A SUB STRUCTURE
B SUPER STRUCTURE
3 Roofing-------------------------------------------------------Birr 145,551.32
6 Finishing-----------------------------------------------------Birr 239,992.20
7 Glazing-------------------------------------------------------Birr 16,047.40
8 Painting------------------------------------------------------Birr 67,569.45
A SUB STRUCTURE
B SUPER STRUCTURE
3 Roofing-------------------------------------------------------Birr 55,732.10
6 Finishing-----------------------------------------------------Birr 136,971.42
7 Glazing-------------------------------------------------------Birr 9,225.00
8 Painting------------------------------------------------------Birr 34,676.85
A SUB STRUCTURE
B SUPPER STRUCTURE
3 Roofing-------------------------------------------------------Birr 34,928.50
6 Finishing-----------------------------------------------------Birr 88,411.15
7 Glazing-------------------------------------------------------Birr 3,214.40
8 Painting------------------------------------------------------Birr 20,894.90
A SUB STRUCTURE
B SUPER STRUCTURE
3 Roofing-------------------------------------------------------Birr 18,398.10
6 Finishing-----------------------------------------------------Birr 46,392.75
7 Glazing-------------------------------------------------------Birr 1,894.20
8 Painting------------------------------------------------------Birr 7,203.30
A.SUB STRUCTURE
1.EARTH WORKS
1.4 Ditto,but exceeding 1500mm and not exceeding 2000mm m3 46.00 90.00
1.7 Cart away and spread excavated material 5km away from the
site. m3 371.00 85.00
2.CONCRETE WORK
3.MASONARY WORK
3.2 Ditto, but 200 mm high exposed roughly dressed stone wall
one side left for plastering above ground level m3 12.29 2,650.00
B.SUPER - STRUCTURE
1. CONCRETE WORK
2. BLOCK WORK
2.2 200mm thick HCB wall bedded in cement - sand mortar mix m3 162.92 400.00
(1:3) both sides left for plastering.
2.3 Ditto, but 150mm thick partition m2 98.63 380.00
3.ROOFING
3.1 Roof cover from CIS fixed to Zigba wood purlins with
necessary fixturesseparately
purlins measured accordingand
to structural
roof coverdrawing apply two
measured
coats of anti-termite solutions to all truss members and purlins
in horizontal
before projection.
covering. Price includesridge cover.
Truss and m2 216.26 380.00
3.3 Supply and install down pipes made of G-28 galvanized flat
metal sheets coated with rust galvanized flat metal sheets
coated with rust resisting paint .price includes fixing of pipes ml 37.80 185.00
Total to summary
EUCALYPTUS TRUSS
5. METAL WORKS
DOORS
Partly glazed and partly covered with ribbed
sheet.
5.4 Type D1, Size = 120 x 210cm No 2.00 5,544.00
5.5 Type D5, Size = 90 x 210cm No 4.00 4,158.00
6. FINISHING
6.10 100mm high 2mm thick plastic tile skirting to wall with ml 108.18 110.00
approved type adhesive.Price include adhesive.
7. GLAZING
8. PAINTING
9. SANITARY INSTALLATION
9.4 Supply and fix low level white glazed vitereous china
wash down water closet,with all accessaries including
white plastic seat cover, white vitereous china flushing
cistern and lid fixing devices flexible pipes adoptors. no 2.00 5,000.00
9.5 Supply and fix water heater complete with all water
proofing mounting and fastening matrial heat insulation
safety and none return valves with all required
accessaries
80 liter capacity no 2.00 6,500.00
9.6 Supply and fix shower tray made of enameled cast iron
plate including chrome plated shower over head
complet with fitings and accessories.
size = 700x700 mm no 2.00 1,950.00
10 ELECTRICAL INSTALLATION
A. Distribution board
A.1 Supply and install main distribution board (MDB)for
wall mounting (recessed) with lockable doorbus
bar system of 3-ph 40 A rating earthing lead and
complete connecting accessories consisting of the.
