Walter Johnson High School

Stadium Turf Field Replacement Project


February 2020
UPDATE

Schedule

Contractor mobilized on 1/20/20.

The following schedule is a general outline of planned activities.

Event Number of Days1


Mobilization 2 days
Removal of Infill and Turf 10 days2
Clean drains rework base surface 3 days
Install Pad, Turf and inlay work 20 days
Install Infill 3 days
Demobilization and cleaning 1 days
Testing 1 day
1
Activities can be affected by weather events and may adjust accordingly.
2
Frozen ground conditions have slowed down the removal of infill.

Removal and Recycling of the artificial turf field

Infill: Removed infill inclusive of crumb rubber and sand will be shipped to Washington Academy, East
Machias, Maine, for use in their artificial turf installation. The contractor will provide certification of the
reuse of the infill extracted.

Synthetic turf carpet: Target Technologies International Inc. (TTII) has confirmed that the product will be
shipped to Poly-Pacific Inc., located in Malaysia. TTII will provide the following information related to
Poly-Pacific Inc.:

1. Name and site location


2. Serial number of container
3. Date containers arrive and depart from site
4. Date of arrival at factory in Malaysia
5. Date of final processing into post-consumer products

Poly-Pacific Inc. will recycle the artificial turf carpet into post-consumer products such as plastic lumber,
irrigation pipes and fence posts. The time frame once the product is received can take up to 4 months
for certification to arrive.