.m Mixed Sand and Gravel @ P 600.00 = P 828,000.00
P 828,000.00
B.EQUIPMENT
1 Road Grader for 3.00 day @ P 9,688.80 = P 29,066.40
1 Road Roller for 3.00 day @ P 9,571.10 = P 28,713.30
540 Liters Diesel @ P 45.00 = P 24,300.00
12 Liters Oil 40 @ P 75.00 = P 900.00
6 Liters Oil 10 @ P 125.00 = P 750.00
P 83,729.70
B.LABOR
1 Foreman for 3 day @ P 450.00 = P 1,350.00
1 Road Grader Ope. for 3 day @ P 320.00 = P 960.00
1 Road Roller Ope. for 3 day @ P 280.00 = P 840.00
2 Helper for 3 days @ P 230.00 = P 1,380.00
P 4,530.00
INDIRECT COST
Pre-Engineering = P 4,500.00
Contingency = P 73,300.78
Taxes = P 109,951.16
Mobilization = P 9,162.60
Material Testing = P
Supervision Cost = P 9,162.60
Contractor's Profit = P 109,951.16
316,028.30
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Item No. : 500
Item Description : REINFORCED CONCRETE PIPE CULVERT
DIRECT COST
A.MATERIALS
10 bags, Portland Cement (40 kgs) @ P 230.00 = P 2,300.00
1 cu.m, washed sand @ P 500.00 = P 500.00
6 Lm 610mm dia. RCPC @ P 2,475.00 = P 14,850.00
P 17,650.00
B.EQUIPMENT
1 1-Tonner Chain Block for 2 day @ P 1,650.00 = P 3,300.00
P 3,300.00
B.LABOR
1 Foreman for 2 day @ P 450.00 = P 900.00
1 Carpenter for 2 day @ P 320.00 = P 640.00
1 Mason for 2 day @ P 320.00 = P 640.00
12 Laborers for 2 days @ P 230.00 = P 5,520.00
P 7,700.00
INDIRECT COST
Pre-Engineering = P
Contingency = P 2,292.00
Taxes = P 3,438.00
Mobilization = P 286.50
Material Testing = P
Supervision Cost = P 286.50
Contractor's Profit = P 3,438.00
9,741.00
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Item No. : 505
Item Description : GROUTED RIPRAP
DIRECT COST
A.MATERIALS
14 bags, Portland Cement (40 kgs) @ P 230.00 = P 3,220.00
1 cu.m, washed sand @ P 500.00 = P 500.00
1 cu.m, washed gravel @ P 600.00 = P 600.00
8 cu.m, 300-500mm dia. Boulders @ P 500.00 = P 4,000.00
P 8,320.00
B.EQUIPMENT
1 Bagger Mixer for 1.00 day @ P 1,650.00 = P 1,650.00
P 1,650.00
B.LABOR
1 Foreman for 1 day @ P 450.00 = P 450.00
1 Carpenter for 1 day @ P 320.00 = P 320.00
1 Mason for 1 day @ P 320.00 = P 320.00
4 Laborers for 1 days @ P 230.00 = P 920.00
P 2,010.00
INDIRECT COST
Pre-Engineering = P
Contingency = P 958.40
Taxes = P 1,437.60
Mobilization = P 119.80
Material Testing = P
Supervision Cost = P 119.80
Contractor's Profit = P 1,437.60
4,073.20
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
cu.m
cu.m
days
/ cu.m
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
cu.m
cu.m
days
/ cu.m
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Ha.
Ha.
days
/ Ha.
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
cu.m.
cu.m.
days
/ cu.m.
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
cu.m.
cu.m.
days
/ cu.m.
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
lm
lm
cu.m
cu.m
cu.m
days
/ lm
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
cu.m
cu.m
days
/ lm
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
1,935.23
1.7
1,758.43
50.00
320.00
370.00
-
183.20
274.80
-
-
22.90
274.80
3,045.70
260.45
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
1,935.23
1.7
1,758.43
1170.9415
1,000.00
50.00
80.00
130.00
-
152.80
229.20
-
-
19.10
229.20
2,540.30
2,000.87
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
1,935.23
7.6
1,758.43
50.00 8,074.00
50.00 8,074.00
420
100.00 25,052.60
50.00
50.00
40.00
140.00
-
2,084.21
3,126.31
260.53
-
260.53
3,126.31
34,910.48
38,789.43
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
1,935.23
7.6
2760
5.52
6.9
1170.9415
###
300.00
350.00 8,074.00
650.00 187,129.40
350.00
350.00
350.00
560.00
1,610.00
4,500.00
###
###
15,776.99
-
15,776.99
###
###
882.76
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
1,935.23
7.6
1380
3.45
828,000.00
150.00
150.00
300.00 83,729.70
150.00
150.00
150.00
240.00
690.00
4,500.00
73,300.78
###
9,162.60
-
9,162.60
###
###
1,026.91
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
1,935.23
7.6
0 0
2.731148
6.9
17,650.00
100.00
100.00 3,300.00
100.00
100.00
100.00
960.00
1,260.00
-
2,292.00
3,438.00
286.50
-
286.50
3,438.00
38,391.00
6,398.50
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
1,935.23
1.7
0 0
3.484515
8,320.00
50.00
50.00 1,650.00
50.00
50.00
50.00
160.00
310.00
-
958.40
1,437.60
119.80
-
119.80
1,437.60
16,053.20
5,298.06
Baltazar B. Lapa
PRC Reg. No.: 8386
DATE: 1-12-67
TIN: 160-878-847
PTR: 0269122
Date: 1-12-11
Place: Butuan City
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
6 laborer = 5 days
1 foreman = 5 days
Direct Cost:
Labor:
4 days for @ 250 / day for 5 laborer and foreman
5 Days Operation
6 laborer @ 250 per day
1 foreman @ 450 per day
Sub.Direct Cost
Approved :
JOEL S. QUITORIANO
Barangay Captain
POSE HALL BUILDING
AN DEL SUR
7500.00
2250.00
9,750.00
Total
56,280.00
10,880.00
17,850.00
10,200.00
95,210.00
33,323.50
128,533.50
Total
36,400.00
19,440.00
3,746.89
59,586.89
20,855.41
₱ 80,442.30
218,725.80
218,725.80
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT
MUNICIPAL ENGINEERING OFFICE
4 laborer = 2 days
1 foreman = 2days
Direct Cost:
Labor:
2 Days Operation
4 laborer @ 300 per day ₱ 2,400.00
1 foreman @ 450 per day ₱ 900.00
Sub.Direct Cost ₱ 3,300.00
Approved :
JOEL S. QUITORIANO
Barangay Captain
Republic of the Philippines
Province of Agusan del Sur
MUNICIPALITY OF SIBAGAT