ID Task WBS Critical Task Name Duration Start Finish 2016

Mode Feb Mar Apr May


1 1 Yes Project - 4 Storey 475 days Mon 07-03-16 Fri 29-12-17 P
Residential Building

15 1.3 Yes SUPERSTRUCTURE 126 days Thu 21-04-16 Thu 13-10-16

47 1.3.1.4 No 3rd Floor 21 days Tue 19-07-16 Tue 16-08-16

48 1.3.1.4.1 No Columns 11 days Tue 19-07-16 Tue 02-08-16

49 1.3.1.4.1.1 No Reinforcement
4 days Tue 19-07-16 Fri 22-07-16

50 1.3.1.4.1.2 No Shuttering 4 days Mon 25-07-16 Thu 28-07-16

51 1.3.1.4.1.3 No Casting 3 days Fri 29-07-16 Tue 02-08-16 C

52 1.3.1.4.2 No Slab 9 days Wed 03-08-16 Mon 15-08-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 1
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
53 1.3.1.4.2.1 No Shuttering 4 days Wed 03-08-16 Mon 08-08-16

54 1.3.1.4.2.2 No Reinforcement
4 days Tue 09-08-16 Fri 12-08-16

55 1.3.1.4.2.3 No Casting 1 day Mon 15-08-16 Mon 15-08-16

56 1.3.1.4.3 No Staircase 1 day Tue 16-08-16 Tue 16-08-16

57 1.3.1.5 No 4th Floor 21 days Wed 17-08-16 Wed 14-09-16

58 1.3.1.5.1 No Columns 11 days Wed 17-08-16 Wed 31-08-16

59 1.3.1.5.1.1 No Reinforcement
4 days Wed 17-08-16 Mon 22-08-16

60 1.3.1.5.1.2 No Shuttering 4 days Tue 23-08-16 Fri 26-08-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 2
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
61 1.3.1.5.1.3 No Casting 3 days Mon 29-08-16 Wed 31-08-16

62 1.3.1.5.2 No Slab 9 days Thu 01-09-16 Tue 13-09-16

63 1.3.1.5.2.1 No Shuttering 4 days Thu 01-09-16 Tue 06-09-16

64 1.3.1.5.2.2 No Reinforcement
4 days Wed 07-09-16 Mon 12-09-16

65 1.3.1.5.2.3 No Casting 1 day Tue 13-09-16 Tue 13-09-16

66 1.3.1.5.3 No Staircase 1 day Wed 14-09-16 Wed 14-09-16

67 1.3.1.6 No Terrace 21 days Thu 15-09-16 Thu 13-10-16

68 1.3.1.6.1 No Columns 11 days Thu 15-09-16 Thu 29-09-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 3
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
69 1.3.1.6.1.1 No Reinforcement
4 days Thu 15-09-16 Tue 20-09-16

70 1.3.1.6.1.2 No Shuttering 4 days Wed 21-09-16 Mon 26-09-16

71 1.3.1.6.1.3 No Casting 3 days Tue 27-09-16 Thu 29-09-16

72 1.3.1.6.2 No Slab 9 days Fri 30-09-16 Wed 12-10-16

73 1.3.1.6.2.1 No Shuttering 4 days Fri 30-09-16 Wed 05-10-16

74 1.3.1.6.2.2 No Reinforcement
4 days Thu 06-10-16 Tue 11-10-16

75 1.3.1.6.2.3 No Casting 1 day Wed 12-10-16 Wed 12-10-16

76 1.3.1.6.3 No Staircase 1 day Thu 13-10-16 Thu 13-10-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 4
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
84 1.3.3 No Internal Plastering 69 days Thu 28-07-16 Tue 01-11-16 I

85 1.3.3.1 No Ground Floor 2 days Thu 28-07-16 Fri 29-07-16

86 1.3.3.2 No 1st Floor 7 days Thu 18-08-16 Fri 26-08-16

87 1.3.3.3 No 2nd Floor 7 days Thu 08-09-16 Fri 16-09-16

88 1.3.3.4 No 3rd Floor 7 days Thu 29-09-16 Fri 07-10-16

89 1.3.3.5 No 4th Floor 7 days Thu 20-10-16 Fri 28-10-16

90 1.3.3.6 No Terrace 2 days Mon 31-10-16 Tue 01-11-16

96 1.3.5 No Floors & Dado/ 70 days Mon 01-08-16 Fri 04-11-16


Skirting

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 5
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
97 1.3.5.1 No Ground Floor 3 days Mon 01-08-16 Wed 03-08-16

