Sei sulla pagina 1di 8

TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE

CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)


R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 2 CONTRACT QTY.: 7,094.89 TOTAL AMOUNT: 1,951,236.65


DESCRIPTION: Clearing and Grubbing UNIT PRICE: 275.02

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

Clearing and Grubbing 5,009.35 266.59 5,275.94 On-going

TOTAL 5,009.35 266.59 5,275.94

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)
TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE
CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)
R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 3 CONTRACT QTY.: 4,107.59 TOTAL AMOUNT: 1,320,508.03


DESCRIPTION: Canal Excavation UNIT PRICE: 321.48
(Common)

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

Canal Excavation (Common) 2,815.27 505.36 3,320.63 On-going

TOTAL 2,815.27 505.36 3,320.63

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)
TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE
CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)
R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 6 CONTRACT QTY.: 7,632.20 TOTAL AMOUNT: 2,095,954.76


DESCRIPTION: Embankment, Construction UNIT PRICE: 274.62
& Compaction (Overhaul=2kms.)

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

Embankment, Construction & Compaction 0.00 913.41 913.41 On-going


(Overhaul=2kms.)

TOTAL 0.00 913.41 913.41

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)
TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE
CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)
R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 7 CONTRACT QTY.: 3,321.91 TOTAL AMOUNT: 4,092,227.71


DESCRIPTION: Road Surfacing Materials UNIT PRICE: 1,231.89

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

Road Surfacing Materials 0.00 1,023.00 1,023.00 On-going

TOTAL 0.00 1,023.00 1,023.00

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)
TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE
CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)
R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 8.2 CONTRACT QTY.: 1,458.00 TOTAL AMOUNT: 7,787,732.04


DESCRIPTION: Concrete Canal Lining, UNIT PRICE: 5,341.38
170 kg/sq.cm

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

Concrete Canal Lining, 170 kg/sq. cm 577.61 320.18 897.79 On-going

TOTAL 577.61 320.18 897.79

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)
TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE
CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)
R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 9.1 CONTRACT QTY.: 4,060.00 TOTAL AMOUNT: 994,091.00


DESCRIPTION: CHB Canal Lining-6" UNIT PRICE: 244.85

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

CHB Canal Lining-6" 465.50 2,262.75 2,728.25 On-going

TOTAL 465.50 2,262.75 2,728.25

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)
TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE
CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)
R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 9.2 CONTRACT QTY.: 3,981.28 TOTAL AMOUNT: 936,516.49


DESCRIPTION: CHB Canal Lining-4" UNIT PRICE: 235.23

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

CHB Canal Lining-4" 2,899.52 146.77 3,046.29 On-going

TOTAL 2,899.52 146.77 3,046.29

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)
TWENTY SIXTEEN CONSTRUCTION AND GENERAL MERCHANDISE
CONSTRUCTION OF BONGABONG RIP CY2019 (PACKAGE 6)
R4B-MMR-BRIP6-29M-CY19-10

PROGRESS BILLING REPORT NO. SECOND PARTIAL BILLING


PERIOD COVERED: NOVEMBER 1, 2019 - JANUARY 31, 2020

SUMMARY OF ACCOMPLISHMENT

ITEM NO.: 10 CONTRACT QTY.: 89,131.12 TOTAL AMOUNT: 7,133,163.53


DESCRIPTION: Reinforcing Steel Bars, UNIT PRICE: 80.03
All sizes

QUANTITY ACCOMPLISHED
DESCRIPTION REMARKS
PREVIOUS THIS PERIOD TO DATE

Reinforcing Steel Bars, All sizes 38,411.03 38,437.31 76,848.34 On-going

TOTAL 38,411.03 38,437.31 76,848.34

CONTRACTOR: NATIONAL IRRIGATION ADMINISTRATION

SUBMITTED BY: INSPECTED BY:

PROJECT ENGINEER/PROJECT MANAGER PROJECT-IN-CHARGE(RIS)/


AUTHORIZED MANAGING OFFICER RESIDENT ENGINEER(SRIP)/
MANAGER, CONST. DIV. (PMO)

VERIFIED/CERTIFIED BY:

MANAGER, IMO/
MANAGER, ENGINEERING DIV.
(PMO/RIO)

Potrebbero piacerti anche