Sei sulla pagina 1di 13

WALIA journal 35(1): 77-89, 2019

Available online at www.Waliaj.com


ISSN 1026-3861
© 2019 WALIA

Risk management in construction projects: Perspective of contractors and owners


Ali Ahmad Jibran Khattak 1, Rehman Akhtar 2, Muhammad Abas 2, Qazi Salman Khalid 2, *, Sahar Noor 2,
AbdurRehman Babar 2, Shakir Azim 2

1Department of Technology Civil, Sarhad University of Science & Information Technology, Peshawar, KPK, Pakistan
2Department of Industrial Engineering, University of Engineering & Technology, Peshawar, KPK, Pakistan

Abstract: Construction industry considers risk management as a critical management process, aiming to realize the
project objectives in terms of time, cost, safety, quality, and sustainable environment. The construction projects are
initiated in environments that consist of various interconnected activities, therefore, risk and uncertainty are
always there. To this aim, a methodology was developed to discover and analyze the key risk factors, risk
prevention and mitigation methods and risk analysis techniques from perception of contractors and owners in
Pakistan. Questionnaire was designed and distributed among contractors and owners working on variety of
projects. To achieve the objectives, the data was collected from 311 contractors and 190 owners. The analysis
reveals that the most severe risk factors according to perspective of owner is defective design and not coordinated
design, while most severe risk according to contractor is financial failure and awarding design to unqualified
designers. Furthermore, the owners and contractors tend to consider the subjective judgment as the most effective
way of risk prevention method. According to the contractors’ and owners perspective, close supervision of the
subordinates, and increase in the working hours was the mainly effective mitigative technique for minimizing
negative impacts. The risk analysis techniques used by the contractors and owners are the direct judgment using
experience and personal skills.

Key words: Risk management; Risk factors; Construction projects

1. Introduction essential to have additional information of different


aspects of project, which can help in making risk-
*Even in the modern age, construction businesses informed decisions. For example, information
are engulfed with uncertainties and risks. In a regarding the unforeseen events is needed
construction industry, risk level defines the success throughout the project execution phase and the risk
and failure of a project (Paslawski, 2013). needs to be assessed. If the risk management of a
Construction projects have a greater number of risks project is not efficient then it can have negative
because of participation of numerous parties such consequences for the stakeholders, as on-time
as; contractors, owners, designers, subcontractors, preventive actions will not be taken against the risks
and suppliers, etc. (Khattak et al., 2015). Recognition and uncertainty associated in the project
and analysis of risks are one of the most important (Hopkinson, 2017). In addition, if preventive actions
areas of decision-making in a construction industry. are not taken on time then it results in
The contractors and owners of projects are widely communication risks, delays in the project
associated with a high degree of risk due to nature of deliverables, disputes and increases cost (Yang et
construction projects (Kartam & Kartam, 2001). al.,2016). Risk management is regarded as one of the
Hence, it is necessary to analyze and manage risks main factors in the designing and management of the
for the successful accomplishment of a construction venture (Qazi et al.,2016). The method of starting a
project. Construction projects require people with project from financial investment to final completion
adequate skills and expertise (Enshassi & Abu Mosa, is mostly a complicated and may possess uncertainty
2008). Some risks that negatively affects in procedures, which incurs additional risks at hand
construction industry of Pakistan are: unable to in the construction industry as compared to others.
complete project on time, injuries/ accidents on site, European Union, construction industry involve
construction delayed specifically due to weather high risk of accidents, counting 1300 causalities due
conditions, price hike of materials and labor, to construction accidents per year. Internationally,
construction approval issues, and defective design, the risk of a person being killed in construction
among others (Abas et al., 2016; Iqbal, et al., 2015; industry is three times and being injured is twice
Liu et al.,2016; Mubin & Mubin, 2016; Zafar et al., than the other industries, which cost heavily to the
2016). To make a competent risk management, it is individual, employer as well as society. Also it is
huge proportion of the contract price (De Lemos et
al., 2004). Occurrence of accidents at construction
* Corresponding Author.

