Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Winch for
Kibble rope kibble
Winch for kibble Winch for scaffold
Winch for scaffold
Crawler
Crawler cranecrane Kibble rope
Kibble
Kibble Five-shaft
Five-shaft jumbo jumbo
Concrete bucket
Concrete bucket
Rock
Lockboltbolt Rein forced
Reinforced concrete concrete
(Entrance part)
( Entrance part )
Mini back
Mini back hoe hoe
Wire mesh
Concrete
Concrete kibble kibble
Scaffold
Scaffold
Scaffold
Scaffold
Wire
Wire mesh
mesh Wire mesh
Wire mesh
Shaft loader Wire mesh
Wire mesh
Shaft loader
Five-shaft Concrete spray-machine
Shaft
Shaft loader
loader
jumbojumbo
Five-shaft
Wire mesh Shaft loader
Shaft loader
Shotcrete
Shotcrete
Kibble
Kibble
The main and connecting tunnels are the key routes for material transfer and emergency escape in
the underground facilities. Typical excavation methods for such horizontal tunnels, are the
blasting, free-face mechanical excavation, full-face mechanical excavation and tunnel boring
machine (TBM) methods. Selection of an applicable method must consider variables such as
compatibility with geology and rock type, use and specification of the tunnel, work period,
economy and impact on the rock. Table 5.1-4 shows a comparison of these methods (Japan
Society of Civil Engineers, 1996). Table 5.1-5 shows the methods selected for main and
connecting tunnels for hard rock and soft rock systems, and the reasons for their selection (Japan
Society of Civil Engineers, 1996).
Table 5.1-4 Comparison of typical excavation methods for tunnels
(one method missing – 4 listed above)
Free-face
Item Blasting method mechanical Tunnel boring machine (TBM)
excavation method
Compatible with most The construction Excellent performance for uniform
geological ability rapidly falls geology and rock.
environments and types when unconfined The performance significantly
Compatibility with
of rock. compressive degrades in rock with large variations
geology
strength exceeds in mechanical properties.
30 to 50MPa.
.
Tunnel specification Applicable to most Same as for Present technology is limited to a
(Cross sectional shape) cross-sectional shapes. blasting. circular cross section.
Economic optimization Excavation speed Initial cost is high. However,
of work is possible: decreases in hard excavation speed is high. Therefore,
Work period, economy e.g., excavation length rock. with increasing amount of
can be varied to respond tunneling, there is an improvement
to rock condition. in cost-effectiveness.
Blasting has the highest Because the Same as for free-face excavation.
impact on rock of the method involves Influence on rock is small.
three methods. mechanical
However, the shock can excavation, impact
Influence on rock be suppressed to some on rock is small.
extent by applying a
smooth blasting
method.
Large influence on rock.
Table 5.1-5 Selection of work methods for main and connecting tunnels
Item Method Reason for selection
Blasting method + Excavation performance is highest of candidate
(Smooth blasting methods, and is economical.
Hard rock system
method) + High flexibility with respect to cross sectional
Excavation shape and length of excavation.
method Free-face + Partial excavation is available. Flexibility in
mechanical excavation responding to variations in geological condition
Soft rock system
method is high.
+ High safety level.
+ Free from dust and flue gas emissions in the
Method for tunnel under operating conditions.
Rail type
mucking + Suitable for transporting large amounts of
muck for a long distance.
Shotcrete + Prevents degradation of rock. Ensures safety
Hard rock system
Tunnel during excavation.
support Steel tunnel supports, + Initial creep of rock conforms to the concept of
Soft rock system
shotcrete NATM.
Invert Concreting + General method
5.1.2.2 Outline of construction methods
Based on the construction methods reviewed in the preceding section, this section describes
examples of methods for the main and connecting tunnels in both hard rock and soft rock systems.
For tunnel support, a shotcrete lining is necessary based on excavation stability analysis, plus
rock bolts to prevent collapse of the damaged zone (EDZ). The length of a rock bolt is
commonly 3 m based on analysis of both hard rock and soft rock systems, which gave similar
depths for the EDZ. The spacing of the rock bolts should be smaller in the soft rock system than
in the hard rock, based on analyses of the extent of the EDZ and field experience. The thickness
of shotcrete for hard rock is a minimum of 50 mm for preventing rockfall, and the thickness of
invert concrete is 150 mm. Figure 5.1-3 illustrates the standard cross-sections (Tanai et al.,
1999a). At the intersections of tunnels, reinforcing rock bolts each with a length of 4 m are
driven into the rock, based on the in-situ experience.
(Units : mm)
3) Installation of
ofthe wire
wire mesh
mesh
Scaffold
4) Rock bolt
Lockbolt
The TBM method is judged to be the safest most efficient and economic method for disposal
tunnel excavation for horizontal emplacement because the standard cross-section is circular. In
addition, this method can be applied to both hard rock and soft rock systems and the extent of the
EDZ can be minimized. The mucking may be carried out either by rail or with a fluid
transportation method. Rail is adopted because the debris does not need not to be crushed and
no large-scale subsurface facilities are required.