following
1pcs main ACB of 32A/1 - ph
4pcs ACB of 10A/1 - ph
5 pcs ACB of 16A/1 - ph pc 2.00 6,500.00
B. Light points
B.1 Supply and install flush mounted light points fed
through 3x2.5mm2 copper conductors in thermoplastic
conduits of dia.13.5/16 mm in/under surface including
boxes with junction boxes with covers, insulating and
screw caps and flush mounted switches . No. 36.00 1,200.00
D.2 RZB 331030.00x with A60 60w lamp No. 2.00 2,500.00
D.3 RZB 331092.00x with A60 60w lamp No. 4.00 2,500.00
D.4 RZB 331037.00x with A60 40w lamp No. 18.00 2,500.00
ITEM DESCCRIPTION UNIT QTY U.PRICE
D.5 RZB 58132.002 with A60 40w lamp No. 10.00 2,500.00
D.6 RZB 22143.00x with A60 60w lamp No. 2.00 2,500.00
ITEM DESCCRIPTION UNIT QTY U.PRICE
E. Bell call systems
E.1 Supply and install bell calling points, Use 2x0.8mm2
conductor size, thermoplastic conduits of F11mm
in/under surface including junction boxes with covers
and insulating screw caps as well as push buttons
for flush mounting. No. 10.00 1,200.00
F. Telephone systems
G. Television system
9,875.00
14,220.00
3,960.00
4,140.00
4,050.00
26,565.00
31,535.00
38,805.00
133,150.00
3,081.00
7,789.60
TOTAL
13,825.00
6,965.00
29,960.00
TOTAL
69,496.00
5,929.00
13,321.00
26,642.00
1,186.24
25,315.84
381.44
14,488.64
5,455.68
17,792.96
241,629.40
172,859.50
32,568.50
205,428.00
10,850.00
33,110.00
TOTAL
18,872.70
50,346.45
6,546.88
TOTAL
1,380.80
5,782.40
19,008.00
145,897.23
66,965.50
65,168.00
37,479.40
169,612.90
82,178.80
20,824.00
6,993.00
11,729.00
13,797.30
10,029.22
145,551.32
TOTAL
10,809.90
10,584.00
9,740.40
27,562.95
10,684.80
127,107.50
14,112.00
10,584.00
10,584.00
9,408.00
94,080.00
112,560.00
60,480.00
106,920.00
90,750.00
705,967.55
TOTAL
TOTAL
28,380.00
43,296.00
4,752.00
11,088.00
16,632.00
104,148.00
103,224.05
5,846.40
3,024.00
1,285.55
18,024.92
15,921.60
38,972.80
5,850.00
3,432.00
TOTAL
11,899.80
10,560.00
TOTAL
7,750.08
14,201.00
239,992.20
14,243.40
1,804.00
16,047.40
48,893.65
1,092.00
12,710.75
2,387.45
2,485.60
67,569.45
TOTAL
990.00
260.00
TOTAL
2,080.00
1,280.00
10,000.00
10,000.00
13,000.00
3,900.00
1,700.00
1,700.00
1,700.00
2,000.00
TOTAL
TOTAL
1,196.00
1,850.00
900.00
52,556.00
13,000.00
43,200.00
24,000.00
5,000.00
5,000.00
10,000.00
45,000.00
TOTAL
25,000.00
5,000.00
TOTAL
12,000.00
3,000.00
9,600.00
9,000.00
208,800.00
Buei PTP
Buei - Butajira 132 KV PTP
A.SUB STRUCTURE
1.EARTH WORKS
1.5 Ditto,but exceeding 1500mm and not exceeding 3000mm m3 19.69 320.00
1.6 Ditto,but excavation in ordinary soil. m3 10.00 105.00
1.7 Ditto,but for masonry trenches (depth upto 1.5mt.) m3 24.21 90.00
1.9 Cart away and spread excavated material 5km away from the
site. m3 232.03 85.00
2.CONCRETE WORK
3.MASONARY WORK
3.2 Ditto, but 200mm high exposed roughly dressed stone wall
one side left for plastering above ground level m3 6.39 2,650.00
2. BLOCK WORK
2.2 200mm thick C.H.B.wall bedded in cement - sand mortar mix m3 107.05 400.00
(1:3) both sides left for plastering.