77
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

sites is also major risk involved in the construction will be discovered in Pakistan’s construction
of buildings, roads etc. As construction is industry and the significance of other factors such as
environment of hazardous in many aspects, the severity is analyzed, thereby providing sensible
accidents it experiences may have different severity suggestions toward updating the risk management
levels, resulting in some major and minor injuries process in construction industry and raises the
with even some resulting in fatality. The result of performance of acquiring firms as well as owners in
accidents are delays in construction, cost overrun the construction industry of Pakistan. The study will
and also cost the organization’s reputation, which be prolonged for an improved understanding of the
results in losing the confidence among workforce risk factors faced by contractors and owners on daily
internationally. Now due to authorities actions to basis. The Investigation of the severity of risks as per
ensure the safety standards, resulted in increased opinions of the owners and the contractors, the
performance of construction industry (Wang et examination of efficiency of risk management
al.,2006). Construction industry in Lithuania has techniques that are used by contractors and owners.
turnover of EUR 1.91 billion, considered as one the Based on the literature review and expert opinion
largest industries in of Lithuania, is the source of the identified risk factors are shown in Table 1.
employment 94 thousand workers in 2011. The literature in this regard is nearly sufficient
Unfortunately, health and safety issues are also with models that assess and measure risk or
there. There are more fatalities and injuries than any methods which managers can employ to manage the
other industry. Statistic shows that in 2011 the risks. However, there are two major gaps in the
number of number of construction workers killed existing methods, as pointed out by (Schieg, 2007).
are 13 compared to 7and 4 industrial and First of all, most of the methods are based on solid
agricultural workers respectively. While the number statistics and past data like Monte Carlo simulation
of fatalities increased by twice than 2010 i.e. from 6 including network analysis and other factors
to 13 fatalities from 2010 (Šukys et al., 2011). (Dawood, 1998), and also matrix propagation
Theoretical risk analysis techniques for the method (Tüysüz & Kahraman, 2006). Manager may
construction industry have been established from experience short of data if the project is done in new
number of years, but very rarely applied in real life environment with new setting, and also many
except for the few areas and few industries in multi- problems are ill-defined and imprecise, which these
disciplinary clients in the private sector (Perry & methods fail to address. Secondly, there always has
Hayes, 1985). The risk factors for all the projects been a discrepancy between risk analysis and risk
may be similar for the local or international projects. management. For example, Analytic Hierarchy
The risk factors include reduced detail design, Process (AHP) is used to identify the risks and divide
insufficient quality check and defective materials the projects as high, medium and low risk (Dey,
which results in defective work. The factors for plan 2010), but no response to diminish risks have been
delays are deficient design, bad weather, late suggested. Since there is a weak link between risk
construction site possession, fluctuation in labor and analysis and risk management, a need for an
materials supply, unforeseen ground conditions and integrated framework which addresses both the
incompetent connections and coordination with the aspects is aspired. (Dey, 2002, 2006) has stressed on
involved parties. All these risk factors can be the need for such a framework over several
addressed by a proper project management, but due publications. (Cho et al., 2002; Kangari & Riggs,
to unique nature of projects the risks may vary for 1989; Zeng et al., 2007) incorporated fuzzy theory in
each project due to which it is difficult to assess risk assessment. Other models used in assessment
these risks in advance. (Zhi, 1995). Any sort of are sensitivity analysis(White, 1995), fault tree
construction project is always prone to risks and analysis (Abdelgawad & Fayek, 2010), and critical
abundant work has been carried on it in the path methods(Nasir et al., 2003) etc.
developed countries, however, in the context of To address these gaps, this study aim to develop
developing countries such as Pakistan, are still risk management framework for Pakistan’s
struggling to quench the research gaps in risk construction industry, which combines risk analysis
perspective of a construction industry (Khan, 2013). and risk management while eliminating the need for
Pakistan’s construction companies industry is previous data and uses the managers’ expertise and
largely impacted by the miscalculation of the intuition as a substitute. The framework, though
vulnerable risk, and lack of understanding regarding reliant on intuition, should be objective, precise and
the risk management including lack of proper easy to apply. The paper first presents a literature
identification, analysis and assessment of risk. review on the risk factors and risk management
According to Nawaz et al. (2019) there is substantial models or tools already available. Next, it elaborates
requirement in the local environment of Pakistan to the tools and methods reviewed, which form the
implement and associate the systematic basis for the new framework, propose the new
methodology of risk management, so that framework to address the problems associated with
individually and collectively the threats of risk can the existing models. Finally, the paper provides a
be minimized. There is a considerable need of detailed discussion on the framework and concludes
standards for risk management in the construction with recommendations on the basis of study that will
industry that need to be developed. Therefore, the assist contractors and owners of projects to
research has a lot of significance as the risk factors effectively manage the common risks.
78
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

Table 1: Risk parameters and factors identified by authors

(Ibn-Homaid, Eldosouky, & Al-Ghamdi,

(El, El Nawawy, & Abdel-Alim, 2017)


(Rooshdi, Ab Rahman, Baki, Majid, &

(Chang, Hwang, Deng, & Zhao, 2018)


(Zolfagharian, Nourbakhsh, Irizarry,

(Choudhry, Aslam, Hinze, & Arain,

(Wu, Nisar, Kapletia, & Prabhakar,


(Mhatre, Thakkar, & Maiti, 2017)
(Zhao, Hwang, & Low, 2013)
(Hwang, Zhao, & Toh, 2014)
Ressang, & Gheisari, 2012)

(Kartam & Kartam, 2001)


(Sharma & Swain, 2011)

(Hallaq & Raouf, 2003)

(Adeleke et al., 2018)


(Wang et al., 2006)

(El-Sayegh, 2008)

(Paslawski, 2008)
(Liu et al., 2016)

Ismail, 2014)

2014)

2011)

2017)
Authors

Risk
Risk Factors
Parameters
Accidents at site     
Physical Supplies    
Varied labor   
Acts of good   
Environmenta Site not accessible    
l Condition of the weather  
Differing site situations  
Defect in design         
Design not coordinated properly      
Design incorrect quantities   
Lack of consistency    
Awarding design     
Material, Labor & equipment
       
productivity
Logistics
Defining scope of work      
precision of project plan     
Inflation     
Financial
Delayed payment      

Pakistan construction industry is highly impacted from owner’s and contractor’s perspective
by the miscalculation of the risks, and lack of and verify the importance of every factor in terms of
understanding regarding the risk management severity and to develop a risk management strategy.
including lack of proper recognition, analysis and Following are the objectives of the study:
evaluation of risk. In Pakistan very little research
have been carried out on risks in construction  This research is aimed to determine the key risk
projects. (Iqbal et al., 2015) carried out a study factors in the construction industry of Pakistan,
regarding risk factors in construction industry of area of focus is Peshawar.
Pakistan, incorporating different risks i-e site  The Investigation of the severity of risks as per
accidents, unforeseen site condition, corruption and opinions of the owners and the contractors.
bribery at sites in total of 37 factors along with two  The examination of risk management techniques
types of risk management techniques risk preventive that are used by contractors and owners.
techniques. Though, mitigation study of risk was  To conclude and give recommendations in light of
undermined in their work (Choudhry et al., 2014) the study that will help contractors and owners of
carried out study on identification of risk projects to effectively manage common risks.
management systems in construction projects in
Pakistan. However, their study is limited to 2. Materials and methods
identification and quantification on bridge
construction and also lacks a proper framework The following methodology is deployed to meet
endorsing risk prevention and mitigation. (Nawaz et the research objectives. As presented in Fig. 1,
al., 2019), also developed a frame work for risk context establishment/ literature of the state-of-the-
management in construction industry of Pakistan, art research is the foundation, which is to be kept in
but the research was limited to success factors and loop during the whole research. This leads to a bi-
risk management techniques solely based on phased study in which the first phase consist of risk
contractor’s perspective. In light of the above identification and its analysis through measuring the
discussion on gap our research has extended scope severity levels, whilst the second phase derives from
taking into account: development of framework for the prior to model for the preventive and mitigative
effective risk management based model risk factors steps been undertaken.
(divided into 9 groups), risk preventive & mitigative
methods, and risk analysis techniques from 2.1. Respondents
perspective of contractors and owners.
Furthermore, the purpose of the research work is The targeted respondents for the present study
to determine the factors that contribute to risk in the were contractors and owners. Information regarding
construction industry of Pakistan. To address this contractors was extracted from Pakistan
purpose, the risk factors within the construction Engineering Council (PEC) website
industry of Pakistan will be discovered https://verification.pec.org.pk/COFirmList.

