Sei sulla pagina 1di 1

THE CONTRACTOR IS TO CHECK ALL DRAWINGS BEFORE

STARTING WORK.

ANY DISCREPANCIES FOUND ON THIS DRAWING OR BETWEEN


THIS DRAWING AND ANY OTHER DRAWING ISSUED BY ANY
SONTAY PA-267 PARTY ARE TO BE NOTIFIED TO CHICK MASTER UK.
RADIUS
DRAWINGS ARE NOT TO BE SCALED.
0.24r
DIMENSIONS ARE TO BE CONFIRMED ON SITE.

SENSOR DUCT

+ -

Low Port
High Port
6mm I.D TUBING IS SUGGESTED FOR TUBING
LENGTHS UP TO 30.5M, 7mm I.D TUBING
LENGTHS UP TO 91.5M AND 9.5mm I.D FOR
TUBING LENGTHS UP TO 274M.

NOTES
NOTES

EACH AREA TO BE CONTROLLED WILL TYPICALLY REQUIRE 2 TERMINATION BOXES - 1 FOR THE THE SENSOR SHOULD BE INSTALLED NOT LESS THAN 2 METERS DOWNSTREAM FROM ANY HEATING
OUTSIDE REFERENCE LINE, AND 1 FOR THE ROOM REFERENCE LINE. OUTSIDE PRESSURE LINES OR COOLING DEVICES, SOURCE OF MOISTURE SUCH AS HUMIDIFIER, FAN OR BEND IN THE
DUCTWORK.
MAY BE SHARED BY MORE THAN 1 ZONE, BUT EACH ZONE MUST HAVE ITS OWN INSIDE LINE AND
THE SENSORS SHOULD BE MOUNTED WITH THE HOLES IN THE END OF THE PROBE ORIENTATED
BOX. MOUNT TERMINATION BOX APPROX. 7' ABOVE FINISHED FLOOR IN AREA FREE OF
DIRECTLY INTO THE AIR FLOW OVER THE SENSING ELEMENT.
TURBULENT AIR MOVEMENT (AWAY FROM SUPPLY / EXHAUST FANS, DUCTWORK AND FRESH AIR
INTAKES). HIGHEST POINT OF PRESSURE LINES SHOULD BE DIRECTLY ABOVE ROOM CONTROL.
LINES SHOULD HAVE DOWNWARD SLOPE TOWARDS TERMINATION BOX TO ALLOW CONDENSED
WATER TO FLOW AWAY FROM ROOM CONTROLLERS.

PRESSURE SENSOR (SONTAY PA-267) AIR VELOCITY SENSOR (SONTAY AV-DSP)

Plenum Pressure Sensor Room Pressure Sensor Dust Plenum Pressure Sensor Room Pressure Sensor
(+ to Room, - Open) (+ to Room, - to Outside) (+ to Room, - Dust Plenum) (+ to Room, - to Outside)

+ - + - - + + -

PLENUM

DUST PLENUM

DUST PLENUM
MACHINES SETTER ROOM MACHINES MACHINES HATCHER ROOM MACHINES

SETTER ROOM PRESSURE SENSOR INSTALLATION (SONTAY PA-267) HATCHER ROOM PRESSURE SENSOR INSTALLATION (SONTAY PA-267)

Room Pressure Sensor


(+ to Room, - to Outside) SONTAY PA-267

+ -
PRESSURE + -
DM TH
TUBING INTO
DUCT.
23/12/2013
CIRCULAR DUCT
N.T.S
6mm I.D TUBING IS SUGGESTED FOR TUBING
LENGTHS UP TO 30.5M, 7mm I.D TUBING
CHICK HOLDING/ CHICK LENGTHS UP TO 91.5M AND 9.5mm I.D FOR
PROCESSING ROOM TUBING LENGTHS UP TO 274M.
NOTES

MOUNT THE UNIT ON THE DUCT BY DRILLING TWO HOLES AT 142mm CENTRES AND
FIXING THE UNIT WITH SELF-TAPPING PAN HEAD SCREWS.
PUSH FIT THE PRESSURE TUBING ONTO THE PRESSURE PORTS ON THE UNITS.
ENSURE THAT THE Hi & Lo PORTS HAVE BEEN CORRECTLY IDENTIFIED.

PROCESSING ROOMS PRESSURE SENSOR INSTALLATION (SONTAY PA-267) DUCT MOUNTED PRESSURE SENSOR INSTALLATION (SONTAY PA-267)

TYPICAL SENSOR DETAILS


EXAMPLE-M-001-A 1/2

Potrebbero piacerti anche