2.3 Ditto, but 150mm thick partition & parapate Wall. m2 62.49 380.00
3.ROOFING
3.1 Roof cover from CIS fixed to Zigba wood purlins with
necessary fixtures according to structural drawing apply two
coats of anti-termite solutions to all truss members and purlins
before covering. Truss and
purlins measured separately and roof cover measured
in horizontal projection. Price includesridge cover.
m2 45.32 380.00
Ditto but to Endulin roofing m2 61.88 380.00
Total to summary
EUCALYPTUS TRUSS
5. METAL WORKS
WINDOWS
DOORS
6. FINISHING
6.11 100mm high 2mm thick plastic tile skirting to wall with
approved type adhesive.Price include adhesive. ml 61.78 110.00
7. GLAZING
8. PAINTING
8.1 To all plastered internal and ext. wall surfaces m2 352.99 65.00
9. SANITARY INSTALLATION
9.4 Supply and fix low level white glazed vitereous china
wash down water closet,with all accessaries including
white plastic seat cover, white vitereous china flushing
cistern and lid fixing devices flexible pipes adoptors.
(Italy made) No 1.00 5,000.00
9.5 Supply and fix water heater complete with all water
proofing mounting and fastening matrial heat insulation
safety and none return valves with all required
accessaries(Itally made)
80 liter capacity No 1.00 6,500.00
9.6 Supply and fix shower tray made of enameled cast iron
plate including chrome plated shower over head
complet with fitings and accessories.
size = 700x700 mm No 1.00 1,950.00
10 ELECTRICAL INSTALLATION
A. Distribution board
A.1 Supply and install main distribution board (MDB)for
wall mounting (recessed) with lockable doorbus
bar system of 3-ph 40 A rating earthing lead and
complete connecting accessories consisting of the.
following
1pcs main ACB of 32A/1 - ph
B. Light points
B.1 Supply and install flush mounted light points fed
through 3x2.5mm2 copper conductors in thermoplastic
conduits of dia.13.5/16 mm in/under surface including
boxes with junction boxes with covers, insulating and
screw caps and flush mounted switches . No. 19.00 1,200.00
D.2 RZB 331030.00x with A60 60w lamp No. 1.00 2,500.00
D.3 RZB 331092.00x with A60 60w lamp No. 2.00 2,500.00
D.4 RZB 331037.00x with A60 40w lamp No. 9.00 2,500.00
D.5 RZB 58132.002 with A60 40w lamp No. 4.00 2,500.00
D.5 RZB 22143.00x with A60 60w lamp No. 2.00 2,500.00
F. Telephone systems
G. Television system
6,243.75
8,991.00
1,645.20
2,800.00
6,300.80
1,050.00
2,178.90
18,056.50
19,722.55
19,884.15
86,872.85
2,012.40
4,430.40
9,030.00
4,550.00
15,015.00
35,689.50
3,911.60
8,843.45
12,951.40
800.00
12,787.84
190.72
3,934.40
5,455.68
17,792.96
137,395.35
84,853.00
16,933.50
101,786.50
7,070.00
33,250.00
3,325.00
13,756.05
27,746.95
3,041.50
4,000.32
3,537.28
8,195.20
103,922.30
98,818.50
42,820.00
23,746.20
17,221.60
23,514.40
5,688.75
1,073.00
3,559.40
4,674.95
55,732.10
5,854.95
6,053.40
1,580.40
13,489.50
61,009.00
7,056.00
5,292.00
5,292.00
4,116.00
4,707.00
54,450.00
45,375.00
220,104.85
14,190.00
Fiq maign single
TOTAL
28,864.00
2,376.00
4,158.00
3,696.00
53,284.00
51,183.55
1,696.50
1,485.00
2,743.65
9,337.32
10,963.20
30,283.20
2,925.00
6,420.00
2,036.16
6,795.80
7,227.00
3,875.04
136,971.42
8,036.00
1,189.00
9,225.00
22,944.35
5,095.35
536.25
6,100.90
34,676.85
495.00
130.00
2,080.00
640.00
5,000.00
5,000.00
6,500.00
1,950.00
850.00
850.00
850.00
1,000.00
517.50
555.00
450.00
26,867.50
6,500.00
22,800.00
15,600.00
2,500.00
2,500.00
5,000.00
22,500.00
10,000.00
5,000.00
6,000.00
1,500.00
4,800.00
Fiq maign single
TOTAL
3,600.00
108,300.00
A.SUB STRUCTURE
1.EARTH WORKS
1.2 Bulk excavation in ordinary soil to a depth of 400mm m3 56.00 90.00 5,040.00
1.3 Excavate for footing trench to an average depth not
exceeding 1500mm below strips ground level. m3 16.90 90.00 1,521.00
1.4 Ditto,but exceeding 1500mm and not exceeding 3000mm m3 17.75 105.00 1,863.75
1.7 Cart away and spread excavated material 5km away from
the site. m3 136.27 85.00 11,582.95
2.CONCRETE WORK
3.MASONARY WORK
B.SUPER - STRUCTURE
1. CONCRETE WORK
2. BLOCK WORK
2.2 200mm thick C.H.B.wall bedded in cement - sand mortar m2 105.97 400.00 42,388.00
mix (1:3) both sides left for plastering.