79
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

Currently, there are 19,820 contractors owners, so the information were obtained through
registered with PEC and they are divided into personal contacts, contractors and consultants. The
different categories based on project cost limit, owners are classified as public (government) and
minimum requirement limit of engineers and private. The numbers of owners found were
financial soundness of contractors as shown in approximately 200 private and 295 public based on
Error! Reference source not found.. the project worth they conducting more than 1000
Unlike contractors as there are no such data million (Rs) and for private between 500 and 2000
available, which gives exact information about the million (Rs).

Context Establishment

Risk Identification Risk Analysis Risk Prevention


 Risk Parameters  Direct Judgment
 Subjective Judgment
1….n  Comparing Analysis
 Risk Factors  Probability Analysis  Devise a proper schedule

1…n  Expert System


 Bias risk premium to time estimation
 Sensitivity Analysis

 Simulation Analysis  Stand by alternative method

 Share Risk with concerned parties

Risk Evaluation
Levels Risk Mitigation

 Supervision to Subordinates
Risk Severity

 Increase Work Hours

High  Coordination with Subordinates


Th> n*

 Change sequence of work by overlapping


Medium

Th> o <n* activities


Low
 Increase Manpower

 Change construction method

Fig. 1: Methodology for Risk Measurement & Prevention

Table 2: Contractors Category Details [(https://www.pec.org.pk/fee_Pakistani.aspx)]


Limit of Construction Financial reliability (Rs.
Total
S.No Category Cost of Project in Engineers Required in million)=Paid up
Registered
million (Rs) Capital/Net Worth
Two P.Es having 20 yrs. of
1 C-A Unlimited 100 195
Experience each + RE
Two P.Es having 15 yrs. of
2 C-B ≤ 4000 70 123
Experience each + RE
Two P.Es having 10 yrs.
3 C-1 ≤ 2500 55 353
Experience each + RE
4 C-2 ≤ 1000 One P.E + R.Es 35 1013
5 C-3 ≤ 500 50 percent R.E 20 1627
6 C-4 ≤ 200 50 percent R.E 4 3521
7 C-5 ≤ 65 Only one R.E 2 4686
8 C-6 ≤ 25 Only one R.E 1 9075
Total 20593
Professional Engineer (P.Es), Registered Engineer (RE)

80
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

2.2. Survey Instrument Wilk test were performed to ensure the normal
distribution of data. The data didn’t follow normal
In this research, the questionnaire deployed has distribution so non-parametric tests were performed
been adopted from (Mousa, 2005). The to further analyze the data. Kruskal-Wallis test was
questionnaire was divided in to three sections: performed to analyze whether there exists difference
in opinion between contractors and owner in raking
• The first section dealing with necessary significant factors. Severity of risk factors were
information regarding to the respondents and calculated using mean score, while risk preventative,
organization, such as designation, experience, mitigative methods and analysis technique were
number of employees and annual work volume. ranked based on % effectiveness
• The second section comprises of series of risk
factors, that belong to nine major groups i.e., 2.4.1. Demography of the respondents
environmental, design, Physical, political,
financial, legal, construction, logistics, and A total of 501 valid questionnaires out of 670
management risks. To take opinion of were received with average response rate of 75
respondents likert scale 1-10 (1-3 represents low percent as shown in Table 3. Hence, it is considered
risks, 4-7 represents medium risks, and 8-10 to be adequate for analysis as it is greater than
represents high risks) was adopted. This section required minimum sample size of 390. Error!
includes 36 risk factors and was finalized after Reference source not found. shows the
consultation with local experts from both demographic information of respondents. The
academia, and construction professionals. responses were recorded through personal
• The third section contains relative use of interview, electronic means and through courier
preventive methods, mitigative risk methods, and services.
risk technique based on five point likert scale 1-5
(1 Never, 2 rarely, 3 sometimes, 4 often, and 5 2.4.2. Reliability analysis
always).
Reliability provide internal consistency of data
2.3. Sample determination and selection that are collected based on scale, and provide the
amount of inter-correlation among the factors
The targeted populations of respondents were (Netemeyer et al., 2003). Cronbach Alpha (α) test
contractors registered with PEC and owners both was conducted to check reliability of collected data
public and private. Hence, a random sample was from contractors and owners. The α value for
needed to make sure to represent the sample of contractors and owners were 0.937 and 0.905, while
target respondents. Therefore, for sample size combined α value were 0.920, so these values are
determination Cochran formula (Cochran, 1977) is rationally higher than 0.7 which is the acceptable
used as shown in Eq. 1. value (Alaghbari et al., 2007). This shows that data
was highly reliable and suitable for further analysis.
𝑍2 ×𝑃×(1−𝑃) 𝑍2 ×𝑃×(1−𝑃)
𝑆𝑆 = ( )/(1 + ) (1)
𝐶2 𝑁𝐶 2
where: 2.4.3. Normality test
SS = Sample Size
Z = Z value (1.96 for 95% confidence interval) As the sample size is less than 2000, a Shaprio-
P = Percentage picking a choice (marginal error) Wilk test is performed to check the normal
N = Population size distribution of collected data (Royston, 1983).
C = Confidence Interval (0.05) Significance (sig.) value greater than 0.05 shows
evidence for normality. As shown in Error! Reference
As P value is unknown, so it is suggested to take it source not found., sig. values for each group of risk
as a conservative value of 0.50 (Cochran, 1977). The factors were less than 0.05, so data is not normally
population size determined for contractors were distributed. It further justified that non parametric
20,593 and for owners both private and public were test would be suitable for further analysis.
495, so this make total population size of 21,088.
Hence, Eq.1 was applied to reduce the population 2.4.4. Kruskal‒Wallis test
size and consider as representative of all
respondents. The desired minimum sample size Kruskal‒Wallis (Breslow, 1970) test was
calculated was approximately 390. To make conducted to check whether there exist difference in
response rate higher questionnaire were distributed opinion of contractor and owners on ranking of
to 670 respondents. The targeted respondents were significant risk factors in each risk group, risk
contractors of category CA, CB, C1, and owners. mitigation, preventive methods and analysis
techniques. Sig. value less than alpha value of 0.05
2.4. Analysis method shows variation in opinion. The test results as shown
in Error! Reference source not found. reveals that
Reliability of questionnaire instrument were except physical group factors there exist difference
analyzed through Cronbach’s alpha test. Shapiro of opinion between contractors and owner on

