Sei sulla pagina 1di 7

KWIKDEK SLAB FORMWORK

KWIKDEK Introduction

KwikDek Slab Shoring & Decking

                    The KwikDek Slab Formwork Decking System replaces the secondary and primary beam in soffit support and provides
a flat support grid for decking out with plywood or other conventional materials, labour costs are greatly reduced in conjunction 
with the speed of construction to provide an economical solution to decking problems.         
Kwikstage requires fewer different pieces than most other similar system and can be stored in less space.

                    This unique system allows the slab formwork to be stripped only (3) three days after concrete has been poured. 
The Drophead allows the support work to remain in place thereby avoiding re‐propping      

Features of the kwikDek system:

• Maximum utilisation of equipment 

• Eliminates any deflection of slab 

• No re‐propping required

• versatile with unlimited adjustments

                   KwikDek Shoring and Decking is a highly versatile, 
very competitive slab formwork system capable of being 
used in many applications:
• Braces fit to the standards using half couplers ensuring no
   loose parts, minimising loss and damage charges 
• Simple erection procedure ensures stringent safety levels
  can be easily achieved
• Make‐up areas around columns can be supported simply by 
  using infill beams, saving customer time and money 
• Quick striking system, enabling early removal of deck beams
  and plywood, saving time and cost 
• Variable ledger positions to suit leg loading, increasing 
   flexibility of the system 
• Quick and easy to erect ledgers and transoms are fixed to
   the vertical standards using captive wedge connections, 
   eliminating the need for transverse bracing 
KWIKDEK Components

Standards Ledgers

Made from standard Scaffold tube. They have V‐pressing   They are welded with C‐press and wedge, used for easy 
welded at 495mm 4‐way connections for ledgers. installation on the standards.
Available Length: 3.0m, 2.5m, 2.0m, 1.5m & 1.0m Available Length: 2.4m, 1.8m, 1.2m, 0.9m & 0.6m

Adjustable Base Jack
Drophead
It used to level the standard 
Support the decking beams which on uneven grounds.
are seated on the projected
support plate.

Adjustable Spigot Jack

Spigot Connector It connects open‐ended standard with
drophead and it is used for adjusting
Used to connect two standard. drophead heights.
KWIKDEK Components

Decking Beams

Designed to support a variety of bay sizes
with a maximum load on any supporting
leg of 40kN.
Available Length : 2.4m, 1.8m & 1.2m

Cantilever Frame
Infill Beams
The cantilever bracket is used to extend the slab formwork in areas 
Designed as secondary beams to support plywood where there is no support from below. It can be used to support a 
at permissible spans. beam or channel. 
Safe Working Load: 40kN UDL Typical applications are for slab extensions and access work. 
Available Length: 1.8m, 1.2m & 0.9m Available Length: 1.5m & 1.0m

Cantilever Beam Bracket

Available Length: 1.5m & 1.0m

Base Plate

It is used when the standard 
are on even grounds.
Internal Beam Bracket

Available Length: 1.5m & 1.0m
KWIKDEK Assembly

Step 1 Step 4
Erection sequence for 4 standards and 2 ledgers. Add the fourth standard and 2 more ledgers in a similar 
manner to complete the assembly of 4 standard and 4 ledgers.

Space out socket bases and stand in jacks if required

Step 2
Assemble a standard on a jack and 2 ledgers at right
angles in a lower "V" pressing of the standard. Step 5
Add the upper layer of 4 ledgers and 2 braces. Assemble the 
upper jack and dropheads on the completed support grid.

Step 3
Take a second standard and assemble on another jack,
fixing the ledger end of the previously assembled ledger Step 6
into the "V" pressing of the standard. Repeat for the  Finally add the primary beams and infill beams in the completed 
third standard to complete a right angled corner. support structure and as grids are completed, tighten all joints.
KWIKDEK Assembly

Stage 1 Dismantling Procedure
Complete slab and support system erected.                     Stripping follows the same procedure the 
techniques of early dismantling are followed or not.
The advantages of early stripping is that the primary
beams and infills may be removed while concrete 
soffit remains supported and completely undisturbed
during its curing period.
Stage 2 The primary beams and infills may therefore be re‐used
Reinforcing steel placed and concrete poured. One day after concreting thus gaining further concrete production with only an
the second set of support can be erected on the upper level.  additional set of supprting components.
Primary beams and infills may be removed by striking
the drophead wedge. While the primary head remains 
in contact with the concrete, the striking of the wedge
allows the beams to drop about 115mm giving 
sufficient clearance for the removal of the infills.
Stage 3
After three days plywood, infill beams and decking beams are stripped 
without removing the support. A double set of support is supplied.

   Up      Down

Stage 4 Whether the advantages of early striking are taken 
After stripping level 1 all decking, ledgers and braces can immediately  or not, complete safety in dismantling operation is 
be placed on the second set of support previously erected on level 2. ensured as primary beams and infills cannot fall to the 
ground after striking, but must be removed manually.
To assemble KwikDek Shoring and Decking remove
the drophead assembly from the jack at one end and
connect  it to the beam.
The completed with its drophead can now be raised
and dropped over the jack.
KWIKDEK Technical Data

Permissible Loads on Base Components Early Stripping

Vertical Axial Load to 57kN                    Early stripping is a technique where by the 
The Loading will vary according to the horizontal loads  is removed 3‐4days after casting the slab but with the
taken into account and the actual extension of the  supporting structure of shoring remaining undisturbed
jack required. for the full curing period.
After striking the primary beams, the infill beams and 
the plywood can be easily removed and re‐used on the
next area of scaffold.
The drophead remains at all times in contact with the
underside of the slab ensuring proper support at all 
Standard "V" pressing times.

Maximum safe shear load on each "V" pressing is 10kN.  Before Striking
Drophead supporting beams in raised position.

Drophead Technical Details

Safe load carrying capacity of 40kN

KwikDek Shoring‐GUIDE

At least two lacing levels have to be used on each
standards. When calculating two horizontal forces,
include for wind forces, the effect of eccentricity,  After Striking
and out of verticality in accordance with British Drophead in struck position.
Standard 5975. 
Take care that the structure is stable in the unloaded
condition, especially if towers or narrow structures 
are used. All standard should be erected plumb.
Horizontal forces should be distributed over all
standards as evenly as possible.
Footings should be provided to prevent settlement
of the standards.

Potrebbero piacerti anche