THE PROJECT

Six-laning of NH-16 from Ranastalam to Anandpuram (Visakhapatnam) (from km


634.000 to km 681.000) in the state of Andhra Pradesh under NHDP Phase-V (Package
II)on Hybrid Annuity Mode

Client:
National Highways Authority of India

Independent Engineer:
MSV International Inc. in association with Armenge
Engineering and Management Consultants Pvt Ltd

Concessionaire:
Ashoka Ranastalam Anandapuram Road Limited
Index

✓ Key Plan
✓ Salient Features
✓ Scope of Work
✓ Linear Progress – Highway
✓ Linear Progress – Structures
✓ Project Milestones
✓ Payment Milestones
✓ Critical Issues
✓ PMIS information
✓ Project Photos
Key Plan
Salient Features
S.No. Name Description

1 Length of Project 47.000 Kms.


2 Contract / Phase NHDP Phase-V (Package-II)
3 Bid Project Cost INR. 1187.10 Crore
4 Authority National Highways Authority of India (NHAI)
M/s MSV International Inc. in association with Armenge
5 Independent Engineer Engineering and Management Consultants Pvt Ltd

6 Concessionaire Ashoka Ranasthalam Anandapuram road Ltd (ARARL)


7 PMC & Design Consultant Samarth Infraengg Technocrats Pvt Ltd.
8 EPC Contractor M/s Ashoka Buildcon Limited
9 Safety Consultant M/s Info Trans Engineers Pvt. Ltd.
10 Date of Agreement 2nd May 2017
11 Design Consultant (MJB) M/s ASC Infratech Pvt. Ltd. Noida.
12 Appointed Date 16th November 2017
13 Construction Period 910 Days from Appointed Date.
14 Schedule Date of Completion 13th May 2020
Scope Of Work
Sl.No. Item Description
1 Total Length of Project 47.00km
2 Service Road Length/Slip Road 76.801km (LHS & RHS)
3 Width of Service Road & Slip Road 7.00 m / 5.50m
4 Major Bridge (NEW) 2 No.
5 Minor Bridge on Service Road 8 No.
6 Minor Bridge on Main Carriageway 2 No.
7 Vehicular Underpass 7 No.
8 Lower Vehicular Underpass 13 No.
9 Flyover (30 m) 1 No.
10 Interchanges 1 No.
11 Cross Drainage Work 147 Nos
12 Major Intersection 2 Nos
13 Minor Intersection 52Nos
14 Toll Plaza 1 No
15 Truck Lay Bye 1 No
16 Bus Bay with Bus Shelter 36 Nos
17 Rest Area 1 No
18 Helipad 1 No
Linear Progress – Highway (31/12/2019)

ABSTRACT OF LINEAR PROGRESS FOR MAIN CARRIAGE WAY


Total Progress In Kms
Sr. No Particulars
SCOPE LHS RHS Total % Achieved
1 Embankment Top 91.60 38.44 37.63 76.07 83.05%
2 Subgrade Top 91.60 38.44 37.38 75.82 82.77%
3 GSB 91.60 37.26 37.16 74.42 81.24%
4 CTB 91.60 36.68 36.18 72.86 79.54%
5 WMM 91.60 36.01 35.43 71.44 77.99%
6 DBM 91.60 35.30 34.97 70.27 76.71%
7 BC 91.60 32.61 31.94 64.55 70.74%

ABSTRACT OF LINEAR PROGRESS FOR SERVICE ROAD


Total Progress In Kms
Sr. No Particulars
SCOPE LHS RHS Total % Achieved
1 Embankment Top 76.16 36.18 35.90 72.08 94.64%
2 Subgrade Top 76.16 36.17 35.41 71.58 93.98%
3 GSB 76.16 36.07 35.41 71.48 93.85%
4 CTSB 76.16 35.24 34.51 69.75 91.58%
5 WMM 76.16 34.71 34.47 69.17 90.83%
6 BC 76.16 34.64 34.41 69.05 90.66%
7 Drain Wall 76.16 36.63 36.79 73.42 96.40%
8 Drain Slab 76.16 36.56 36.72 73.28 96.22%
Linear Progress – Structures (31/12/2019)
%
S.No Description Scope (Nos) Completed In Progress Remarks
Completion
1 Culverts
a)Hume Pipe Culverts 88 84 4 95.45%
b)Box Culverts 31 26 3 83.87%
2 Minor Bridges
a)Widening 5 5 100%
b)New 4 4 100%
Ch. 673+710 - Substructure Works in
c)Reconstruction 1 1 45%
Progress
3 Underpass/Flyover/Interchange
Ch. 675+740 (RHS) - Superstructure
a)LVUP 13 12.5 0.5 96.15%
Work completed as on 21/1/20
Ch. 676+200 (LHS) - Superstrucutre
Works in Progress
b)VUP 7 5.5 1.5 78.57%
Ch. 656+040 - Foundation &
Substructure Works in Progress
c)Flyover (Structure) 1 1 100%
Super Structure Works are in
d)Interchange (Structure) 1 1 75%
Progress.
4 Major Bridges 2 2 100%
5 RE Wall Erection (Sqm) 1,86,272 1,54,036 32,236 82.69%
Status of Project Milestone