98 1.3.5.2 No 1st Floor 3 days Thu 04-08-16 Mon 08-08-16

99 1.3.5.3 No 2nd Floor 3 days Tue 09-08-16 Thu 11-08-16

100 1.3.5.4 No 3rd Floor 3 days Fri 12-08-16 Tue 16-08-16

101 1.3.5.5 No 4th Floor 3 days Wed 17-08-16 Fri 19-08-16

102 1.3.5.6 No Terrace 3 days Wed 02-11-16 Fri 04-11-16

103 1.3.6 No Doors & Windows 68 days Thu 04-08-16 Mon 07-11-16

104 1.3.6.1 No Ground Floor 1 day Thu 04-08-16 Thu 04-08-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 6
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
105 1.3.6.2 No 1st Floor 2 days Fri 05-08-16 Mon 08-08-16

106 1.3.6.3 No 2nd Floor 2 days Tue 09-08-16 Wed 10-08-16

107 1.3.6.4 No 3rd Floor 2 days Thu 11-08-16 Fri 12-08-16

108 1.3.6.5 No 4th Floor 2 days Mon 15-08-16 Tue 16-08-16

109 1.3.6.6 No Terrace 1 day Mon 07-11-16 Mon 07-11-16

110 1.3.7 No Electrical Fixtures 68 days Fri 05-08-16 Tue 08-11-16

111 1.3.7.1 No Ground Floor 2 days Fri 05-08-16 Mon 08-08-16

112 1.3.7.2 No 1st Floor 2 days Tue 09-08-16 Wed 10-08-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 7
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
113 1.3.7.3 No 2nd Floor 2 days Thu 11-08-16 Fri 12-08-16

114 1.3.7.4 No 3rd Floor 2 days Mon 15-08-16 Tue 16-08-16

115 1.3.7.5 No 4th Floor 2 days Wed 17-08-16 Thu 18-08-16

116 1.3.7.6 No Terrace 1 day Tue 08-11-16 Tue 08-11-16

117 1.3.8 No Plumbing Fixtures 69 days Fri 05-08-16 Wed 09-11-16

118 1.3.8.1 No Ground Floor 2 days Fri 05-08-16 Mon 08-08-16

119 1.3.8.2 No 1st Floor 2 days Tue 09-08-16 Wed 10-08-16

120 1.3.8.3 No 2nd Floor 2 days Thu 11-08-16 Fri 12-08-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 8
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
121 1.3.8.4 No 3rd Floor 2 days Mon 15-08-16 Tue 16-08-16

122 1.3.8.5 No 4th Floor 2 days Wed 17-08-16 Thu 18-08-16

123 1.3.8.6 No Terrace 1 day Wed 09-11-16 Wed 09-11-16

124 1.3.9 No Internal Paint 68 days Tue 09-08-16 Thu 10-11-16

125 1.3.9.1 No Ground Floor 1 day Tue 09-08-16 Tue 09-08-16

126 1.3.9.2 No 1st Floor 7 days Wed 10-08-16 Thu 18-08-16

127 1.3.9.3 No 2nd Floor 7 days Fri 19-08-16 Mon 29-08-16

128 1.3.9.4 No 3rd Floor 7 days Tue 30-08-16 Wed 07-09-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 9
ID Task WBS Critical Task Name Duration Start Finish 2016
Mode Feb Mar Apr May
129 1.3.9.5 No 4th Floor 7 days Thu 08-09-16 Fri 16-09-16

130 1.3.9.6 No Terrace 1 day Thu 10-11-16 Thu 10-11-16

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 10
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
29-12
Project - 4 Storey Residential Buildin

SUPERSTRUCTURE

3rd Floor

Columns

Reinforcement

Shuttering

Casting

Slab

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 11
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Shuttering

Reinforcement

Casting

Staircase

4th Floor

Columns

Reinforcement

Shuttering

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 12
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Casting

Slab

Shuttering

Reinforcement

Casting

Staircase

Terrace

Columns

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 13
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Reinforcement

Shuttering

Casting

Slab

Shuttering

Reinforcement

Casting

Staircase

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 14
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Internal Plastering

Ground Floor

1st Floor

2nd Floor

3rd Floor

4th Floor

Terrace

Floors & Dado/ Skirting

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 15
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Ground Floor

1st Floor

2nd Floor

3rd Floor

4th Floor

Terrace

Doors & Windows

Ground Floor

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 16
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1st Floor

2nd Floor

3rd Floor

4th Floor

Terrace

Electrical Fixtures

Ground Floor

1st Floor

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 17
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2nd Floor

3rd Floor

4th Floor

Terrace

Plumbing Fixtures

Ground Floor

1st Floor

2nd Floor

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 18
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
3rd Floor

4th Floor

Terrace

Internal Paint

Ground Floor

1st Floor

2nd Floor

3rd Floor

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress

Page 19
2017 2018
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
4th Floor

Terrace

Free-total slack Inactive Task Finish-only

ls-lf Inactive Milestone External Tasks

es-ef Inactive Summary External Milestone

Project: Project 4 Storey.mpp Task Manual Task Deadline


Date: Sat 02-04-16 Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Summary Manual Summary Progress

Project Summary Start-only Manual Progress