Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Rev No: 00
PROCEDURE Date Rev: 17 Dec 2008
Page No: 1 of 11
REVISION HISTORY
Reviewed
Approved
Controlled document: No part of this document may be printed or reproduced for external purposes
without the written permission of the management appointee of Science-Tech Solutions Sdn Bhd.
2.0 SCOPE
The hydrostatic and pneumatic testing works cover the repair works (hot work) on
pressure vessel, heat exchanger, piping and newly fabricated piping,
ifapplicable. All
hydro testing works are required to be supervised and witnessed by Client. In the event
of repair to be carried out on DOSH registered equipment, DOSH officer is required to
witness the testing under FMA Act 1967.
4.0 PROCEDURE
6.1.1 All hydrostatic and pneumatic testing for specific work shall be
accompanied by the latest revision of relevant P&ID's/ Isometric/
General Arrangement drawing.
6.1.2 A minimum of (2) calibrated and valid pressure gauge shall be used
during testing. Pressure gauge range shall be 1.5 to 4 times from
testing range. One (1) pressure gauge shall be located at the high point
and one (1) pressure gauge for injection at the low point. In addition to
pressure gauge, chart recorder to be used if required by Client and/or
DOSH.
6.1.3 Readings at the high point shall govern the test result. Pressure gauge
and chart recorder shall be calibrated for every 1 year ‘OR’ earlier
whenever the accuracy is questionable.
Note: Valid calibration certificate shall be provided
6.1.4 Pipe spool prior for installation for testing shall be free from dust and
debris and ensure all spring hangers are locked and all supports are
installed and instrument devices excluded during testing.
6.1.5 Establish the maximum test pressure for the equipment taking into
account the static head of the test media as per following:
6.1.7 Slowly raise the pressure to 2.0 kg/cm 2 and holding time with minimum
of 5 minute. Visually inspect system for leaks.
6.1.8 Increase from pressure of 2.0 kg/cm 2 to 50% operating pressure. Hold
for a minimum of 5 minute to allow strains to equalize.
6.1.9 Continue to increase until the system pressure is at operating pressure.
Hold for a minimum of 5 minute.
6.1.10 Gradually increase pressure to test pressure for a minimum of holding
is 30 minute. Observe pressure gage for loss of system pressure.
6.1.11 Reduce pressure to 2/3 test pressure and check for leaks. Hold for a
minimum of 5 minute.
6.1.12 Perform visual inspection at every single joint.
6.1.13 If no leaks is detected, release pressure gradually at constant rate.
6.1.14 Alternative test shall be performed if both of the following apply:
a. Hydrostatic testing would damage internal lining or insulation,
contaminate a process, or present a hazard of brittle fracture
because of the temperature during the test.
b. A pneumatic test would present an undue hazard of
possible of release of energy stored in the system, or would
present the danger of brittle fracture because of the
temperature during the test.
6.2.1 Pneumatic test may be performed if a hydro static test is not practical.
The line size should be limited to maximum of 3” diameter, or special
procedures followed to cope with the potential release of energy stored
in compressed gas. This is the least desirable of the test methods.
6.2.2 Air is to be used as a testing medium unless specified otherwise.
6.2.3 The test pressure shall be 110% of the operating pressure.
6.2.4 Slowly raise the pressure to 1.8 kg/cm 2 (25psi) or one-half the test
pressure (25%) whichever is lower. Hold for 10 min and visually inspect
system for leaks.
6.2.5 Increase from pressure in item specified in paragraph 6.2.4 by
3.57kg/cm2 (50psi) or to 35% test pressure, whichever is greater. Hold
for a minimum of 3 min to allow strains to equalize.
6.2.6 Continue to increase by 3.57kg/cm2 (50psi) increments until the system
pressure is at 50% test pressure. Hold at 50% test pressure for a
minimum of 10 min. Observe pressure gauge for loss of system
pressure.
