Production and Transportation Cost per unit

Plants/Markets Bglre Chennai Delhi Mumbai Lucknow Kolkata Capacity Fixed Cost
Ahemedabad 910 953 775 740 864 936 350 78000
Baddi 1036 1083 622 853 741 830 400 42000
Hubali 727 788 977 755 1022 976 450 36000
Nagpur 790 785 808 742 773 860 300 38000
Vishakapatnam 838 782 1003 892 978 878 400 34000
Demand 165 135 280 200 125 155
Decision Variables
Plants/Markets Bglre Chennai Delhi Mumbai Lucknow Kolkata Supply
Ahemedabad 0 0 0 200 0 0 200
Baddi 0 0 280 0 120 0 400
Hubali 165 0 0 0 0 0 165
Nagpur 0 0 0 0 5 155 160
Vishakapatnam 0 135 0 0 0 0 135
Demand 165 135 280 200 125 155

Objective Function
Total Variable Cost 773770
Fixed Cost

B19-Objective Function
B16-Demand Constraints-6Nos
H11-Supply Constraints-5Nos

Solver Paramaters
1.Transportation parameters should be greater than Zero
2. SupplyB16toG16 should be equal to Actual Demand B8 to G8
3.Supply H11to H15 should be less than the Capacity H3toH7
Production and Transportation Cost per unit
Plants/MarkeBglre Chennai Delhi Mumbai Lucknow Kolkata Capacity
Ahemedabad 910 953 775 740 864 936 350
Baddi 1036 1083 622 853 741 830 400
Hubali 727 788 977 755 1022 976 450
Nagpur 790 785 808 742 773 860 300
Vishakapatn 838 782 1003 892 978 878 400
Demand 165 135 280 200 125 155
Decision Variables
Plants/MarkeBglre Chennai Delhi Mumbai Lucknow Kolkata Plant Open
Ahemedabad 0 0 0 0 0 0 0
Baddi 0 0 280 0 120 0 1
Hubali 165 0 0 200 0 0 1
Nagpur 0 0 0 0 0 0 0
Vishakapatn 0 135 0 0 5 155 1
Demand 165 135 280 200 125 155 0

Objective Function
Total Variabl 892585
Fixed Cost
78000
42000
36000
38000
34000

Supply Eff.Cap
0 0
400 400
365 450
0 0
295 400
0