TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.

TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 1 of 8

METHOD STATEMENT FOR RECTIFICATION FOR MEP


CHASING AT BLOCK WALLS

PROJECT : (Replace with the project’s name, at location , city name)

CLIENT : (Replace with the client’s name)

MASTER DEVELOPER : (Replace with the master developer’s name)

PMC : (Replace with the PMC’s name)

LEAD CONSULTANT : (Replace with the lead consultant’s name)

SUB-CONSULTANT : (Replace with the sub-consultant’s name)

MAIN CONTRACTOR : (Replace with the main contractor’s name)

SUB-CONTRACTOR : (Replace with the sub-contractor’s name)

TABLE OF CONTENTS
1. REVISION RECORD..............................................................................................................................3
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 2 of 8
2. PURPOSE................................................................................................................................................4
3. SCOPE OF WORKS...............................................................................................................................4
4. REFERENCES........................................................................................................................................4
4.1. Contract documents...........................................................................................................................4
4.2. Contractors Submittal........................................................................................................................4
5. DEFINITIONS / ABBREVIATIONS.......................................................................................................4
5.1. Definition.............................................................................................................................................4
5.2. Abbreviations......................................................................................................................................5
6. RESPONSIBILITIES...............................................................................................................................5
7. EQUIPMENTS/ TOOLS/ MANPOWER................................................................................................5
7.1. Equipments / Tools.............................................................................................................................5
7.2. List of Manpower................................................................................................................................6
7.3. List of Materials..................................................................................................................................6
8. PROCEDURE..........................................................................................................................................6
8.1. Demolition of the block at the base of 100 mm block wall due to installation of double
switch boxes back to back............................................................................................................................6
8.2. Chasing of block wall from one side with width of chasing not more than 100 mm. ..............7
8.3. Longitudinal Chasing of block wall from both sides.....................................................................7
8.4. Chasing at the AAC block.................................................................................................................8
8.5. Chasing at the concrete structural elements.................................................................................8
9. HEALTH, SAFETY AND ENVIRONMENT...........................................................................................9
10. ATTACHMENTS..................................................................................................................................9
10.1. Inspection Checklists....................................................................................................................9
10.2. Inspection Test Plan......................................................................................................................9
10.3. Risk Assessment............................................................................................................................9
10.4. Technical Data sheet (TDS).........................................................................................................9

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 3 of 8

0 First issue

Signature field
Revision
Revision
Number 0
Date
Prepared by Checked by

Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor

Approved
By Project
Manager

2. PURPOSE
The purpose of this method statement is to define the procedure for the sequence of Rectification for MEP chasing at
Block walls considering all safety and quality requirements.
3. SCOPE OF WORKS
The scope of this method statement is to rectify the chasing done for the MEP services. All the situations caused by
chasing for MEP services is grouped in to five case and a solution for each case to reinstate the block wall after getting
the MEP clearance and approval for the embedded conduits, boxes & pipes and prior to the commencement of the
plaster work in accordance with the contract drawings and specification.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 4 of 8
4. REFERENCES
4.1. Contract documents
1. Project Specification :- Division 4, Section 042200
2. Contract Drawings :-
4.2. Contractors Submittal
3. Project Quality Plan :-
4. Project Safety Plan :-
5. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1 Cement
2 Sand
3 Block work accessories
4 Plaster accessories
5 Bonding agent for Concrete surfaces
6 Plasticizer for cement mortar
6. Shop Drawings approvals
Sr. No. Description Shop Dwg. No. Rev No. Date Remarks
1
2
5. DEFINITIONS / ABBREVIATIONS
5.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
5.2. Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT - Material Submittal
8. MEP - Mechanical Electrical Plumbing
9. MET - Method Statement
10. MIR - Material Inspection Request
11. MSDS - Material Safety Data Sheet
12. PPE -Personal Protective Equipment
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 5 of 8
13. PQP -Project Quality Plan
14. PTW -Permit To Work ( Working at Height or enclosed spaces)
15. RA -Hazard Identification and Risk Assessment
16. RFIA - Request for Inspection and Approval
17. SPD - Shop Drawing
18. TBM - Temporary Bench Mark
6. RESPONSIBILITIES
1. The Construction Manager is overall responsible for the implementation of the method statement, to ensure that
the team of Engineers and foremen are aware of this MS and, to ensure that all resources (labour, material and
equipment) are available to carry out the work as planned.
2. The Project Engineer/ Site Engineer are responsible to carry out the work as per the approved MS. He is also
responsible to ensure adequate equipment for mobilization works are in place prior to the starting of work.
3. QA/QC Engineer is responsible to ensure work has been done as per the specification and drawings, inspections
are done as per Quality Control Procedure and the Inspection and Test plan, and all work are offered to
client/consultant for inspection.
4. The Safety Engineer is responsible to ensure that all Safety precautions are in place, and that all personnel on site
are using the required Personal Protective Equipment (helmet, gloves, shoes, coveralls, etc.). He must also ensure
that all relevant permissions are available for the works.

