DAILY DRILLING REPORT

CLIENT : PT. Lanay Jaya Group RIG NO. : RG-01


PROJECT : Pre-Production Drilling RIG TYPE : Jacro-175
LOCATION : Dingin Muara Lawa SIZE : AW
DAY : Selasa
DATE : 1 Oktober 2019

SHIFT Day Night

HOLE DRILLING
ID Open Hole
Easting Northing RL
Plan Actual From (m) To (m) Total (m) From (m)
DPLJ_A13 DHLJ_A13 369309 9939142 66 m 0.00 30.00 30.00

CONSUMABLES ACTIVITY
Qty
Item Time Hole Description Remark
PVC
General Go to site
Foam Work Drilling OH, EOH
Cement General Geophysical Logging
Liquid Polymer (Liter) General Down Rig
Fuel - Solar (liter) General Back to mess
Fuel - Bensin (Liter)
Engine Oil (Liter)
Hydraulic Oil (Liter)
PERSONIL Hours
Driller : P. Pian
Mechanic : idir
Crew : atonk ( korlap )
pian
rudy
P. ambo
belanda

Total Manpower Hour

Total Open Hole : 30.00 Comment :


Total Coring : 0.00
Total Depth Drilled : 30.00
Total Depth Logging :
Moving Distance : 150 m

Signatures
Sample ID :
Driller : P. Pian

Wellsite : Ricardus Guido Aresso


WORK Drilling (OH/Coring)
GENERAL Traveling (Moving/Demob)

Setup/Down Rig
Pull Up/Down Rod
Hole Condition
Reaming/Flushing
Geophisical Logging
STANDING Rest & Meal / Shifting
Water Problem
Waiting (Rain/Order/Geos)
BREAKDOWRepair / Service
Trouble Machine/Spere part

DRILLING
Coring
To (m) Cored (m) Recovered (m) Rec (%)

TY HOURS
Remark From To AGG

7:00 8:00 1.000


8:00 14:00 6.000
14:00 15:00 1.000
15:00 16:00 1.000
16:00 17:00 1.000
10.000
DAILY DRILLING REPORT

CLIENT : PT. Lanay Jaya Group RIG NO. : RG-01


PROJECT : Pre-Production Drilling RIG TYPE : Jacro-175
LOCATION : Dingin Muara Lawa SIZE : AW
DAY : Rabu
DATE : 2 Oktober 2019

SHIFT Day Night

HOLE DRILLING
ID Open Hole
Easting Northing RL
Plan Actual From (m) To (m) Total (m) From (m)
DPLJ_A14 DHLJ_A14 369206 9939115 70 m 0.00 2.65 2.65 2.65
4.15
4.65 20.45 15.80

CONSUMABLES ACTIVITY
Qty
Item Time Hole Description Remark
PVC
General Go to site
Foam General Moving Rig to DPLJ_A14
Cement General Set up Rig
Liquid Polymer (Liter) Work Drilling OH, Continue
Fuel - Solar (liter) Work Drilling Coring, Run 1
Fuel - Bensin (Liter) Work Drilling Coring, Run 2
Engine Oil (Liter) Work Drilling OH, Continue
Hydraulic Oil (Liter) General Reaming/Flushing
PERSONIL Hours General Back to mess
Driller : P. Pian
Mechanic : idir
Crew : atonk ( korlap )
pian
rudy
P. ambo
belanda

Total Manpower Hour

Total Open Hole : 18.45 Comment :


Total Coring : 2.00
Total Depth Drilled : 20.45
Total Depth Logging :
Moving Distance : 150 m

Signatures
Sample ID :
Driller : P. Pian

Wellsite : Ricardus Guido Aresso


WORK Drilling (OH/Coring)
GENERAL Traveling (Moving/Demob)

Setup/Down Rig
Pull Up/Down Rod
Hole Condition
Reaming/Flushing
Geophisical Logging
STANDING Rest & Meal / Shifting
Water Problem
Waiting (Rain/Order/Geos)
BREAKDOWRepair / Service
Trouble Machine/Spere part

DRILLING
Coring
To (m) Cored (m) Recovered (m) Rec (%)
4.15 1.50 1.50 100%
4.65 0.50 0.50 100%

TY HOURS
Remark From To AGG

7:00 8:00 1.000


g to DPLJ_A14 8:00 10:00 2.000
10:00 11:00 1.000
11:00 12:00 1.000
12:00 13:00 1.000
13:00 14:00 1.000
14:00 16:00 2.000
16:00 18:00 2.000
18:00 19:00 1.000
12.000
DAILY DRILLING REPORT

CLIENT : PT. Lanay Jaya Group RIG NO. : RG-01


PROJECT : Pre-Production Drilling RIG TYPE : Jacro-175
LOCATION : Dingin Muara Lawa SIZE : AW
DAY : Kamis
DATE : 3 Oktober 2019

SHIFT Day Night

HOLE DRILLING
ID Open Hole
Easting Northing RL
Plan Actual From (m) To (m) Total (m) From (m)
DPLJ_A14 DHLJ_A14 369206 9939115 70 m 20.45
21.95 45.00 23.05

CONSUMABLES ACTIVITY
Qty
Item Time Hole Description Remark
PVC
General Go to site
Foam General Continue, Reaming/Flushing
Cement Work Drilling Coring, Run 3
Liquid Polymer (Liter) Work Drilling OH, EOH
Fuel - Solar (liter) General Geophysical Logging
Fuel - Bensin (Liter) General Back to mess
Engine Oil (Liter)
Hydraulic Oil (Liter)
PERSONIL Hours
Driller : P. Pian
Mechanic : idir
Crew : atonk ( korlap )
pian
rudy
P. ambo
belanda

