Sei sulla pagina 1di 15

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/311985277

Ground Control Management Plan - Rampura Agucha Underground Mine

Conference Paper · October 2015

CITATIONS READS
0 828

2 authors, including:

Pranay Yadav
Laurentian University
4 PUBLICATIONS   2 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Time dependent anisotropic deformations in foliated rock mass View project

All content following this page was uploaded by Pranay Yadav on 04 October 2018.

The user has requested enhancement of the downloaded file.


2nd National Conference on Mining Equipment: New Technologies, Challenges & Applications
9-10 October, 2015. ISM, Dhanbad India

Ground Control Management Plan Rampura Agucha Underground Mine


P. Yadav, M. Sonam, A. Panda, B. Banerjee, D.C. Paneri, A. Vyazmensky
Geotechnical Department, Rampura Agucha Underground Mine, Rajasthan India

ABSTRACT:

To maintain safe working conditions at a mine site, all risks associated with mining operations need to be
managed. From 1995-2005 about 60% of fatalities in Indian coal mines occurred due to fall of ground
(Chakraborty, 2009). Managing the risks of fall of ground hazards requires a clear and well understood
plan that is implemented, followed and monitored rigorously. This is easier in principle than it is in
practice.

A Ground Control Management Plan (GCMP) framework provides a systematic and methodical approach
to managing ground fall hazards. It is a dynamic document that has regular auditing and updates due to
changing ground conditions and regular introductions of improved mining technologies.

This paper outlines the basic principles of ground control management and presents an example of a
GCMP used at Rampura Agucha Underground Mine (RAM UG).

1 Introduction industries up to around 1990, when ground


To maintain safe working conditions at a control management plans (i.e. methodical
mine site, all risks associated with mining and systematic approaches in dealing with
operations need to be managed. A mine site ground control hazards) were introduced
can have several risk management plans, that reduced injuries and fatalities associated
such as Mine Management Plan, Tailings with fall of ground and significantly
Management Plan, Mine Infrastructure improve overall safety. All mines in
Management Plan, Seismic Risk Australia and Canada have an auditable
Management Plan, Backfill Management Ground Control Management Plan as a
Plan, Cave Management Plan and Ground requirement for complying with their
Control Management Plan. The latter is obligation to manage fall of ground hazards.
subject of this paper. A “zero harm” policy is being implemented
across major international mining
In an underground mining environment companies.
ground instability is one of the primary
hazards to personnel safety. Table 1 Recently, Vedanta Group introduced new
summarizes accident statistics in Indian coal sustainability standards, which requires each
mines between 1995 and 2005. About 60% Vedanta operation to develop and
of all fatal accidents are associated with fall implement a Ground Control Management
of ground (Chakraborty, 2009). Similar Plan (GCMP). This paper outlines the basic
trends were prevalent in western mining principles of ground control management

Page | 1
and presents an example of a GCMP used at 2 Ground Control Management
Rampura Agucha Underground mine Plan (GCMP)
(RAM UG). The purpose of a GCMP is to:
> Provide a systematic approach to
planning, design, management and
Table 1.0 – Statistics of fatal accidents in revision of all aspects of works
coal mines 1995-2005 (Chakraborty, 2009).
associated with ground control
Fatality Cause # > Describe, formalize and consolidate the
Fall of roof 306 systems used to manage geotechnical
Fall of side 97
hazards at a mine
Other ground movements 4
Transportation machinery 16 > Outline the processes required to ensure
Rope Haulage 116 that adequate geotechnical
Wheeled trackless transport 0 considerations are given to planning,
Other transportation machinery 18 production and rehabilitation of mine
Machinery other than transportation 17
workings
Explosives 30
Electricity 7 > Establish processes required to ensure
Gas, dust and other combustible that the risk of injury to personnel from
9
materials geotechnical hazards is minimized
Fall of person 37
Fall of object 10 Key components of GCMP are summarized
Other falls 1 in Figure 1.0 flowchart and the following
Irruption of water 11 sub-sections thereafter.
Flying pieces 1
Miscellaneous 6
Total 686

Page | 2
ANALYSE  Analyse geotechnical data
 Evaluate ground conditions and fall of ground hazards

 Developed by competent persons – Geotechnical Engineer,


Geologist, Mining Engineer
nd rd
 Validated by 2 /3 party
CREATE GROUND CONTROL  Sign off by GM/Mine Manager
 Design philosophy, design standards, ground support
MANAGEMENT PLAN requirements
 selection, specification and implementation of ground
support systems
 Performance testing, QA and maintenance of ground
support and excavation stability.