81
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

scoring of significant risk factors in each risk group, techniques.


risk mitigation, preventive methods and analysis

Table 3: Demography of the respondent


Target Respondent Years of Individual Total Response
Distributed
Respondents Designation Experience Responses Received Rate (%)
Managing director 15-20 18
Project Manager 13-15 21
Resident Engineer 10-15 21
CA 125 95 76
Senior site
15-20 20
Engineer
Surveyor 10-15 15
Managing director 15-22 13
Structural Engineer 10-15 15
CB Safety Engineer 12-16 95 15 71 75
Project Manager 15-20 15
Resident Engineer 10-15 13
Managing director 16-20 25
Project Manager 10-15 30
C1 Site Engineer 15-20 190 30 145 76
Safety Engineer 11-15 30
Surveyor 12-16 30
Public Owner 15-20 140 100 100 71
Private Owner 12-17 120 90 90 75
Total 670 501

Table 4: Normality Test % 𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒𝑛𝑒𝑠𝑠 =


∑𝟓𝒊 𝒂𝒊 𝒇𝒊
× 100 (3)
Groups Sig. value 𝟓𝑵

Physical 0.024
Environmental 0.047 where, “a” is the weight assigned to each responses
Design 0.031 (1-5), f =frequency of each response, N =total
Logistics 0.002 number of responses.
Financial 0.041
Legal 0.031 3. Results
Construction 0.019
Political 0.017 This section presents and describes the current
Management 0.013 views of contractors and owners in Pakistan
concerning the severity of the identified 44 risk
Sig.value for physical group is 0.078, which factors divide into 9 groups as shown in Error!
greater alpha value of 0.05 therefore is insignificant Reference source not found..
and shows agreement on ranking of factors, while for
the rest of groups are less than 0.05 therefore is 3.1. Physical group
significant and shows difference of opinion on
ranking of significant factors as evident from ranking Results established that the provision of
in Table 6. materials that are defective is the most severe
hazard in the physical group with mean score of
2.4.5. Ranking of factors 5.95, followed by occurrence of accidents (5.625),
and variations in labor and equipment productivity
The severity of identified risk factors were (4.625).
ranked according mean score (Alaghbari et al., 2007) These results point to the concerns of contractors
as shown in Eq. 2. as well as owners about the fitness of materials and
∑ 𝑓×𝑠
safety actions for construction projects, this outcome
𝑀𝑒𝑎𝑛𝑆𝑐𝑜𝑟𝑒 = (10 − ) (1 ≤ 𝑀𝑒𝑎𝑛𝑆𝑐𝑜𝑟𝑒 ≤ 10) (2) is supported by the results of (Ahmed et al. 1999)
𝑁
both contractors and owners agree upon occurrence
where, f is the frequency of responses to each of accidents and delivery of defective materials as
scoring (1-10), s is the score on scale (ranges from 1 the most severe risks in the physical group. Accident
to 10)given to each factor by the respondents, and N and site safety are amongst the top significant risks
is the total number of responses concerning that which are typically disregarded in Pakistan but are
factor the main setback according to this survey and must
Risk preventative, mitigative methods and be appropriately addressed.
analysis technique were ranked based on
%effectiveness (%frequency index) (Le-Hoai et al.,
2008), which is calculated as shown in Eq. 3.

82
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

Table 5: Kruskal-Wallis test for risk groups

Environmental

Construction

Management
Risk Groups

Financial
Logistics
Physical

Political
Design

Legal
Chi-
18.373 38.040 38.279 38.457 38.235 38.29 38.198 38.401 38.261
Square
sig. value .078 .00272 .0019 .0002 .0023 .0017 .0025 .0005 .0020
Risk Preventive Analysis
Mitigation Methods Technique
Chi-
36.012 36.231 36.193
Square
sig. value .0032 .0021 .0025

Table 6: Overall risk significance


Contractor Owner
Risk factors with groups Group Overall Group Overall
Severity Owner
Rank Rank Rank Rank
Physical group risks
Occurrence of accidents due to poor safety procedures 5.625 2 5 5.575 2 3
Supplies of materials that is defective 5.95 1 7 6.375 1 16
Varied labor and machinery productivity 4.625 3 8 5.35 3 4
Environmental risks
Site not accessible 5.65 1 9 4.025 3 30
Adverse weather conditions 4.75 2 18 4.2 2 23
Environmental factors 3.675 4 28 6.1 1 7
Acts of God 4.2 3 23 3.375 4 34
Design group
Design awarded to unqualified designers 7.35 2 2 5.675 4 6
Not coordinated design 5.975 3 3 7.925 1 2
Lack of consistency 5.6 4 10 7.4 2 8
Defective design 8.2 1 15 6.075 3 1
Inaccurate quantities 4.825 5 17 4.275 5 15
Logistics group
Labor, Material, equipment unavailability 6.6 1 20 4.7 2 21
Scope of work defining 5.475 2 29 6.15 1 25
Accuracy of project program 4.125 3 24 4.125 3 26
Financial group.
Price rises(Inflation) 5.5 2 12 5.2 3 18
Payments delayed 6.375 3 13 5.525 2 12
Financial failure 8.45 1 1 8.10 1 14
Legal group
permit and regulation 4.25 4 25 5.92 1 27
Disputes among labors 5.6 2 19 3.90 4 28
Delays made by third parties 6.1 1 26 3.95 3 29
Delayed dispute resolution 5.55 3 11 5.50 2 13
Construction group
Change of order/negotiation 3.025 4 36 3.025 4 36
Lower work quality due to time constraints 3.35 1 31 4.2 2 24
Change in work plan 3.225 3 34 3.25 3 35
Actual quantities 3.3 2 33 5.025 1 32
Political group
Acts of Government 5.775 2 6 4.975 3 20
Legislation 4.75 3 27 5.675 1 10
War threats 5.875 1 4 5.525 2 11
Blockade 5.3 4 32 4.475 4 33
Management group
Ambiguous planning due to complex projects 3.075 6 35 5.05 4 19
Organization 4.325 3 21 5.275 3 17
Coordination with sub-contractors 4.825 2 16 5.675 2 9
Resource management 4.225 4 22 4.45 5 22
Information unavailability 3.45 5 30 3.475 6 31
Poor communication between involved parties 5.225 1 14 6.3 1 5