2.3 Ditto, but 150mm thick partition Wall. m2 28.60 380.00 10,868.00
3.1 Roof cover from CIS fixed to Zigba wood purlins with
necessary fixtures according to structural drawing apply
two coats of anti-termite solutions to all truss members and
purlins before covering. Truss and
purlins measured separately and roof cover measured
in horizontal projection. Price includesridge cover. m2 70.35 380.00 26,733.00
EUCALYPTUS TRUSS
5. METAL WORKS
WINDOWS
DOORS
6. FINISHING
7. GLAZING
8. PAINTING
9. SANITARY INSTALLATION
9.4 Turkish type W.C coupled with pillar top showerhead and
with high level flush cistern complete with all No 2.00 5,000.00 10,000.00
accessories
9.5 Stainless steel sink for double bowl and drain,for cold
and hot water and mixer complete with all accessories
size,1200x600mm No 2.00 5,000.00 10,000.00
9.12 Precast concrete laundry basin complete with taps and No 2.00 7,500.00 15,000.00
drains
Siemens 5LG 3092 - 2c with 2xTLD 36W lamp pcs 2.00 2,500.00 5,000.00
Siemens 5LG 2252 - 2c with 2xTLD 36W lamp pcs 2.00 2,500.00 5,000.00
RZB 31663.002 with A60 60w lamp pcs 2.00 2,500.00 5,000.00
A.SUB STRUCTURE
1.EARTH WORKS
1.4 Ditto,but exceeding 1500mm and not exceeding 3000mm m3 10.65 105.00
1.6 Fill around footings & footing columns to a required level with
non expansive selected material from site and well compacted in
layer of 200mm thick. m3 17.73 385.00
1.7 Cart away and spread excavated material 5km away from the
site. m3 71.92 85.00
1.8 250 mm thick basaltic or equivalent stone hard core well rolled
and consolidated and blinded with crushed stone. m2 18.49 195.00
2.CONCRETE WORK
content of 360 kgs/m3 filled nto form work and vibrated around
Provide cut and fix in position swan zigba wood formwork for:
3.MASONARY WORK
3.2 Ditto, but200 mm high exposed roughly dressed stone wall one
side left for plastering above ground level m3 2.14 2,650.00
B.SUPER - STRUCTURE
1. CONCRETE WORK
ITEM DESCCRIPTION UNIT QTY U.PRICE
Reinforced concrete in class C-25, with minimum cement
content of 360 kgs/m3 filled into form work and vibrated around
2. BLOCK WORK
2.1 200mm thick C.H.B.wall bedded in cement - sand mortar mix
(1:3) both sides left for plastering. m3 56.73 400.00
3.2 Supply and install down pipes made of G-28 galvanized flat
metal sheets coated with rust galvanized flat metal sheets coated
with rust resisting paint .price includes fixing of pipes ml 5.40 185.00
3.3 Supply and fix gutter made of G - 28 galvanized flat metal sheet
coated with rust resisting paint development length mm with
0.5% slope towards down pipe ml 8.85 185.00
3.4 Supply and fix coping made of G - 28 galvanized flat metal sheet
coated with rust resisting paint ml 8.85 185.00
ITEM DESCCRIPTION UNIT QTY U.PRICE
Total to summary
EUCALYPTUS TRUSS
5. METAL WORKS
WINDOWS
6. FINISHING
7. GLAZING
Supply and fix clear glass glazed to windows
ITEM DESCCRIPTION UNIT QTY U.PRICE
and doors.