MINE PLANNING  Factoring of geological info, GCMP, span design, pillar/support


design into mine layout
 Appropriate input from Geologist, Geotechnical Engineer into
mine planning process
 Regular mine planning meetings
 Review and update of mine plan
 Production rates to take account of FoG risks and need for support

 Persons trained and competent to implement the GCMP


IMPLEMENT
 Adherence to GCMP and safe working practices
 Provision and maintenance of equipment/resources
 Communication of changes in mining conditions
 Control of changes to support pattern
 Change management process

MONITOR  Audit implementation of GCMP


 Behaviour based audits
 Tracking and investigation of FoG incidents

 Consider changes in available technology/techniques


REVIEW/ADAPT  Continuous improvement and reduction of FoG risks

Figure 1.0 – Key Components of a Ground Control Management Plan.

Page | 3
1.1.Geotechnical Conditions, Data water, rock mass parameters for Q‟
Collection and Analyses assessment, and a photograph and/or a
sketch of a heading. The structural
This GCMP section incorporates the
orientation data collected is stored in Excel
existing knowledge of geological &
spreadsheets and in DIPS™ format.
geotechnical condition of the rock types
found at Rampura Agucha mine and If the Geologist feels that failure in the
provides procedures for systematic data heading is imminent, or is not sure of the
collection through core logging and conditions in the heading, the Shift
mapping of UG exposures. Supervisor or Geotechnical Engineer is
informed. The heading is then inspected by a
Geotechnical data collected from drill core
Geotechnical Engineer, and an appropriate
is used to characterize the rock mass
course of action recommended.
following ISRM (International Society for
Rock Mechanics) guidelines, and used in the Any significant observations are
rock mass classification based on the Q- photographed and stored electronically. This
system (Barton et al., 1974) (Q ratings are database provides a geotechnical history for
convertible to RMR ratings). Geotechnical the mine and as a reference for ground
data is collected from all diamond drill holes control instructions.
and includes:
Geotechnical domains are defined for which
 RQD (Rock Quality Designation) rock mass conditions are broadly similar in
and core recovery terms of response to mining activities.
 Jn – joint number
Primary data is collected by geotechnical
 Jr – joint roughness number
mapping of UG excavations and drillhole
 Ja – joint alteration number
 Notable shear zones data. The two areas of focus are the footwall
country rock (where UG infrastructure
Diamond drill core is oriented where
exists) and the resource & its immediate
possible, allowing oriented core
surroundings where the mining will take
measurements of discontinuities to be
place. Domains are determined by lithology,
recorded. This logging is carried out by the UCS, geological discontinuities and
Geologists and core yard technicians prior to
geotechnical parameters (modeling &
core splitting. All drill core is photographed
empirical results).
and stored electronically.
Three geotechnical domains have been
Scanline and/or window mapping of
identified based on ISRM strength
development headings is carried out by
classification and rock mass behavior:
Geologists. At the minimum, ore drives are
mapped after every second cut and waste  Medium Strength Strong Foliated Rock
drives are mapped every forth cut. The  Resource (ore zone)
minimum information to be collected is:  High Strength Metamorphic Bands &
lithology, prominent structures, presence of Intrusions

Page | 4
Medium Strength Strong Foliated Rock: The dimensions of the joints vary with rock
rock mass is of a Garnet-Biotite-Silimanite types.
Gneiss & Schist (GBSG & GBSS) and
represents the majority of the footwall & 1.2.Ground Control Methods and
hangingwall rock mass (approximately Minimum Designs
70%). Variations with pegmatite bands and 1.2.1. Ground Control Process
high mica content are present, with typical
gneisses having strong foliations defined by The ground control process details the
layered arrangement of flaky & fibrous responsibility of various personnel regarding
minerals around the garnet. what procedures to follow if ground
conditions & ground support are
Pegmatite and aplite occur as bands of
unsatisfactory and /or if they are unsure of
discontinuous veins, of sizable dimensions
what to do. Figure 2 illustrates ground
mainly parallel to foliation within GBSG &
control process as implemented under the
GBSS.
GCMP.
Resource: Graphite Mica Schist (GMS)
forms the host for mineralization and GROUND CONTROL SHIFT
OPERATOR SUPERVISOR
consists of mica, feldspar, quartz and an

