RFQ DATA SHEET

A. Introduction
Project LOTTE CHEMICAL INDONESIA NEW ETHYLENE COMPLEX
Subject A. Jetty (Bottom Side only) and B. Seawater Intake/Outfall Construction
Site Location Cilegon City, Indonesia
Client PT. Lotte Chemical Indonesia (PT. LCI)
Contractor Hyundai Engineering Co., Ltd.("HEC")

Construction Period 39 months after commencement date (Tentative Commencement Date : Early 2020)

Jetty (Bottom Side only) and Seawater Intake/Outfall Construction


1) Jetty (Bottom Side only) 2) Seawater Intake/Outfall
Project Salient Features - Trestle Structure : 1,768m - Intake (140,000m3/hr) : 2.25OD HDPE
(Scope of Work) - Berth #2 (120,000DWT) 772mx3EA
- Berth #4 (10,000DWT) - Outfall : 2.25OD HDPE 1,262mx3EA
- Berth #5 (10,000DWT)
B. Preparation of Quotes
1) Instruction to Bidder
2) Subcontract Agreement
Contents of RFQ Documents 3) General Terms and Conditions
4) Particular Terms and Conditions
5) Annexes of Subcontract
1) ANNEX 4.2 Subcontract Work Time Schedule
2) ANNEX 5.1 Manpower Mobilization Schedule
3) ANNEX 5.2 Construction Equipment Schedule
4) ANNEX 5.3 Utility Consumption Schedule
Contents of Subcontractor 5) ANNEX 5.4 Space Requirement
Proposals 6) ANNEX 8.1 Bill of Quantities and Unit Rates
7) ANNEX 8.2 Manpower Unit Rate
8) ANNEX 8.3 Construction Equipment Unit Rate
9) Subcontractor Information
The Subcontractor shall submit with its proposals the above documents.
Currency of Quote Indonesian Rupiah (IDR)
Quote Validity Period 180 days

Language for Communications English

C. Submission of Quotes
For clarification and submission purposes, the Contractor's address is:
1) Sunwook, Kwon / Senior Engineer 2) Seongtae, Kim / Lead Engineer
Tel. : +82-2-2134-3141 Tel. : +82-2-2134-3134
E-mail : ksjksw63@hec.co.kr E-mail : kst@hec.co.kr
3) Huiwoong, Bae / Senior Engineer
Tel. : +82-2-2134-3147
E-mail : baepitt1@hec.co.kr
The Deadline for Submission
2019-08-23
of Quote is:
D. Contract Data
Payment Currency Indonesian Rupiah (IDR)
Time for Completion 39 months after commencement date (Tentative Commencement Date : Early 2020)
Defects Notification Period 365 days
Advance Payment 5% of the final Contract Amount.
Amortization for Repayment of 10% of the value of each monthly progress invoice.
Advance Payment (until the total Advance Payment amount is completely reimbursed)
Advance Payment Bond By an international bank with a Standard and Poor rating of A or higher
Made within 45 days from the date of receipt approved of the invoice by the
Monthly Progress Payments
Contractor
Delay Damages for the Works 0.2% of the final Contract Amount per day
Maximum Amount of Delay
10% of the final Contract Price
Damages
1) Insurance for Subcontractor’s Equipment
Required Insurances for 2) Insurance for Subcontractor’s Personnel
Subcontractor's Works 3) Insurance for Marine Cargo
4) All Other Insurance Required by Applicable Law
Governing Law and Settlement 1) Governing Law : the Law of England
Disputes 2) The venue of arbitration : LCIA(The London Court of International Arbitration)