Client:
National Highways Authority of India
Independent Engineer:
MSV International Inc. in association with Armenge
Engineering and Management Consultants Pvt Ltd
Concessionaire:
Ashoka Ranastalam Anandapuram Road Limited
Index
✓ Key Plan
✓ Salient Features
✓ Scope of Work
✓ Linear Progress – Highway
✓ Linear Progress – Structures
✓ Project Milestones
✓ Payment Milestones
✓ Critical Issues
✓ PMIS information
✓ Project Photos
Key Plan
Salient Features
S.No. Name Description
Milestone - 1 10% 8% (eight per cent) of the Bid Project Cost Achieved
Milestone - 2 30% 8% (eight per cent) of the Bid Project Cost Achieved
Milestone - 3 50% 8% (eight per cent) of the Bid Project Cost Achieved
Milestone - 4 75% 8% (eight per cent) of the Bid Project Cost Achieved
The detailed proposals along with the Cost implications are submitted to the Authority.
The approval and issuance of COS orders is awaited
The following are the locations for which the land is yet to be made available to the Concessionaire. The
Concessionaire has appraised the Authority to descope the works in the respective Land Parcels form the
Scope of work.
The Superintending Engineer had not accorded the approval for commencement of shifting the 132 Kv Line at
Pydibhimavaram due to the difference in approved rates by NHAI as against estimated rates by APTRANSCO.
The Concessionaire has intimated the Authority regarding the local public of Pusapatirega have
confronted the Concessionaire and have stopped the works of approach construction at Ch.
651+400. They are demanding to construct a box culvert instead of widening of existing pipe
culvert at Ch. 651+250 as per Concession Agreement. The construction of underpass approaches is
on critical path of activities. The Concessionaire has intimated the Authority regarding the issue
with a request to provide necessary administrative support to resume the works at said location.
Pending Issues Contd.
Concessionaire on behalf of the Authority has , paid 3% towards The Payment is yet to
1 spare approved by APEPDCL which is yet to be reimbursed by be reimbursed to the
94,77,069
the Authority. Concessionaire
Rejected by the
Incident Management during Construction Period (Nov-17 to
2 68,99,323 Authority. However
Jun-18)
the Concessionaire has
appraised the
Authority on why the
Incident Management work during construction period change of incident Management
3 1,81,09,853 services are to be
scope (July-18 to Sep-19)
considered under COS
Updating of PMIS/ Updated information copy of PMIS
(i.e.25/12/2019)
State
1 2 3 4 5 6 7 8 9 10 11 12
6-laning of Ranasthalam-
Sankar
AP
11 Anandapuram section of NH-16 47 1187.1 34.201 807.775 0.863 2.75 11.936 13/05/2020
under NHDP Phase.V
Updating of PMIS/ Updated information copy of PMIS Contd..
as on 25/12/2019
Cumulative
Date of Cost of (Rs. Crs.) * Expenditure (Rs. Crs.) Physical
Contractor and Progress (%)
6 Lane
Lengt Award to its Nationality
Contract Comple
NH h Funde Civil Target
Stretch Anticipa ted
No. (In Complet d By Contractor Upto for Cumm. Supervision
State ted (km) Total During Achieve
km) Start ion / BOT 03/201 Year Expend and its Target
Complet Project CFY d
Original grant / 9 2018- . Nationality
ion
Annuity 19
Payment
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
M/s.Ashoka
6-laning of
Ranasthalam-
Ranasthalam - NHAI
Hybrid Anandapuram
Anandapuram 16/11/20 13/05/20 13/05/20 & 501.75
16 47 35.06 1187.1 Annuity 0 308.77 810.520 Road Ltd., 87.58% 77.21%
section of NH-16 17 20 20 ARAR 0
Mode MSV -
under NHDP L
Armenge
Phase.V
Indian & USA
Project Photos
Project Photos
Project Photos