Total Manpower Hour

Total Open Hole : 23.05 Comment :


Total Coring : 1.50
Total Depth Drilled : 24.55
Total Depth Logging :
Moving Distance : 150 m

Signatures
Sample ID :
Driller : P. Pian

Wellsite : Ricardus Guido Aresso


WORK Drilling (OH/Coring)
GENERAL Traveling (Moving/Demob)

Setup/Down Rig
Pull Up/Down Rod
Hole Condition
Reaming/Flushing
Geophisical Logging
STANDING Rest & Meal / Shifting
Water Problem
Waiting (Rain/Order/Geos)
BREAKDOWRepair / Service
Trouble Machine/Spere part

DRILLING
Coring
To (m) Cored (m) Recovered (m) Rec (%)
21.95 1.50 1.50 100%

TY HOURS
Remark From To AGG

7:00 8:00 1.000


Reaming/Flushing 8:00 10:00 2.000
10:00 12:00 2.000
12:00 16:00 4.000
16:00 18:00 2.000
18:00 19:00 1.000
12.000
DAILY DRILLING REPORT

CLIENT : PT. Lanay Jaya Group RIG NO. : RG-01


PROJECT : Pre-Production Drilling RIG TYPE : Jacro-175
LOCATION : Dingin Muara Lawa SIZE : AW
DAY : Jumad
DATE : 4 Oktober 2019

SHIFT Day Night

HOLE DRILLING
ID Open Hole
Easting Northing RL
Plan Actual From (m) To (m) Total (m) From (m)
DPLJ_A15 DHLJ_A15 369193 9939039 66 m 0.00 4.50 4.50 4.50
5.30
6.80 25.00 18.20

CONSUMABLES ACTIVITY
Qty
Item Time Hole Description Remark
PVC
General Go to site
Foam General Moving Rig to DPLJ_A15
Cement General Set Up Rig
Liquid Polymer (Liter) Work Drilling OH, Continue
Fuel - Solar (liter) Work Drilling Coring, Run 1
Fuel - Bensin (Liter) Work Drilling Coring, Run 2
Engine Oil (Liter) Work Drilling OH, EOH
Hydraulic Oil (Liter) General Geophysical Logging
PERSONIL Hours General Back to mess
Driller : P. Pian
Mechanic : idir
Crew : atonk ( korlap )
pian
rudy
P. ambo
belanda

Total Manpower Hour

Total Open Hole : 22.70 Comment :


Total Coring : 2.30
Total Depth Drilled : 25.00
Total Depth Logging :
Moving Distance : 70 m

Signatures
Sample ID :
Driller : P. Pian

Wellsite : Ricardus Guido Aresso


WORK Drilling (OH/Coring)
GENERAL Traveling (Moving/Demob)

Setup/Down Rig
Pull Up/Down Rod
Hole Condition
Reaming/Flushing
Geophisical Logging
STANDING Rest & Meal / Shifting
Water Problem
Waiting (Rain/Order/Geos)
BREAKDOWRepair / Service
Trouble Machine/Spere part

DRILLING
Coring
To (m) Cored (m) Recovered (m) Rec (%)
5.30 0.80 0.80 100%
6.80 1.50 1.50 100%

TY HOURS
Remark From To AGG

7:00 8:00 1.000


g to DPLJ_A15 8:00 10:00 2.000
10:00 11:00 1.000
11:00 12:00 1.000
12:00 13:00 1.000
13:00 14:00 1.000
14:00 17:00 3.000
17:00 18:00 1.000
18:00 19:00 1.000
12.000
DAILY DRILLING REPORT

CLIENT : PT. Lanay Jaya Group RIG NO. : RG-01


PROJECT : Pre-Production Drilling RIG TYPE : Jacro-175
LOCATION : Dingin Muara Lawa SIZE : AW
DAY : Sabtu
DATE : 5 Oktober 2019

SHIFT Day Night

HOLE DRILLING
ID Open Hole
Easting Northing RL
Plan Actual From (m) To (m) Total (m) From (m)

CONSUMABLES ACTIVITY
Qty
Item Time Hole Description Remark
PVC
General Go to site
Foam General Down Rig
Cement General Demob Rig & Demob Logging
Liquid Polymer (Liter) General Back to mess
Fuel - Solar (liter)
Fuel - Bensin (Liter)
Engine Oil (Liter)
Hydraulic Oil (Liter)
PERSONIL Hours
Driller : P. Pian
Mechanic : idir
Crew : atonk ( korlap )
pian
rudy
P. ambo
belanda

Total Manpower Hour

Total Open Hole : 0.00 Comment :


Total Coring : 0.00
Total Depth Drilled : 0.00
Total Depth Logging :
Moving Distance : 1.330 m

Signatures
Sample ID :
Driller : P. Pian

Wellsite : Ricardus Guido Aresso


WORK Drilling (OH/Coring)
GENERAL Traveling (Moving/Demob)

Setup/Down Rig
Pull Up/Down Rod
Hole Condition
Reaming/Flushing
Geophisical Logging
STANDING Rest & Meal / Shifting
Water Problem
Waiting (Rain/Order/Geos)
BREAKDOWRepair / Service
Trouble Machine/Spere part

DRILLING
Coring
To (m) Cored (m) Recovered (m) Rec (%)

TY HOURS
Remark From To AGG

7:00 8:00 1.000


8:00 9:00 1.000
g & Demob Logging 9:00 17:00 8.000
17:00 18:00 1.000
11.000