Unsure
- Inspect ground conditions - Inspect ground
appreciable amount of graphite. The (as per workplace conditions
inspection sheet) - Recommend
orebody comprises of weak to moderately - Install appropriate ground ground control
Unsatisfactory

strong, heavily jointed rock mass containing control to operator


- Report work to Shift
zones of extremely friable & weak rock

Unsure
Supervisor
material.
Sure

ASSISTANT MANAGER
The ore zone footwall & ore zone contact SHIFT / SECTION IN CHARGE
with the footwall country rock show SUPERVISOR - Inspect ground
Unsure

- Inspect ground conditions


shearing and mylonitization. The shear zone - Recommend ground
conditions
inside the orebody (OSZ) is continuous - Check the adequacy of control to Shift
throughout the resource. On the upper levels installed ground control Supervisor
Unsatisfactory

- Record on shift log


of the resource the OSZ is closer to the
Unsure

footwall and with depth the OSZ transitions


Sure

through the center to the hangingwall. GEOTECHNICAL ENGINEER


ASSIST. MANAGER / - Inspect ground
SECTION IN CHARGE conditions
High Strength Metamorphic Bands &
Unsure

- Inspect ground - Recommend ground


Intrusions: The country rock GBSG & conditions control to Assistant
- Check the adequacy of
GBSS have intercalated bands of Manager / Section in
installed ground control Charge
Amphibolite, Pegmatite and Psammitic
band. Calc-silicates, Amphibolite, Granite Figure 2.0 – Ground Control Process flow
gneiss (QBG), Quartzite and Pegmatite chart outlined in the RAM UG GCMP
exposed in the deposit area are highly (Vyazmensky, 2014).
jointed, although the nature, intensity and

Page | 5
1.2.2. Scaling 1.2.3. Ground Support Design
Methodology
Scaling (or “barring down”) is necessary to
remove loose rock from the sidewalls and The key philosophy of the ground support
the roof of mine roadways, particularly system adopted at RAM UG is to maintain
when rock and ore is removed by blasting. stable excavations by reinforcing the rock
Those carrying out scaling are particularly at mass and preventing uncontrolled failure of
risk if they do not follow safe scaling the rock mass. This is achieved by installing
practices. rock reinforcement and surface support
elements to the excavation as part of the
Scaling can be carried out either manually normal mining cycle.
using a hand-held pinch bar or
mechanically. Mechanical scaling generally Ground support design is based on the
provides the operator with a higher degree following methodology:
of protection as the person is normally a) Collect geological, structural and
enclosed in a protective cab. However there rock mass characterization data.
are many situations where manual scaling is b) Analyze using three techniques:
the only viable option due to the working empirical analysis (Q system), 2D
environment. wedge analysis and UNWEDGE™
The GCMP requires manual scaling should analysis.
only be used to remove small scats and that c) Ground support design should meet a
the person undertaking the activity is always minimum factor of safety (FOS) of
located under supported ground. Equipment 1.6.
to be used for barring should be appropriate Due to the relatively wide range of ground
and persons involved should be standing at a conditions at RAM UG, there can be
safe distance. Scaling bars must be available variations to ground control requirements.
on most machines and on racks located in The development standards include ground
active headings. support design for good and poor ground
All active areas of the mine are required to conditions. The decision on which to use for
be check scaled at intervals not exceeding a particular design is guided by the relevant
three months and more frequently if Q rating and also engineering experience of
required. All major scaling activities development in that particular geotechnical
(including those issued on scaling plans) are domain.
recorded by the Section in Charge in the Non-standard development will have an
Scaling Logbook. individual geotechnical assessment for
ground conditions, ground support
requirements and monitoring.

RAM UG utilizes the following support


elements:

Page | 6
Primary support: Kinematic analysis: Geotechnical
 25mm diameter x 2400mm long parameters of geological discontinuities are
resin grouted rock bolts – primary collected. These parameters are utilized in
support for UG development; Rocscience UNWEDGE™ software to
 Fiber reinforced shotcrete (50mm) determine potential wedge formations and to
calculate factor of safety. This analysis
Secondary support:
method however does not consider influence
 15.5mm diameter cable bolts –
of stresses on the rock mass.
secondary support used for
intersection and large excavations. Empirical analysis: Factors such as stope
 Welded 5.6mm diameter wire mesh, dimensions/ hydraulic radius, rock mass
with 100mm squares – utilized for properties and geological discontinuity type
support of development parallel or & orientation, etc are used to determine the
oblique to rock mass foliation. potentially stable, unstable or caving zone
 Self-drilling anchors utilized for using the Mathew‟s Stability Graph
support of ore body shear zone. (Mawdesley et al, 2001).

