Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.General
The Contractor shall perform a number of approved pullout tests on the rockbolts prior to and during
tunnel excavation. For this purpose the Contractor shall furnish at least two sets of testing equipment
including but not limited to hydraulic jacks, fixing device, hydraulic pump with manometer,
extensometer, and all necessary accessories. The testing equipment shall be capable of stressing the
largest diameter rockbolt to the yield stress of the bolt. The ram stroke shall be sufficient to
accommodate a bolt movement of at least 75 mm during tensioning of grouted bolts and 200mm for
Swellex bolts.
2. Pre-production testing
(i) For resin grouted rockbolts and Swellex bolts, a series of tests shall be undertaken prior to their use
in the tunnel. Not less than ten (10) rockbolts of each type of rockbolt shall be tested to assess the
installation performance and capacity of the specified rock bolts. Pre-production testing shall be
undertaken in three successive stages as follows:
(iii)Any test results considered unsatisfactory by the Engineer shall be repeated, as instructed.
Installation procedures may need to be amended as required in the light of the trial results so as to
achieve the requirements of the Specification.
(iv) Anchoring of the rockbolts shall be monitored by pull-out testing on 2% of all rockbolts installed
or as otherwise approved by the Engineer, applying a test load of 80% of the yield force of the steel bar.
An alternative method of testing may be proposed. The testing method and program must be submitted
and approved by the Engineer prior to any such testing.
3 Production testing
(i) Production testing of rockbolts shall be undertaken by pull-out testing on a minimum of2% of all
rockbolts installed or as otherwise approved by the Engineer, applying a test load of 80% of the yield
strength of the rockbolt. These tests shall be undertaken on rockbolts installed at a variety of orientations
and locations along the tunnel alignment, and in a variety of geological conditions.
(ii) Should any rockbolt fail at a load less than 80% of the yield strength, the test shall be repeated on
adjacent rockbolts until a test is completed successfully and the Engineer is satisfied that the failed
rockbolt is not symptomatic of a wider problem. The Contractor and the Engineer shall attempt to
establish the reason for any failed rockbolts and if necessary, the method of rockbolt installation shall
be modified accordingly. The Engineer may instruct that any failed rockbolts are replaced at the
Contractor's own cost.