7. EQUIPMENTS/ TOOLS/ MANPOWER


7.1. Equipment’s / Tools
1. Mechanical mixer machine
2. Chipping hammers
3. Masonry tools
4. Cleaning tools
5. Wheel barrow

7.2. List of Manpower


1. Project Manager
2. Safety Engineer/ Officer
3. Construction Manager
4. Foremen / Work Supervisors
5. Site Engineer
6. Skilled and unskilled labourers
7. QA/ QC Engineer/ Inspector

7.3. List of Materials


1. Concrete mix (C30/10)
2. Bonding agent PVA LATEX RIPRESA
3. Repair material, CONREP 311 MC

8. PROCEDURE
1. Clearance for the MEP Installation
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 6 of 8
2. Prior to start the rectification of the MEP chasing at the block wall, a clearance shall be obtained from the MEP
engineer that the installation has been completed properly, inspected and found acceptable.
3. Cases of concern
4. Based on the joint investigation done by all parties at the site, certain cases have been observed and need to be
rectified as follow:

8.1. Demolition of the block at the base of 100 mm block wall due to installation
of double switch boxes back to back.

For this case, the following procedure will be followed:


1. Shutter will be fixed at both sides of the wall, leaving a chute at the top.
2. Approved flow able concrete mix (C30/10), as per the submittal number above will be cast to fill the total void.
3. Approved metal lath will be fixed at the junction between the concrete & block as per the approved method
statement.

8.2. Chasing of block wall from one side with width of chasing not more than
100 mm.

For this case, the following procedure will be followed:


1. Cement sand mortar with ratio of 1 part cement to 4 parts sand will be mixed with water and applied at the chasing.
2. Approved metal lath will be fixed at the mortar as per the approved method statement of plaster.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 7 of 8
8.3. Longitudinal Chasing of block wall from both sides.

For this case, the following procedure will be followed:


1. Shutter will be fixed at both sides of the wall, leaving a chute at the top.
2. Approved flow able concrete mix will be cast to fill the total voids.
3. Approved metal lath will be fixed at the junction between the concrete & block as per the approved method
statement of plaster.

8.4. Chasing at the AAC block

For that case and as agreed earlier based on the AAC block supplier recommendations, the following procedure will be
followed:
1. Cement sand mortar with ratio of 1 part cement to 5 parts sand will be mixed with approved bonding agent of 10-15
% of water and applied at the chasing.
2. Approved metal lath will be fixed at the mortar as per the approved method statement.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-042200-MET-DoR-
Project Name) (Rev No.) 005
METHOD STATEMENT Issue Date 02 October 2013
Method statement for rectification for MEP chasing at Rev. Date NA
block walls Pages 8 of 8
8.5. Chasing at the concrete structural elements.

For this case and as agreed earlier via our response to certain NCR’s the following procedure will be followed:
1. The filled mortar will be removed to check the status of the steel reinforcement.
2. Prior to the repair material application, the chased area will be cleaned properly and dampen by water.
3. Approved bonding agent PVA LATEX RIPRESA as per the approval as above will be applied. Manufacturer
instructions will be strictly followed.
4. Approved repair material, Conrep 311 mc non shrink micro concrete for grouting and general void filling, will be
mixed, prepared and applied as per the manufacturer instructions.
5. RFIA will be raised to the consultant to inspect the methodology of rectification.

9. HEALTH, SAFETY AND ENVIRONMENT


10. ATTACHMENTS
10.1. Inspection Checklists
10.2. Inspection Test Plan
10.3. Risk Assessment
10.4. Technical Data sheet (TDS)
1. Data sheet for approved bonding agent PVA LATEX REPRESA
2. Data sheet for approved repair material CONREP 311 MC