6.2.7 Gradually increase system pressure in increments of 10% of test
pressure. At each increment observe pressure gauge for 5 min.
6.2.8 Once full test pressure is reached, observe pressure gauge for a
minimum of 10 min.
6.2.9 Reduce pressure to 4/5 test pressure and check for leaks. Hold for a
minimum of 5 minute.
6.2.10 Perform visual inspection at every single joint.
6.2.11 If no leaks is detected, release pressure gradually at constant rate.
6.2.12 Examine all joints for leakage. The “soap bubble” test is an effective
way to locate leakage when testing.
6.3 Alternative Test Pressure / In lieu of Hydro-static and Pneumatic
Testing
6.3.1 All welds, including those made in the manufacture of the pipe and
fitting, which have not been hydro statically and pneumatically tested,
shall be tested as follows:
6.3.1.1 Circumferential, longitudinal and spiral groove welds shall
undergo 100 % radiography testing and if RT is not possible then
UT shear wave shall be applied.
6.4.2 Install a vent line with a vent valve at the highest point of the piping
system.
6.4.3 Install the gauges for testing as close as possible to the lowest point
and highest point either for piping, pressure vessel or heat exchanger.
Test gauge range shall be (1.5 to 4.0 time) higher than test pressure
and shall exhibit valid calibration certificate.
6.4.4 Allow water to flow from vent line for a few minutes until all the air
trapped has escaped before closing the vent valve.
6.4.5 When the system has no indication for a leak or a problem, proceed to
start hydro test pump to reach the required test pressure and follow
the step as per table below, please refer attachment 4.0 for pressure
test certificate.
6.4.6 Examine and check each joint for leaks during holding time for each
step. Commence inspection of the system in the presence of the
Client's Inspector.
6.4.7 Probable weak points that could be found leaking during testing:
a. Flange Connections
b. Welded Joint
c. Valve Glands
6.4.8 When the required test pressure has been attained satisfactorily in the
presence of the CLIENT'S Inspector, hold the pressure for at least 30
minutes as per above table. During holding time, disconnected the
hose/piping to pump. Marking on the pressure gauge and as long as it
takes to check the full test circuit and then check the pressure drop.
6.4.9 With the approval of the Client Inspector, the test pressure shall be
released gradually to 2/3 Test Pressure and check the full circuit for any
leak and pressure drop then drops to zero gradually. After testing the
circuit will be flushed in line with pre commissioning requirements.
6.4.10 The test water used for testing the piping system/vessel shall be
removed as soon as possible and be dried immediately by blowing
after draining. All vent points will be in open position during draining to
prevent any vacuum forming. The system will be air blown with
compressed air and all drain points will be checked until no moisture is
presence. Client witness is recommended.
6.4.11 All testing temporary spading shall be color coded with red paint to
identify them as temporary fixtures. After testing the temporary gasket
and stud bolts will be replaced with the original items and torque to the
required tensioned.
6.4.12 Flanges or valves that are permanent fixtures the original gasket and
stud bolts shall be installed during testing.
6.4.13 Prior to testing, Supervisor shall ensure that all work has been
completed and verified. All pre-test QC activities and NDT have been
carried out and shall submit all required documents to consultant in
pack form including but not limited to:
a. The side with the lower test pressure shall be indicated with
sticker “side L” on the pressure gauge while the side with the
higher test pressure shall be indicated with sticker “side H” on the
pressure gauge. Two manometers shall be fitted on both sides.
b. Two sides shall be pressurized at the same time, using only one
pump. To connect the pump simultaneously at the two chambers,
a three-way cock shall be used.
c. During pumping the connection between the “side L” and the “side
H” shall be maintained. When the test pressure of “side L” is
reached the correspondent valve shall be closed.
5.0 RECORDS
8.0 ATTACHMENTS
Vent Point
Pressure Gauge
Test Equipment
Pressure Gauge
Injection Point
Hydrotest
Pump
Draining
Point
Appendix 2.0