7.1 4mm thick clear glass m2 4.62 410.00
8. PAINTING
9. SANITARY INSTALLATION
9.5 Stainless steel sink for double bowl and drain,for cold
and hot water and mixer complete with all accessories
size,1200x600mm No 1.00 5,000.00
Siemens 5LG 3092 - 2c with 2xTLD 36W lamp pcs 1.00 2,500.00
Siemens 5LG 2252 - 2c with 2xTLD 36W lamp pcs 1.00 2,500.00
1,750.00
2,520.00
912.60
1,118.25
821.70
6,826.05
6,113.20
3,605.55
23,667.35
631.80
1,392.30
TOTAL
2,695.00
1,505.00
3,290.00
6,688.50
1,524.60
3,742.20
3,619.00
315.52
2,540.16
2,741.76
620.48
2,920.96
34,227.28
28,381.50
5,671.00
34,052.50
TOTAL
2,310.00
4,130.00
TOTAL
5,717.25
20,497.40
800.00
4,640.00
640.00
3,040.00
320.00
1,920.00
44,014.65
22,692.00
5,434.00
28,126.00
14,124.60
999.00
1,637.25
1,637.25
TOTAL
18,398.10
1,288.35
1,102.50
1,016.40
4,513.50
4,620.00
12,252.50
24,793.25
2,904.00
TOTAL
6,116.00
3,927.00
TOTAL
3,696.00
2,660.00
19,303.00
10,097.80
1,226.70
9,664.25
9,048.00
5,499.00
1,248.00
1,590.00
8,019.00
46,392.75
TOTAL
1,894.20
1,894.20
TOTAL
4,526.60
549.90
947.70
1,179.10
7,203.30
495.00
195.00
2,080.00
320.00
TOTAL
5,000.00
TOTAL
5,000.00
5,000.00
850.00
850.00
850.00
1,000.00
2,070.00
555.00
900.00
7,500.00
32,665.00
TOTAL
6,500.00
3,600.00
3,600.00
1,200.00
2,500.00
2,500.00
2,500.00
22,400.00
Buei PTP
Buei - Butajira 132 KV PTP
Septic Tank
f 50mm & 2m long PVC vent pipe with cap pcs 2.00 180.00
Total to summary……………….Birr
1,548.25
6,864.90
1,330.56
12,326.16
3,080.00
7,803.00
12,168.00
1,058.46
304.00
1,362.90
5,659.50
173.25
83.52
16,180.80
36.48
2,850.00
2,175.00
3,700.00
300.00
300.00
360.00
107,067.78
Site work
Sanitary site work
Water supply alternative 1
1.1 Construct the water supply system from the available
manucipality or city water line connection point and
supply water to the substation control building and
dwelling houses.The contractor has to visit the site
and quote his price accordingly.
lump
lot sum *
Water supply alternative 2
1.2 In case there is no available manucipality or city water
supply , then the contractor should construct and
supply potable water from ground water by making
water well. The depth of the water well will be
decided as the availablity of ground water. The
contractor shall supply submersable pump and fittngs
with all accessaries with the necessary spare parts and
supply substation dwelling houses and control
building.The contractor has to investigate the
availablity of ground water and quote his price.
lump
lot sum *
1.1 Supply & lay galvanized steel water pipe line as where
shown on the drawing from the existing water
line complete with the necessary fittings and accesso-
ries. unit price shall include excavation
of trenches to a depth of 500 mm for
laying the pipes, spreading of granular
material around the pipe and back filling.