83
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

3.2. Environmental group given by contractor’s as well as owner’s. According


to Contractors the financial failure is the most
As seen in Error! Reference source not found., significant risk in the financial group. Financial
according to the contractors site accessibility is the failure of project occurs due to:
main reason of delay in construction projects with
mean score of 5.65; adding up the risk of adverse  Bank loans with high interest rates.
weather conditions is second most important risk in  Lack of financial resources.
this group with mean score of 4.75. On the other  Lack of knowledge about the ongoing project.
hand, according to owners environmental factors  Poor or insufficient management of cash flow.
such as flood, earthquake and hurricanes are  Low profit margin due to large number of
considered as severe risks with mean score of 6.1 for contractors competing for projects.
construction projects while the risks of unfavorable  Awarding projects to lowest bidder.
weather conditions and site accessibility did not
come out to high significant risks amongst the Above 80 percent the failure was caused by
surveyed risks. financial factors that is why financial risks got the
top weights among the studied risks. Small firms of
3.3. Design group category C4,C5,C6 do not have accounting sections
that on regular basis publishes financial reports and
Design group factors incorporated one of the therefore, financial ratios are difficult to monitor as
most significant factors among the surveyed risks. As they appoint private accountants. It is a very good
illustrated in Table 6, defective design with (8.2) idea to have adequate funds so the projects are
severity and grant the planning to unqualified delivered in time without any delay. Financial risk in
designer with (7.8) severity are the key risk factors. construction projects are of improper cash flow,
The results conjointly indicate that contractors bankruptcy due to delayed payments and dispute
expertise deficient or inaccurate design data for a with the supplier etc. in addition mega projects
construction project. This result was obtained from comprise of complex financial planning.
ranking the defective design risk class mutually of
the foremost vital risks to a project. it's to be noted 3.6. Legal group
that contractors involved concerning defective
design problems as a result of they might be Error! Reference source not found. shows that
accountable concerning any crucial problems could third party delays, labor disputes, delayed dispute
happen because of incorrect design. owners assigned resolution had the highest mean score of 6.1, 5.6, and
the risks of un-coordinated style with a mean score 5.55 in the legal group given by the contractors,
of 7.925, these risks will be decreased by being which show the significance of dispute resolution
attentive and coordinate properly between the and its consequences. Owners consider difficulty to
consultants providing the planning. Thus steps get permits from the government authorities to start
should be taken by a consultant and client to work in projects as a severe risk. Legal construction risks in
coordination and also involving the contractor if the construction projects consist of local law and
contract permits to have correct design & thus avoid building code, contractors should ensure to follow
problems in the implementation of a project. the legal contractual compulsions so they can benefit
from it.
3.4. Logistics group
3.7. Construction group
According to the Contractors unavailability of
labor and materials is a significant risk (Mean score There were four risks associated with
6.6). The unavailability of material and labor is some construction group namely change order
way related to political situation of our country, if negotiation, lower quality of work due to time
shutter down occurs, material prices will increase. constrains, changes in work and difference between
Vague work scope and inaccurate project program actual and estimated quantities. According to
has nearly equal severity, indicated by the owners. contractors there were no significant risks in the
These risks need to be fully understood to ease and construction group. Owners considered estimation
manage the work properly. Shortage of construction of incorrect quantities as a risk of medium severity,
material supply is a considerable risks and the due to non-practice of advanced methods to estimate
contractor is liable for this risk as provision of material quantities there is always difference
materials in most projects is the contractor’s liability between actual and estimated quantities.
and should be planned accordingly to mitigate this
hazard. 3.8. Management group

3.5. Financial group According to owners in the management risks,


the highest risk is that of poor communication
Financial failure risk with mean score of 8.45 got between different parties (severity 6.3). Lack of
the highest score among the surveyed risk factors proper coordination with the subordinates is also a