1.2.4. Stoping Design Methodology Numerical analysis: 2D stope models are


created and analyzed in Rocscience Phase2™
The mining method implemented at RAM software. This methodology does not
UG is long hole open stoping with CRF & consider the complexity of geological
paste backfill. Both longitudinal and discontinuities but does provide a better
transverse stope designs are planned understanding of in-situ stresses and their
depending on the geometry of the orebody. influences on the rock mass.
Currently the four analyses methods used in
the Stope Design Methodology are: At times the stope stability analyses indicate
challenging conditions which requires the
 Global Numerical Analysis using ground control measure to recommend
Abacus and Flac 3D. change the ore extraction design. This could
 Kinematic analysis (UNWEDGE™) be recommending changing from
 Empirical analysis (Mathew‟s stability longitudinal to transverse stopes and/or
graph) leaving a sill or crown pillar to increase the
 Local stress analysis (Phase2™ modeling) stability of the open stopes.

Global stress analysis: The life of mine Stopes are monitored with CMS scans, and
plan is analyzed for stress and deformation the surrounding rock mass with stress cells
in relation to the open pit and surrounding & multiple point borehole extensometers
excavations, and in relation to the planned (MPBX). The data collected provide better
mining sequence and mining rate. Location understanding of the actual stope
of major infrastructure and regional pillars is performance and are used to calibrate the
determined by this analysis. current rock mass parameters and stope
models.

Page | 7
1.3. Mine plans – review and sign off referred to on the SN. Where a revised or
process local support design has been produced by
the geotechnical department, this design is
1.3.1. Global Mine Design referred to the SN and is included with the
SN instruction for the mining crews. The
A life of mine plan (LOMP) was produced
support designs comply with the RAM UG
during the feasibility study. Global Stability
Ground Support Standards.
analysis was conducted to determine
infrastructure layout and key parameters 1.3.4. Planning Geotechnical Checklist
such as mining method, equipment
configuration, excavation sizes and To ensure all geotechnical aspects are
extraction sequence. This plan was based on considered adequately in the mine design
geotechnical analysis, which was then and planning process, the following
updated after trial stopes were completed questions are positively answered prior to
and is updated on a yearly basis. the plans being signed off:

1.3.2. Strategic Level Planning  Does geotechnical data exist for the
planned mining area?
A Plan of Intent (POI) is produced to inform  Has the data been used to review the
all relevant personnel of the proposed mine excavation design?
development showing locations, excavation
 Is the excavation design appropriate for
size and geometry, and the purpose of the
the geotechnical domain?
planned excavation. The plan is issued by
 Are major structures considered in
the Mine Planning department, and reviewed
design?
by all stakeholders before the final sign off
 Is the proposed excavation unfavourably
by the Mine Manager. Following the Mine
oriented with respect to rock mass
Manager‟s approval it is issued to the survey
structure?
department to generate a survey note for
 Has modeling of the area been
issue for construction/excavation.
completed and are high stress conditions
1.3.3. Tactical Level Planning or unfavourable orientation conditions
expected?
GCMP requires no mining to take place  Are pillars being created, and if so, are
without a Survey Note (SN) file note the dimensions appropriate?
instruction being signed off by all relevant  Are there any planned excavations
stake holders. All SN instructions are which pass too close to each other?
expected to include notes on the expected  Is the mining sequence appropriate and
ground conditions, all interpreted geological acceptable?
contacts, geotechnical boundaries, and
 Is there the potential for backfill or water
expected structures as detailed on the source
inrush?
POI. Where ground support is to be installed
 Has the void model been checked for
to a defined standard, this standard is
adjacent workings?

