Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification: MQ-SP-D-0001

Project Name: Date: 09 Dec 2011


Contract Number: Page: 1 of 5
Revision: 2

SPECIFICATION – SPECIFICATION WAIVER PROCEDURE

This specification has been revised as indicated below and described in the revision record on the following
page. Please destroy all previous revisions.

Revision Date Originator's Reviewed/Checked By Pages


No. Name & Initials Name & Initials
A 08/31/2011 D. Mayadas R. Berg 5
1 10/05/2011 D. Mayadas R. Berg 5
2 12/09/11 D. Mayadas R. Berg 5

APPROVALS SIGNATURES DATE

Lead Engineer Ron Berg


Project Manager: Russell Shulz
Client Approval:

ISSUED FOR : Construction X Other For Design


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification: MQ-SP-D-0001
Project Name: Date: 09 Dec 2011
Contract Number: Page: 2 of 5
Revision: 2

SPECIFICATION – SPECIFICATION WAIVER PROCEDURE

Record of Revisions
Revision
No. Date Description

A 8/31/2011 Issued for Approval

1 10/5/2011 Issue for Design. Revised per Client comments, paragraph 4.1. Revised to read
Marafiq Project Engineering throughout.

2 12/09/2011 Issue for Design. Revised per Client comments, paragraphs 1.1 and 3.2.
Revised to read Engineering Standard.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification: MQ-SP-D-0001
Project Name: Date: 09 Dec 2011
Contract Number: Page: 3 of 5
Revision: 2

SPECIFICATION – SPECIFICATION WAIVER PROCEDURE

Specification Waiver Procedure

Contents

1. SCOPE………………………………………………………………………………….4
2. REFERENCES…………………………………………………………………………4
3. GENERAL………………………………………………………………………………4
4. WAIVER REQUEST PROCEDURE…………………………………………………4
5. MARAFIQ PROJECT ENGINEERING ACTION PROCEDURE.………………...5
6. ATTACHMENT A ( 2 Pages)
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification: MQ-SP-D-0001
Project Name: Date: 09 Dec 2011
Contract Number: Page: 4 of 5
Revision: 2

SPECIFICATION – SPECIFICATION WAIVER PROCEDURE

1. Scope

1.1 This standard details the procedure and requirements for requesting MARAFIQ
Project Engineering for a waiver to a MARAFIQ Engineering Standard.

1. 2 This standard shall be used in conjunction with Waiver Request Form described in
section 2 below.

2. References

2.1 Reference is made in this standard to the following attached document. The latest
issue, amendments and supplements to this document shall apply unless otherwise
indicated.
“Attachment A” Waiver Request Form, two(2) pages.

3. General
3.1 Requests for waivers shall only be submitted by MARAFIQ affiliates and MARAFIQ
project management. Requests shall not be submitted by contractors, vendors,
manufacturers or their successors.
3.2 Written waiver approval shall be obtained prior to implementing a specific
nonconformance with a mandatory requirement of a MARAFIQ Engineering Standard.
3.3 Generalized ‘blanket’ waiver requests shall not be made.
3.4 An approved waiver for one requirement shall not be extended to cover other
requirements.

4. Waiver Request Procedure


4.1 Requester shall submit a waiver request on Attachment “A”, Waiver Request Form.
Any supporting documents shall be attached.
4.2 Request shall include any impacts of the waiver, by addressing changes in the
following items, for example, as applicable:
a. Facility Safety or reliability
b. Acquisition or Life Cycle costs
c. Length of overall project schedule
d. Environmental impact
4.3 Requester may also identify and analyze other alternatives to the requirement(s).
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Master Specification: MQ-SP-D-0001
Project Name: Date: 09 Dec 2011
Contract Number: Page: 5 of 5
Revision: 2

SPECIFICATION – SPECIFICATION WAIVER PROCEDURE

4.4 Requester shall sign waiver request form and submit to MARAFIQ Project Engineering
for evaluation.
4.5 Requester shall provide any additional information specified by MARAFIQ Project
Engineering, for review and evaluation.
4.6 Requester shall abide by MARAFIQ Project Engineering decision for approval or
rejection.

5. MARAFIQ Project Engineering Action Procedure

5.1 A reference number will be assigned to each submitted request.


5.2 Form will be returned to requester:
a. If waiver to the Engineering Standard is not required
b. If complete justification, as described in 4.2, is not provided
c. If not signed by requester

5.3 MARAFIQ Project Engineering may ask for additional explanation of specific factors or
concerns from requester if further evaluation is required prior to making a decision.

5.4 After final evaluation, request will be approved as is, approved as noted, or rejected.
5.5 If approved as noted, conditions associated with the approval will be specified.
5.6 If rejected, reasons for rejection will be provided.
5.7 MARAFIQ Project Engineering will determine whether a revision to the Engineering
Standard in question is required.
5.8 Waiver request form will be signed and returned to requester.
5.9 Records of all waiver requests, supporting documentation, evaluation results, and other
applicable information will be maintained.
“Attachment A”
REV. NO. 2
Waiver Request Form DATE 09 Dec 2011

PAGE 1 OF 2

Scope
This form shall be used in conjunction with MQ-SP-D-0001 Specification Waiver
Procedure. Details and related documents shall be attached to this form, referring to
respective affected Specification section(s).

Requester Reference No.:________________________ Date:__________________

Contract No.:__________________________ Job No.:__________________________


1
Project:_______________________________ Affiliate__________________________

Affected Specification No.:_____________________ Rev. No.:_______________


Paragraph No.:_______________________________

SPECIFY REQUEST_________________________________________________________

2 ___________________________________________________________________________

___________________________________________________________________________

3
WAIVER IMPACTS ON
Safety or Reliability Yes No Acquisition or Life-Cycle Cost Yes No
Environmental Factors Yes No Length of overall project schedule Yes No
Other Yes No Compatibility with Requirements Yes No

Details and Justifications________________________________________________________

____________________________________________________________________________

ALTERNATIVE(S)____________________________________________________________
4
____________________________________________________________________________

REQUESTER DETAILS

Name:______________________________ Organization:____________________________
5
Position:____________________________ Signature:_______________________________
“Attachment A”
REV. NO. 2
Waiver Request Form DATE 09 Dec 2011

PAGE 2 OF 2

For MARAFIQ Engineering Use Only

Waiver Request Log No.:____________________ Date Received_______________

Additional Information needed from requester Yes No


6
Details:____________________________________________________________________

__________________________________________________________________________

Name:_______________________ Signature:______________________ Date:__________

EVALUATION______________________________________________________________

___________________________________________________________________________
7
___________________________________________________________________________

Specification Revision required Yes No

FINAL DECISION

Rejected Approved as is Approved as noted

Note(s)____________________________________________________________________

__________________________________________________________________________
8
__________________________________________________________________________

Name:___________________________________ Position_________________________

Signature:________________________________ Date:___________________________

If this is a one-time deviation, describe affected equipment/component (including tag number,


if applicable) and location: