Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Contract Details
PO No:- 4101903003
PO issue date:- 25th Sep 2019
Po Version No:- 0
Scope of value:- 229,320,006.72 INR (excl. GST)
270,597,607.92 INR (incl. GST)
CONTRACTUAL MILESTONE
Actual work
**Note: All planned date for U # 1 as per contract (NOA+10 month) and +4 month for Unit #2
Summary
EHS SUMMARY
PROGRESS
PHOTOGRAPHIC REPORT
3 MONTHS LOOK AHEAD SCHEDULE
MAN POWER STATUS
T&P STATUS
EHS SUMMARY
1 Observation 0 13 0 0 0
Sl. No. DISCIPLINE TILL LAST MONTH DURING THIS MONTH CUMULATIVE
1 Safe man hours 5960 13950 19910
2 Pep / Tool box talks 0 30 30
3 Induction training 19 22 41
4 Incident / Accident 0 0 0
5 Minor First Aid 0 0 0
6 Major Accidents 0 0 0
PROGRESS
PLANNED UPTO DATE AS %
TOTAL ACHIVED FOR %TAGE UPTO DATE UPTO DATE %TAGE
S.NO ITEM / DESCRIPTION UNIT FOR THE OF FINAL Reasons for incompletion
Qty THE MONTH COMPLETED PLANNED ACHIVED COMPLETED
MONTH QUANTITY
Absorber-1
1) Foundation CTO not yet received.
1 Erection MT 265.0 30.39 8.86 29% 30.39 8.86 29.17% 3.34%
2) Welding Electrode for C276 not available
2 Alignment 0% 0.00% 0.00% 3) Bottom Plate SPB2 excess in Length
4) Back filing not done near to absorber for scaffolding
3 Welding & NDT 0% 0.00% 0.00% purpose.
Absorber-2
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
Process Water Tank-1
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
Process Water Tank-2
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
AUXI
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
PRIMARY HC FEED TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
REAGENT TANK -1
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
REAGENT TANK -2
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
FILTER WATER TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
WASTE WATER TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
SECONDARY HC FEED TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
Area Wise Photographs - Visual Progress
Last Month Photgraph This Month Photograph
Absorber # 1 Absorber # 1
3 MONTH LOOK-AHEAD SCHEDULE
January-19 February-19 March-19
Weekl Wee Wee Wee Weekl
Week-1 Week-2 Week-3 Week-4 Week-5 MONTH-2 MONTH-3
SI. PLAN y plan kly kly kly y plan
WORK ACTIVITY UOM SCOPE COMPL QTY BAL QYT START DATE END DATE 1-Jan-20 8-Jan-19 13-Jan-19 20-Jan-19 27-Jan-19
No DAY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su % COMPLETE NOTES
A ABSORBER - 1
Welding of Bottom Shell (1st Shell) MT 0 01-Jan-20 03-Jan-20 3 - - - - - 1) Welding Electrode for
Erection & Fitup of Shell from 1.2 mtr to 2.4 mtr (2nd C276 not available
MT 9.366 9.366 04-Jan-20 06-Jan-20 3 3.12 3.12 6.24 3.12 3.12 - - - 2) CTO & FQP for Welding
Shell)
Erection Joint weld of Bottom Shell (1st Shell) & 2nd not yet received
07-Jan-20 09-Jan-20 3
Shell
Shell Welding from 1.2 mtr to 2.4 mtr (2nd Shell) MT 0 10-Jan-20 12-Jan-20 3 - - - - -
Erection & Fitup of Shell from 2.4 mtr to 3.6 mtr (3rd
MT 9.366 9.366 13-Jan-20 15-Jan-20 3 - - 3.12 3.12 3.12 9.37 - -
Shell)
Erection Joint weld of 2nd Shell & 3rd Shell 16-Jan-20 18-Jan-20 3
Shell Welding from 2.4 mtr to 3.6 mtr (3rd Shell) MT 0 19-Jan-20 21-Jan-20 3 - - - - -
Erection & Fitup of Shell from 3.6 mtr to 4.8 mtr (4th
MT 8.253 8.253 22-Jan-20 24-Jan-20 3 - - - 2.75 2.75 2.75 8.25 -
Shell)
Erection Joint weld of 3rd Shell & 4th Shell MT 25-Jan-20 27-Jan-20 3
Shell Welding from 3.6 mtr to 4.8 mtr (4th Shell) MT 0 28-Jan-20 30-Jan-20 3 - - - - -
