PROJECT: Two storey Apartment (Duplex)

LOCATION:Brgy. 4, P. herrera Batangas City

BAR CHART / S-CURVE


DAY 1-23 DAY 24-45 DAY 46-68 DAY 69-90

ITEM NO. DESCRIPTION DAYS AMOUNT ##########################################################################################

I. GENERAL REQUIREMENTS 11 255750


II. FORMWORKS 12 112750
III. EARTHWORKS 5 29056.5
IV. FOUNDATION 5 116217.5
V. COLUMN 13 169505
VI. SLABS 13 128760
VII BEAMS 13 331180
VIII MASONRY 34 496262.5
IX CARPENTRY 30 137025
X Paint Works 30 274050
XI DOORS & WIndows 9 204450
XII SANITARY WORKS AND WATER LINES 54 145000
XIII ELECTRICAL WORKS 54 145000
XIV Stairs and railings 18 0
XV Roofing works 17 80583.75
416890.5385 746453.3756 672567.0875 789679.2484
416890.5385 1163343.914 1835911.002 2625590.25
15.88 44.31 69.92 100.00

Direct Cost 2625590.25


OCM 7 % 183791.3175
Contractors Profit 10 % 262559.025
GRAND TOTAL 3071940.593

SAY P 3,000,000.00

Prepared by : Engr. Allen Robert M. Wagan


Civil Engineer
PRC No: 131332