Page | 8
 Are the support and reinforcement to confirm that the ground support selection,
elements appropriate for the excavation installation methods and installed quality are
service life? adequate.
 Is the proposed excavation an unusual
1.4.1. Inspection and Audits Schedule and
size/shape with special ground control
Accountabilities
requirements?
 Is the planned excavation a highly All personnel entering a work area complete
exposed area? a workplace inspection, to identify and
 Are intersections planned; if so is the assess hazards associated with the ground
ground support/reinforcement conditions. If a geotechnical hazard exists
appropriate? then, if possible the person finding the
 Has the life and purpose of the hazard rectifies the deficiency immediately.
excavation been considered? If the hazard cannot be immediately
rectified, the area is barricaded and the
1.4. Verification hazard reported to the Mining Mate / Shift
Ground support performance is highly Supervisor. Ground inspections are
dependent upon the quality of installation undertaken on a regular basis as outlined in
and its suitability in respect of the ground the inspection matrix in Table 2.0.
conditions encountered. The inspections,
audits, and QA/QC procedures are designed

Table 2.0 – Inspection Matrix outlined in the GCMP (Vyazmensky, 2014).


Inspection Reporting
Type of Inspection Responsible Person/s
period Level
Mining Mate inspection of active heading Mining Mate via Shift
Shift / working area (Development and Statutory Diary Supervisor
Production)
Assistant
Shift Supervisor inspection of active Shift Supervisor via Manager
Daily heading / working area (Development and Statutory Diary (Section in
Production) Charge)
 Declines Assistant Manager/s Mine
Weekly  Production levels via Statutory Diary Manager

 All active mining areas for the month


including declines and stockpiles. Head of Geotechnical
Mine
Monthly  Workshop, inactive mining areas, Engineering via UG
Manager
electrical substations, pump stations, Inspection Log Book
fan installations

Page | 9
1.4.2. Ground Support Systems QA/QC 1.5.2. General Geotechnical Hazards

To determine the actual performance of the Processes to be followed for the reporting of
installed support elements, pull tests and geotechnical hazards:
visual inspections are carried out on resin
encapsulated rock bolts and cement grouted  The operator/person notices or observes
a geotechnical hazard;
cable bolts. Strength testing of FRS is
 The hazard must be reported to the
carried out to determine its compressive Mining Mate / Underground Supervisor
strength. Regular resin lab tests are carried (if considered significant, retreat and
out by the geotechnical department and by barricade the area before reporting the
supplier as a part of the quality check and event);
quality assurance. The testing procedures are  A workplace inspection must be
designed in accordance with the DGMS completed by the first person(s) who
observes the hazard.
guidelines.

1.5. Geotechnical Hazard reporting


1.5.3. Communication of Ground
1.5.1. Fall of Ground Conditions

All falls of ground are immediately reported Daily production meetings are held and all
to the Mining Mate and/or Shift Supervisor, observed or expected ground condition
who then inform the Assistant Manager / information is communicated at these times.
Section in Charge, Geotechnical Engineer Communication at this meeting does not
and Mine Manager. The Shift Supervisor is replace timely reporting when hazards are
tasked to ensure the area is barricaded and identified. Rather, the meeting is a forum to
inspected by a Geotechnical Engineer. The ensure that all relevant personnel are
Geotechnical Engineer reports all apprised of developments during the past 24
information to the Mine Manager with hours, and expected conditions for the day
any/all proposed further actions, and ahead. This information is then
identifies the cause of the rock fall. communicated to the underground
workforce through the Assistant Manager or
Any recommended actions and support Mine Manager.
plans are outlined and the ground control
checklist signed off before any work may 1.6. Training
commence. The Geotechnical department is involved in
various training programs provided to
Once remedial works are completed, the RAM UG personnel, from executives to
Geotechnical Engineer also should inspect operators & helpers.
and sign-off for compliance.
The GCMP stipulates all personnel working
in underground to undergo a „ground
awareness‟ training. The training
communicates the observed ground behavior
Page | 10
& conditions, ground related hazard A GCMP review will also be initiated
identification, ground support practices following a serious potential injury or
adopted and communication procedures. incident from a ground control related
hazard, or to reflect and correct any areas of
In addition to the ground awareness deficiency identified.
training, the Geotechnical department
conducts or is involved in various training The Mine Manager and Head of
on ground support SOPs, such as cable bolt Geotechnical Engineering are required to
installation, etc. sign off on the GCMP after each review to
formalise and give currency to the
1.7. Responsibility / Accountability document.
Matrix
Organizing responsibilities and lines of RAM UG utilizes services of CIMFR Rock
communication is critical during ground Mechanics experts from Dhanbad for
control measures. At RAM UG the GCMP independent peer review of the document.
provides responsibility roles for all
personnel regarding ground related issues,
from Unit Head & Mine Manager to
Geotechnical Engineers and all UG
employees & contractors. An example of the
various roles associated with their positions
is provided in Table 3.0.