84
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

matter of concern for the owners (severity 5.675). in the construction project. The consequence of poor
According to contractors in the management risks, communications for an organization is that
the highest risk is that of poor communication employees will misjudge management decisions or
between different parties (severity 5.225). Lack of respond to them in a way that was not deliberated.
proper coordination with the subordinates is also a Equally, managers will misread the prerequisites of
matter of concern for the contractors (severity employees and will consequently suffer from lower
4.825) and information unavailability has 138 performance and a higher turnover of staff.
weighted score and 3.45 severity being the risk of Construction projects are greatly affected by
lowest concern. Improper communication has a lot environmental factors. The environmental effects on
of effects and consequences on construction projects the Project could include: reduced visibility and
such as cost overruns, time dealys, disputes and inability to maneuver construction and operation
finally project failure. It also found that highly instrumentation, delays in receipt of materials
effective communication can attain good cost and and/or provides (e.g., construction materials,
time management in production of flourishing reagents) and/or in delivering merchandise, changes
projects. to the power of employees to access the positioning
(e.g., if a road were to scrub out), injury to
3.9. Overall risk significance from perspective of infrastructure, raised structural loading, and/or loss
contractors and owners of electric power leading to potential loss of
production.
The results show that medium as well as high risk Financial failures greatly impact construction
were there from contractors’ point of view. projects. Possible solutions in mitigating financial-
According to the results, the highest risks of financial related delay like to structure the market, to not over
failure (Severity = 8.45), defective design (severity develop, to conduct coaching on cash flow
8.2) followed by awarding design to the unqualified management, right use of risk management, to be
designers (severity = 7.35). The lowest risk is of sensible in acceptance of the contract, to settle on a
change order negotiation (severity 3.025) and decent remunerator, and to use payment bond with
ambiguous planning due to project complexity bank and consumer were urged to purchasers and
(severity 3.075). contractors, severally.
According to the owners’ perspective, the highest Our results are supported by the results of
risk is of not coordinated design (severity = 7.925) (Kartam and Kartam, 2001), claiming that supply of
and not defective design (Severity = 6.075). The defective materials is accepted as a risk by the
lowest risk according to the perspective of owners is contractors. The same allocation has also been
of change order negotiation (severity = 3.025) and accepted by the contractors from Hong Kong
changes in work (severity = 3.25). (Ahmed et al., 1999). The results of environmental
factors i.e., difficulty in access to site is supported by
4. Discussion the results of the research of (Kartam and Kartam,
2001). The contractors on the other hand also tend
This research provides insights about the to be worried about the defective design as argued
perception of contractors and owners towards by (De Lemos et al., 2004; Koushki et al., 2005).
different types of risks that construction industry Contractors also tend to be worried about poor
face in Pakistan. There were 36 risks included in the communications and unavailability of labor,
questionnaire. The significant risks have been materials as it is related to the political situations.
identified a) defective design; b) not coordinated occurrence of accidents due to poor site safety
design; c) occurrence of accidents during conditions are also among the significant risks which
construction; d) varied labor and equipment is typically neglected in our country Pakistan but are
productivity; e) weak communication among the major source of postponement as per this survey
involved parties; f) Project design by incompetent and have to be given proper attention., client and
designers; g) environmental factors; h)lack of contractor must also take care to advance safety on
consistency; i) coordination with subcontractors; j) sites and affecting the projects in a positive way all
shortage/delay of material supply and; L) financial these findings are also supported by (Iqbal et al.,
failure. 2015). (Hallaq and Raouf, 2003) argues that there
Varied equipment and labour output is also a are so many reasons that the contractors can
significant risk in construction projects. Good project financially fail, which include lack of capital amount,
management in construction should smartly pursue lack of relevant experience, depending on the banks,
the economical utilization of labor, material and low profit margin, closure and awarding contracts to
instruments. Improvement of labor productivity the lowest price.(Hallaq and Raouf, 2003) also
ought to be significant and continual concern of the argues that greater than 80 percent of the failures
construction firms who are accountable for happened due to the economic failure. Moreover, if
construction projects. Material handling, which any kind of shortage in market occurs then prices of
incorporates procurement, inventory, workshop materials also increases (Ahmed et al., 1999).
fabrication needs special attention for price Therefore, our results are in line with the results of
reduction. Another major risk is improper (Hallaq and Raouf, 2003). Contractors also argue
communication between involved technical groups that delayed payments by the owners also causes
85
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

trouble and this is supported by the study of (Kartam is subjective judgment (80%) followed by the
and Kartam, 2001). The delayed resolution of updated project information (77.5%). The least
dispute also needs to be addressed as this creates effective method considered by the contractors’ is
ambiguity in the work legislations and it also utilization of a quantitative risk analysis technique
enhances difficulty in getting permits. The (47.5%).
construction group risks are in line with the findings
of (Ahmed et al., 1999). Political risks also tend to be 4.2. Risk mitigative methods adopted by
significant due to the unstable condition in the contractors and Owners
country.
Owner’s also consider design risks as significant Conferring to Fig. 3, according to the contractors’
risks and these results are supported by research perspective, close supervision of the subordinates
work of (Ahmed et al., 1999; De Lemos et al., 2004; was the mainly effective mitigative technique for
Shen, 1997). If a rush design is given then it gives minimizing negative impacts. Second most effective
rise to serious risks and the owners tend to have method is increase in the working hours. Increasing
problems. This means that there is a need of working hours helps in speeding up the processes.
innovative contract methods through, which the The rarely used mitigative method was of change in
allocation of risks can be done appropriately so that the construction method (60%). The six mitigate
the parties are able to handle them. methods are presented in the Fig. 3. The first
Risk management in construction isn't restricted mitigative technique suggested by the owners is
to noting down all the execs and cons or put a label close supervision to the subordinates for
‘negative risk’ on every troubling event. Management minimization of the unproductive work (92.5%)
could be a sophisticated, lasting and comprehensive whereas the last method suggested is the change in
method that begins before the investment and construction methods (60%). Coordination with the
generally lasts even once the completion of project. sub-contractors is also considered as an efficient
To sanely manage risk doesn't mean to stay aloof mitigative method by the owners (85%)
from it's however to acknowledge it properly and
direct all connected opportunities and hazards this is 4.3. Risk analysis techniques adopted by
also supported by (Szymański, 2017). contractors and owners

4.1. Risk Preventive actions adopted by The risk analysis techniques used by the
contractors and owners contractors as revealed in Fig. 4, the most is the
direct judgment using experience and personal skills
The preventive actions from owners’ perspective (90%) followed by comparing analysis (82.5%).
are shown in Fig. 2. Owners tend to consider the Simulation analysis is barely used by the contractors.
subjective judgment as the most effective way. Next, Owners also tend to use direct judgment the most
owners consider getting up to date information (95%) followed by comparing and probability
regarding the project necessary and essential. analysis (75%). Simulation analysis is the least used
Owners consider shift or sharing risk with other analysis technique (25%).
parties as the least efficient preventive action.
The contractors’ perspective is same as owners’
perspective as the most effective method considered

Preventive Actions

Share or transfer risk to/with other

Use quantiative risk analysis methods for correct time


estimate

Plan alternative methods as stand by

Adjust for the bias risk premium to time estimation

Refer to present and past projects for accurate idea

Produce a proper schedule by getting updated project


information
Depend on subjective judgement to produce a proper
program

0 10 20 30 40 50 60 70 80 90

Owner Contractor

Fig. 2: Risk preventive actions adopted by owners

86
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

Mitigative Methods

Change the construction technique

Increase number of labour and/or equipment

Change the sequence of work by overlapping activities

Coordinate closely with subcontractors

Increase the working hours

Close supervision to subordinates for minimizing abortive


work
0 10 20 30 40 50 60 70 80 90 100

Owner Contractor

Fig. 3: Risk mitigative methods adopted by contractors and owners

Analysis Techniques

Simulation analysis using simulator computer packages

Sensitivity analysis

Expert systems

Probability analysis

Comparing analysis

Direct judgement using experience and personal skills

0 10 20 30 40 50 60 70 80 90 100

Owner Contractor
-
Fig. 4: Risk analysis techniques adopted by contractors and owners

