Document Transmittal
Ref. No. :
Mohamed El-Dardiry
Project Manager
WETICO
For Approval
Contractor:
Sub Contractor:
Project:
Document Title:
Design / Elevation
Design working Ref. to P&ID
Material from ground
T.P NO. Location Pipe line TAG No. T.P Connection T.P Rating Pipe Size *C (BAR) QIPP-MPN013- COOR. E COOR. N Remarks rev.
Spec. Temp. Pressure M00-0100
to center
System line
Suction line for effluent transfer pumps Direct connection with the
T.P 3 GBL50-BR001-500-GRP Flange (FF) ANSI B16.5 Class # 150 GRP DN500 20" 18-60 1 1/9 2631.196 4055.071 4.68m D
from tank nozzle of RCC tank
Suction line for backwash pumps from Direct connection with the
T.P 5 GCP53-BR001-400-GRP Flange (FF) ANSI B16.5 Class # 150 GRP DN400 16" 18-60 1 3/9 2624.846 4047.301 4.775m D
filtered water tank nozzle of RCC tank
Suction line for RO pass-1 feed pumps from Direct connection with the
T.P 6 GCK54-BR001-600-GRP Flange ANSI B16.5 Class # 150 GRP DN600 24" 18-60 1 3/9 2624.846 4043.820 4.96m D
filtered water tank nozzle of RCC tank
Filtered water line from Dual media filters No TP direct to tank from
T.P 7 GCB56-BR001-450-GRP - - GRP DN450 18" 18-60 6 3/9 NA NA NA D
to filtered water tank top
Prep. by : S.A
Check. by: H.M
App. by : T.M
Design / Elevation
Design working Ref. to P&ID
Material from ground
T.P NO. Location Pipe line TAG No. T.P Connection T.P Rating Pipe Size *C (BAR) QIPP-MPN013- COOR. E COOR. N Remarks rev.
Spec. Temp. Pressure M00-0100
to center
System line
NOTE : ALL THESE T.Ps ARE REFER TO DRAWINGS: QIPP-MPN013-M00-0100 1/9 SHEETS REV.0.
QIPP-MPN013-M00-0001 1/2 SHEETS REV.0.
QIPP-MPN013-C00-0001 1/2 SHEETS REV.0.
QIPP-MPN013-C00-0002 1/2 SHEETS REV.0.
Prep. by : S.A
Check. by: H.M
App. by : T.M