1.8. GCMP review and audit process


Components of the GCMP will be reviewed
on an annual basis by the following:

 Unit Head
 Mine Manager
 Assistant Manager(s) / Section-in-
Charge
 Head of Mine Planning
 Head of Geotechnical Engineering
The RAM UG GCMP will be reviewed in
the first year initially on a 6 monthly basis
and then on periods not exceeding 1 year.
As necessary, external reviews can be
initiated by the site management to ensure
that all the latest ground control regulations
and developments are incorporated.

Page | 11
Table 3.0 – Some key points of the Responsibility / Accountability matrix outlined in the GCMP
(Vyazmensky, 2014)
Appointed
Responsibilities
Positions
GCMP is implemented, management systems and work practices comply with statutory
Unit Head regulatory requirements, qualified and/or suitably trained persons are appointed or
retained, and an external audit of the GCMP is done at intervals not exceeding 2 years.
GCMP is implemented and resources are allocated in order to implement it. Ground
control related SOPs are implemented and regular SOP reviews are done. Qualified
personnel are appointed to line management roles. Geotechnical inputs are considered
Mine Manager
in mine design and operations, and mining activities have an approved survey note.
Ongoing training, suitable equipment & material, quality assurance programs, etc are
available. Non-compliance items are rectified in a timely manner.
Mining Mining contractor meets GCMP requirements, if ground support is considered
Contractor Site inadequate it is brought to the notice of Technical Services Manager or his delegates,
Manager assist in investigating ground fall incidents and in executing remedial actions.
Mining Mates SOPs are understood, implemented and monitored to ensure compliance. Ground
and Shift support meets requirements. Approved SN present for mining. Geotechnical related
Supervisors issues are inspected and appropriately reported in accordance with site requirements.
GCMP is implemented and timely updated. Geological and geotechnical models are
Technical
timely calibrated, updated and communicated. Geotechnical inputs are appropriately
Services
considered to mine design and operations. Ongoing training where appropriate. Audit,
Manager
review and quality assurance programs are carried out regularly and documented.
Sufficient reliable data is available, timely updated, analyzed and communicated.
Appropriate and best practice ground control standards are implemented on current
Geotechnical
and/or expected rock mass conditions. Timely review of mine design and advice on
Head
planning, design and sequencing. New technologies are reviewed and their applicability
recommended. GCMP and associated documents are audited and updated as required.
Sufficient & reliable geological data is available, updated, analyzed and communicated.
Up to date resource, structural and lithological models are available. Geotechnical
Geological
inputs are considered regarding grade control and ore reserve reporting. Any significant
Head
changes to geological interpretations are reported to Tech Services Manager and
Geotechnical Head.
All necessary information in the Plan of Intent mine design is provided. All
development within the mine is designed to a set standard and does not commence
Mine Planning without an SN file note. Geotechnical inputs are appropriately considered regarding
Head mine design, planning and sequencing. Monthly, annual and life of mine
plans/schedules are provided to the geotechnical department in time to allow suitable
analyses. Assistance is provided in the review of the GCMP when required.
Appropriate training and refresher courses are provided in the relevant aspects of the
Safety Officer
GCMP and related SOPs, and then assessed to be deemed competent.
Survey notes (SN) contain relevant information and are available in a timely manner
Statutory
for review. All developments are surveyed to assess compliance with design tolerance
Surveyor
and communicated.
Ground Control Ground support is installed meet GCMP requirements. Report poor support installation,
Officers ground falls, poor ground conditions, etc to shift supervisor.
Complete appropriate training and assessments and be deemed competent by RAM UG
All UG
and/or the contractor. Be vigilant of the ground and ground support conditions and
employees and
report any relevant information/observations to the shift supervisor. Not undertake any
contractors
work without approved plan or without the work being covered by an up to date SOP.