5. Conclusions  Financial failures should be avoided by the


contractors and more steps should be taken in
Construction project typically fail to deliver on order to ensure any kind of financial failure.
time or affected by price overruns owing to  Both owners and contractors to be more aware
improper, un-systematized risk management. The about safety techniques.
causes of failure (risk factors) are often internal to  Contractors should thrive to share different risks
the project or are often embedded within the that they face.
external surroundings a number of these could also  Contractors should hire risk managers so
be governable et al could also be uncontrollable. The computerized approaches can utilized by the
various kinds of risks need different strategies for contractors instead of largely making use of
mitigation. The uncontrollable ones cannot be direct judgment.
eliminated and only adequate responses to dilute  The personnel may be trained so that
their effect can be developed. The controllable ones management principles can be suitably applied.
can be nipped in the bud and should be prevented at  Tenders may be awarded to those contractors
supply. The interior ones have their origin among that estimate the costs accurately.
the organization and wish effective management of  Continuous training programs may be held to
internal resources to forestall them, whereas the enhance the risk management process.
external ones want continual scanning and  The design products need to be of highest quality
statement of the surroundings. as it is one of the most significant phases.
Additionally, some risks have larger impact on  Exchange rate variation to be thought of as a risk
the project and area unit essential to its timely issue by owners and donors and that they ought
completion, while some do not need attention as to provide a compensation mechanism if there's
they have negligible importance. Following are any hurt because of this risk
recommendations for contractors and owners for  Contractors and owners may concentrate on site
assessing risk before starting construction activities safety techniques.
and during construction activities:  A satisfactory level of communication is must to
be maintained by both the owners and the
 Contracting companies can add risk premium in contractors.
their quotations.
87
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

 Proper Documentation works to be used widely Lisbon, Portugal. International Journal of Project
in construction Management, 22(1), 63–73.
 Contractors and owners should save digital Dey, P. K. (2002). Project risk management: A combined
record of finished projects. It will be a source of analytic hierarchy process and decision tree
information for upcoming projects approach. Cost Engineering, 44(3), 13–27.
 Contractors must provide the professional staff
Dey, P. K. (2006). Integrated project evaluation and
i.e., risk manager to manage the risk in projects, selection using multiple-attribute decision-making
that in turn causes significant reduction in the technique. International Journal of Production
price and time of completion. Economics, 103(1), 90–103.
Dey, P. K. (2010). Managing project risk using combined
References analytic hierarchy process and risk map. Applied Soft
Computing, 10(4), 990–1000.
Abas, M., Khattak, S., Akhtar, R., Ahmad, I., Ullah, M., & Haq,
I. (2016). Identification of Factors Affecting Cost El, M. S. B. A. A., El Nawawy, O. A. M., & Abdel-Alim, A. M.
Performance of Construction Projects. University of (2017). Identification and assessment of risk factors
Engineering and Technology Taxila. Technical affecting construction projects. HBRC journal, 13(2),
Journal, 21(1), 72. 202–216.
Abdelgawad, M., & Fayek, A. R. (2010). Fuzzy reliability El-Sayegh, S. M. (2008). Risk assessment and allocation in
analyzer: Quantitative assessment of risk events in the UAE construction industry. International journal
the construction industry using fuzzy fault-tree of project management, 26(4), 431–438.
analysis. Journal of Construction Engineering and
Enshassi, A., & Abu Mosa, J. (2008). Risk management in
Management, 137(4), 294–302.
building projects: Owners’ perspective. Risk
Adeleke, A., Bahaudin, A., Kamaruddeen, A., Bamgbade, J., management in building projects: Owners’
Salimon, M. G., Khan, M. W. A., & Sorooshian, S. perspective, 16(1).
(2018). The influence of organizational external
Hallaq, A., & Raouf, K. A. (2003). Causes of contractor’s
factors on construction risk management among
failure in Gaza Strip. Causes of contractor’s failure in
Nigerian construction companies. Safety and health
gaza strip.
at work, 9(1), 115–124.
Hopkinson, M. (2017). The project risk maturity model:
Ahmed, S. M., Ahmad, R., & Darshi De Saram, D. (1999).
Measuring and improving risk management
Risk management trends in the Hong Kong
capability. Routledge.
construction industry: A comparison of contractors
and owners perceptions. Engineering, Construction Hwang, B.-G., Zhao, X., & Toh, L. P. (2014). Risk
and Architectural Management, 6(3), 225–234. management in small construction projects in
Singapore: Status, barriers and impact. International
Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati.
journal of project management, 32(1), 116–124.
(2007). The significant factors causing delay of
building construction projects in Malaysia. Ibn-Homaid, N. T., Eldosouky, A. I., & Al-Ghamdi, M. A.
Engineering, Construction and Architectural (2011). Change orders in Saudi linear construction
Management, 14(2), 192–206. projects. Emirates Journal for Engineering Research,
16(1), 33–42.
Breslow, N. (1970). A generalized Kruskal-Wallis test for
comparing K samples subject to unequal patterns of Iqbal, S., Choudhry, R. M., Holschemacher, K., Ali, A., &
censorship. Biometrika, 57(3), 579–594. Tamošaitienė, J. (2015). Risk management in
construction projects. Technological and Economic
Chang, T., Hwang, B.-G., Deng, X., & Zhao, X. (2018).
Development of Economy, 21(1), 65–78.
Identifying political risk management strategies in
international construction projects. Advances in Civil Kangari, R., & Riggs, L. S. (1989). Construction risk
Engineering, 2018. assessment by linguistics. IEEE transactions on
engineering management, 36(2), 126–131.
Cho, H.-N., Choi, H.-H., & Kim, Y.-B. (2002). A risk
assessment methodology for incorporating Kartam, N. A., & Kartam, S. A. (2001). Risk and its
uncertainties using fuzzy concepts. Reliability management in the Kuwaiti construction industry: A
Engineering & System Safety, 78(2), 173–183. contractors’ perspective. International journal of
project management, 19(6), 325–335.
Choudhry, R. M., Aslam, M. A., Hinze, J. W., & Arain, F. M.
(2014). Cost and schedule risk analysis of bridge Khan, A. H. (2013). The Contractors Perception of Risk
construction in Pakistan: Establishing risk guidelines. Management in Pakistan. Pakistan Acedmy of
Journal of Construction Engineering and Sciences, 50, 189–200.
Management, 140(7), 04014020.
Khattak, S., Abas, M., Maqsood, S., Omair, M., Nawaz, R., &
Cochran, W. G. (1977). Sampling techniques-3. Haq, I. U. (2015). Identification and Evaluation of
Risk Factors Affecting the Supply Chain Environment
Dawood, N. (1998). Estimating project and activity
of Construction Industry of Khyber Pukhtunkhwa
duration: A risk management approach using
(KPK). University of Engineering and Technology
network analysis. Construction Management &
(UET) Taxila, Pakistan, 20(6).
Economics, 16(1), 41–48.
Koushki, P., Al‐Rashid, K., & Kartam, N. (2005). Delays and
De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T.
cost increases in the construction of private
(2004). Risk management in the Lusoponte
residential projects in Kuwait. Construction
concession—a case study of the two bridges in
Management and Economics, 23(3), 285–294.
88
Khattak et al / WALIA, 35(1) 2019, Pages: 77-89