Duration from Due Date of


Milestone No. (%) Progress Remarks
Appointed Date Milestone

Milestone - 1 290 Days 1st Sept 2018 20% Achieved

Milestone - 2 430 Days 19th Jan 2019 35% Achieved

Milestone - 3 690 Days 6th Oct 2019 75% Achieved

Scheduled Completion 77.38% as on


910 Days 13th May 2020 100%
Date 31/12/2019
Status of Payment Milestone

Milestone No. Physical Progress Due Date of Milestone Remarks

Milestone - 1 10% 8% (eight per cent) of the Bid Project Cost Achieved

Milestone - 2 30% 8% (eight per cent) of the Bid Project Cost Achieved

Milestone - 3 50% 8% (eight per cent) of the Bid Project Cost Achieved

Milestone - 4 75% 8% (eight per cent) of the Bid Project Cost Achieved

Milestone - 5 90% 8% (eight per cent) of the Bid Project Cost


Change of Scope

The detailed proposals along with the Cost implications are submitted to the Authority.
The approval and issuance of COS orders is awaited

S.No COS Item Block Costing


(Rs.)
Positive COS
Construction of Continuous Service roads - Compliance of
1 8,31,45,217
Development Stage Safety Audit Report

2 Development of Minor Junction at Km. 639+900 & Km. 658+900 1,42,30,281

Total Amount (Rs) A 9,73,75,498


Negative COS
Widening instead of reconstruction of Box Culverts at Ch. 672+236,
1 76,54,398
& Ch. 672+915.
Widening instead of reconstruction of Box Culverts at Ch. 664+834,
2 & Ch.676+689. 28,33,621

Total Amount (Rs) B 1,04,88,019


Net Total Amount (Rs) (A-B) 8,68,87,479
Critical Issues – Land Availability

The following are the locations for which the land is yet to be made available to the Concessionaire. The
Concessionaire has appraised the Authority to descope the works in the respective Land Parcels form the
Scope of work.

Type of work affected due to


S.No. Description Chainage Side
non-availability of land

New Interchange (Approaches


1 New Interchange 665+640 BHS
and Ramps)

2 Helipad Yet to decide - Helipad

3 Rest Area 663+500 LHS Construction of Rest Area

4 Truck Parking 680+421 RHS Construction of Truck Layby


Service Road from Ch.
5 Service Road 671+275 RHS
671+275 to Ch. 671+380
Critical Issues Contd..

Utility Shifting (LILO Line)

The Superintending Engineer had not accorded the approval for commencement of shifting the 132 Kv Line at
Pydibhimavaram due to the difference in approved rates by NHAI as against estimated rates by APTRANSCO.

Local public demanding for Box Culvert at Ch. 651+250

The Concessionaire has intimated the Authority regarding the local public of Pusapatirega have
confronted the Concessionaire and have stopped the works of approach construction at Ch.
651+400. They are demanding to construct a box culvert instead of widening of existing pipe
culvert at Ch. 651+250 as per Concession Agreement. The construction of underpass approaches is
on critical path of activities. The Concessionaire has intimated the Authority regarding the issue
with a request to provide necessary administrative support to resume the works at said location.
Pending Issues Contd.

Sr.No. Particulars Amount (Rs) Remarks

Concessionaire on behalf of the Authority has , paid 3% towards The Payment is yet to
1 spare approved by APEPDCL which is yet to be reimbursed by be reimbursed to the
94,77,069
the Authority. Concessionaire

Rejected by the
Incident Management during Construction Period (Nov-17 to
2 68,99,323 Authority. However
Jun-18)
the Concessionaire has
appraised the
Authority on why the
Incident Management work during construction period change of incident Management
3 1,81,09,853 services are to be
scope (July-18 to Sep-19)
considered under COS
Updating of PMIS/ Updated information copy of PMIS

Form - I (25th December-2019)


NATIONAL HIGHWAYS AUTHORITY OF INDIA
Regional Office, Vijayawada

DETAILS OF PROJECTS IN THE STATE OF ANDHRA PRADESH

Progress for the


Status as on 25/11/2019 month of Dec, 2019
Project Director

(i.e.25/12/2019)
State

Length Project Cost Length Probable date


Sl.No Name of the Road Project
(Km) (Crore Rs.) remaining of completion
Length Length
Exp. Exp.
Completed Completed
(in Cr.) (in Cr.)
(in Km.) (in Km.)

1 2 3 4 5 6 7 8 9 10 11 12

Name of PIU : PIU , Visakhapatnam


Shri P.Siva

6-laning of Ranasthalam-
Sankar
AP

11 Anandapuram section of NH-16 47 1187.1 34.201 807.775 0.863 2.75 11.936 13/05/2020
under NHDP Phase.V
Updating of PMIS/ Updated information copy of PMIS Contd..

MIS Report [Dec-2019]

NATIONAL HIGHWAYS AUTHORITY OF INDIA


Regional Office, Vijayawada

as on 25/12/2019
Cumulative
Date of Cost of (Rs. Crs.) * Expenditure (Rs. Crs.) Physical
Contractor and Progress (%)
6 Lane
Lengt Award to its Nationality
Contract Comple
NH h Funde Civil Target
Stretch Anticipa ted
No. (In Complet d By Contractor Upto for Cumm. Supervision
State ted (km) Total During Achieve
km) Start ion / BOT 03/201 Year Expend and its Target
Complet Project CFY d
Original grant / 9 2018- . Nationality
ion
Annuity 19
Payment
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
M/s.Ashoka
6-laning of
Ranasthalam-
Ranasthalam - NHAI
Hybrid Anandapuram
Anandapuram 16/11/20 13/05/20 13/05/20 & 501.75
16 47 35.06 1187.1 Annuity 0 308.77 810.520 Road Ltd., 87.58% 77.21%
section of NH-16 17 20 20 ARAR 0
Mode MSV -
under NHDP L
Armenge
Phase.V
Indian & USA
Project Photos
Project Photos
Project Photos