Page | 12
ec-
3. Conclusion 2009/Presentations/Day3/Safety&Heal
thPerformanceinIndianCoalMining-
The GCMP framework provides a RBChakraborty.pdf).
systematic and methodical approach to
managing ground fall hazards. DIPS™, version 6.0. Rocscience ©
software.
Rampura Agucha UG mine is in process of (https://www.rocscience.com/rocscienc
finalizing of GCMP implementation. A e/products/dips).
word of advice for operations planning to
develop and implement GCMP: Mawdesley, C., Trueman, R., Whiten, W.J.,
(2001). Extending the Mathews
> When developing the document get
stability graph for open-stope design.
ALL key stakeholders involved,
Copyright © 2003 EBSCO Publishing.
encourage comment, peer review and
audits; Phase2 ™, version 8.0. Rocscience ©
> Keep it simple and easy to follow, software.
yet comprehensive; (https://www.rocscience.com/rocscienc
e/products/phase2).
> Ensure that GCMP requirement meet
and/or exceed regulatory R. Ulusay (Ed.) and J.A. Hudson (Ed.).
requirements; (2007). The Complete ISRM Suggested
> Embark on training efforts early; Methods For Rock Characterization,
Testing and Monitoring: 1974-2006.
> Maintain records related to ground International Society for Rock
control – “if you cannot measure – Mechanics (ISRM).
you cannot manage”
UNWEDGE™, version 3.0. Rocscience©
software.
REFERENCES
(https://www.rocscience.com/rocscienc
Barton, N., Lien, R. and Lunde, J. (1974). e/products/unwedge).
Engineering classification of rock Vyazmensky, A. (2014). Ground Control
masses for the design of rock support, Management Plan, Rampura Agucha
Rock Mechanics, Vol. 6, pp. 189-236. Underground Project. Version 1.
Chakraborty, R.B. (2009). Safety and Health
Performance in Indian Coal Mining.
Presentation by Dy. Director General
Mines Safety, DGMS, Dhanbad,
(http://www.sari-
energy.org/PageFiles/What_We_Do/a
ctivities/advanced_coal_managment_d

Page | 13
About the Authors
Geotechnical Department, Rampura Agucha Underground Mine
Bhilwara District, Rajasthan, India 311 029
Tel. No. (+91) 77268 11694 / 95210 54894

Pranay Yadav – Geotechnical Engineer (Pranay.Yadav@vedanta.co.in)


Pranay completed his Bachelors in Mining Engineering degree from the prestigious Indian
School of Mines (ISM), Dhanbad India, in 2013. Since then he has been working at Rampura
Agucha Underground Mine as a Mining Geotechnical engineer.
Mikhail Sonam – Geotechnical Engineer (Mikhail.Sonam@vedanta.co.in)
Mikhail completed his Bachelors in Geotechnical Engineering with Honors from the University
of Tasmania, Australia in 2011. He has since worked in various projects in civil and open pit /
underground mining and has recently joined the Rampura Agucha underground geotechnical
team in 2015.
Amit Panda – Geotechnical Engineer (Amit.Panda@vedanta.co.in)
Amit completed his Bachelors in Mining Engineering degree from the prestigious Indian School
of Mines (ISM), Dhanbad India, in 2013. Since then he has been working at Rampura Agucha
Underground Mine as a Mining Geotechnical engineer.
Binayak Banerjee – Geologist, Geotechnical Dept. (Binayak.Banerjee@vedanta.co.in)
Binayak completed his M. Sc in Geology from the Presidency University (Kolkata) in 2013 and
since has been working at Rampura Agucha Underground Mine adding his geological input in
the Geotechnical department.
Dinesh C. Paneri – Associate General Manager (Geology) Geotechnical Dept.
(Dinesh.Paneri@vedanta.co.in)
Dinesh completed his M. Sc degree in Geology (1985) & M. Sc (Tech) in applied geology
(1986) from the University of Rajasthan Jaipur. His invaluable experience spans over 20 years in
both open pit and underground mining, and he is a Fellow member of Geological Society of
India and life member of Quality Circle Forum of India. He has written papers on ore
characterization and on application of six sigma in mining at a national level.
Dr. Alexander Vyazmensky – Geotechnical Department Head
(Alexander.Vyazmensky@vedanta.co.in)
Dr. Alex educational background includes his Masters degree in Geotechnical Engineering and
Doctorate in Earth Sciences / Rock Mechanics. He brings over 15 years of diverse international
work experience, from mining, civil construction industries, to applied research and IT.

Page | 14

View publication stats

Potrebbero piacerti anche