Le-Hoai, L., Dai Lee, Y., & Lee, J. Y. (2008). Delay and cost Sharma, S. K., & Swain, N. (2011). Risk management in
overruns in Vietnam large construction projects: A construction projects. Asia Pacific Business Review,
comparison with other selected countries. KSCE 7(3), 107–120.
journal of civil engineering, 12(6), 367–377.
Shen, L. Y. (1997). Project risk management in Hong Kong.
Liu, J., Zhao, X., & Yan, P. (2016). Risk paths in international International journal of project management, 15(2),
construction projects: Case study from Chinese 101–105.
contractors. Journal of Construction Engineering and
Šukys, R., Čyras, P., & Šakėnaitė, J. (2011). Economical loss
Management, 142(6), 05016002.
due to non-compliance with requirements for
Mhatre, T. N., Thakkar, J., & Maiti, J. (2017). Modelling personnel safety and health in Lithuanian
critical risk factors for Indian construction project construction sector. Journal of Civil Engineering and
using interpretive ranking process (IRP) and system Management, 17(2), 168–176.
dynamics (SD). International Journal of Quality &
Szymański, P. (2017). Risk management in construction
Reliability Management, 34(9), 1451–1473.
projects. Procedia engineering, 208, 174–182.
Mubin, S., & Mubin, G. (2016). Risk analysis for
Tüysüz, F., & Kahraman, C. (2006). Project risk evaluation
construction and operation of gas pipeline projects in
using a fuzzy analytic hierarchy process: An
Pakistan. Pakistan Journal of Engineering and
application to information technology projects.
Applied Sciences.
International Journal of Intelligent Systems, 21(6),
Nasir, D., McCabe, B., & Hartono, L. (2003). Evaluating risk 559–584.
in construction–schedule model (ERIC–S):
Wang, W.-C., Liu, J.-J., & Chou, S.-C. (2006). Simulation-
Construction schedule risk model. Journal of
based safety evaluation model integrated with
construction engineering and management, 129(5),
network schedule. Automation in construction,
518–527.
15(3), 341–354.
Nawaz, A., Waqar, A., Shah, S. A. R., Sajid, M., & Khalid, M. I.
White, D. (1995). Application of systems thinking to risk
(2019). An Innovative Framework for Risk
management: A review of the literature. Management
Management in Construction Projects in Developing
Decision, 33(10), 35–45.
Countries: Evidence from Pakistan. Risks, 7(1), 24.
Wu, Z., Nisar, T., Kapletia, D., & Prabhakar, G. (2017). Risk
Netemeyer, R. G., Bearden, W. O., & Sharma, S. (2003).
factors for project success in the Chinese
Scaling procedures: Issues and applications. Sage
construction industry. Journal of manufacturing
Publications.
technology management, 28(7), 850–866.
Paslawski, J. (2008). Flexibility approach in construction
Yang, R. J., Zou, P. X., & Wang, J. (2016). Modelling
process engineering. Technological and Economic
Development of Economy, 14(4), 518–530. stakeholder-associated risk networks in green
building projects. International journal of project
Paslawski, J. (2013). Hybrid flexible approach for Six Sigma management, 34(1), 66–81.
implementation in constructional SME. Journal of
Zafar, I., Yousaf, T., & Ahmed, S. (2016). Evaluation of risk
Civil Engineering and Management, 19(5), 718–727.
factors causing cost overrun in road projects in
Perry, J., & Hayes, R. (1985). Risk and its management in terrorism affected areas Pakistan–a case study. KSCE
construction projects. Proceedings of the Institution Journal of Civil Engineering, 20(5), 1613–1620.
of Civil Engineers, 78(3), 499–521.
Zeng, J., An, M., & Smith, N. J. (2007). Application of a fuzzy
Qazi, A., Quigley, J., Dickson, A., & Kirytopoulos, K. (2016). based decision making methodology to construction
Project Complexity and Risk Management project risk assessment. International journal of
(ProCRiM): Towards modelling project complexity project management, 25(6), 589–600.
driven risk paths in construction projects.
Zhao, X., Hwang, B.-G., & Low, S. P. (2013). Developing
International Journal of Project Management, 34(7),
fuzzy enterprise risk management maturity model
1183–1198.
for construction firms. Journal of Construction
Rooshdi, R. R. R. M., Ab Rahman, N., Baki, N. Z. U., Majid, M. Engineering and Management, 139(9), 1179–1189.
Z. A., & Ismail, F. (2014). An evaluation of sustainable
Zhi, H. (1995). Risk management for overseas construction
design and construction criteria for green highway.
projects. International journal of project
Procedia Environmental Sciences, 20, 180–186.
management, 13(4), 231–237.
Royston, J. (1983). Some techniques for assessing
Zolfagharian, S., Nourbakhsh, M., Irizarry, J., Ressang, A., &
multivarate normality based on the Shapiro‐Wilk W.
Gheisari, M. (2012). Environmental impacts
Journal of the Royal Statistical Society: Series C
assessment on construction sites (Vol. 2012, pp. 1750–
(Applied Statistics), 32(2), 121–133.
1759). Presented at the Construction Research
Schieg, M. (2007). Post‐mortem analysis on the analysis Congress.
and evaluation of risks in construction project
management. Journal of business Economics and
management, 8(2), 145–153.

89

Potrebbero piacerti anche