Erection & Fitup of Shell from 4.8 mtr to 6.0 mtr (5th
MT 8.253 8.253 31-Jan-20 02-Feb-20 3 - - - - 2.751 2.75 5.502
Shell)
Erection Joint weld of 4th Shell & 5th Shell MT 03-Feb-20 05-Feb-20 3
Shell Welding from 4.8 mtr to 6.0 mtr MT 0 06-Feb-20 08-Feb-20 3 - - - - -
Erection & Fitup of Bottom Plate MT 19.479 19.479 09-Feb-20 13-Feb-20 5 19.479
Welding of Bottol plate, and bottom plate with bottom
MT 0 13-Feb-20 17-Feb-20 5
shell
Erection & Fitup of Shell from 6.0 mtr to 7.2 mtr (6th
MT 8.253 8.253 18-Feb-20 20-Feb-20 3 8.253
Shell)
Erection Joint weld of 5th Shell & 6th Shell 21-Feb-20 23-Feb-20 3
Shell Welding from 6.0 mtr to 7.2 mtr (6th Shell) MT 0 24-Feb-20 26-Feb-20 3
Erection & Fitup of Shell from 7.2 mtr to 8.4 mtr (7th
MT 8.253 8.253 27-Feb-20 29-Feb-20 3 8.253
Shell)
Erection Joint weld of 6th Shell & 7th Shell 01-Mar-20 03-Mar-20 3
Shell Welding from 7.2 mtr to 8.4 mtr (7th Shell) MT 8.253 8.253 04-Mar-20 06-Mar-20 3 8.253
Erection & Fitup of Shell from 8.4 mtr to 9.6 mtr (8th
MT 6.006 6.006 07-Mar-20 09-Mar-20 3 6.006
Shell)
Erection Joint weld of 7th Shell & 8th Shell 10-Mar-20 12-Mar-20 3
Shell Welding from 8.4 mtr to 9.6 mtr (8th Shell) 13-Mar-20 15-Mar-20 3
Erection & Fitup of Shell from 9.6 mtr to 10.8 mtr (9th
MT 5.151 5.151 16-Mar-20 18-Mar-20 3 5.151
Shell)
Erection Joint weld of 8th Shell & 9th Shell 19-Mar-20 21-Mar-20 3
Shell Welding from 9.6 mtr to 10.8 mtr (9th Shell) 22-Mar-20 24-Mar-20 3
Erection & Fitup of Shell from 10.8 mtr to 12 mtr (10th
MT 4.551 4.551 25-Mar-20 27-Mar-20 3 4.551
Shell)
Erection Joint weld of 9th Shell & 10th Shell 28-Mar-20 30-Mar-20 3
Shell Welding from 10.8 mtr to 12 mtr (10th Shell) 31-Mar-20 02-Apr-20 3
- - - - -
Fitup & Erection of Roof Structure MT 11.555 11.555 29-Jan-20 31-Jan-20 3 - - - - 3.85 3.85 3.85 11.56
Welding of Roof Structure 01-Feb-20 03-Feb-20 3
Welding of Roof Structure, Shell S8 04-Feb-20 06-Feb-20 3
Erection & Fitup (L seam fitup) - S6 (Shell S6) MT 4.292 4.292 07-Feb-20 09-Feb-20 3 4.292
Shell welding (L seam welding) - S6 (Shell S6) 10-Feb-20 12-Feb-20 3
Fitup & Welding of S6 & S7 13-Feb-20 15-Feb-20 3
Erection & Fitup (L seam fitup) - S5 (Shell S5) MT 4.292 4.292 16-Feb-20 18-Feb-20 3 4.292
Shell welding (L seam welding) - S5 (Shell S5) 19-Feb-20 21-Feb-20 3
Fitup & Welding of S5 & S6 22-Feb-20 24-Feb-20 3
Erection & Fitup (L seam fitup) - S4 (Shell S4) MT 4.292 4.292 25-Feb-20 27-Feb-20 3 4.292
Shell welding (L seam welding) - S4 (Shell S4) 28-Feb-20 01-Mar-20 3
Fitup & Welding of S4 & S5 02-Mar-20 04-Mar-20 3
Erection & Fitup (L seam fitup) - S3 (Shell S3) MT 8.948 8.948 05-Mar-20 07-Mar-20 3 8.948
Shell welding (L seam welding) - S3 (Shell S3) 08-Mar-20 10-Mar-20 3
Fitup & Welding of S3 & S4 11-Mar-20 13-Mar-20 3
Erection & Fitup (L seam fitup) - S2 (Shell S2) MT 10.737 10.737 14-Mar-20 16-Mar-20 3 10.737
Shell welding (L seam welding) - S2 (Shell S2) 17-Mar-20 19-Mar-20 3
Fitup & Welding of S2 & S3 20-Mar-20 22-Mar-20 3
Erection & Fitup (L seam fitup) - S1 (Shell S1) MT 10.172 10.172 23-Mar-20 25-Mar-20 3 10.172
Shell welding (L seam welding) - S1 (Shell S1) 26-Mar-20 28-Mar-20 3
Fitup & Welding of S1 & S2 29-Mar-20 31-Mar-20 3
Fitup & Erection of Roof Structure MT 7.01 7.01 22-Jan-20 24-Jan-20 3 - - - 2.34 2.34 2.34 7.01 -
Welding of Roof Structure 25-Jan-20 27-Jan-20 3
Welding of Roof Structure, Shell S8 28-Jan-20 30-Jan-20 3
Erection & Fitup (L seam fitup) - S6 (Shell S6) MT 2.532 2.532 31-Jan-20 02-Feb-20 3 0.84 1.69
Structure material &
Nozzle, Appratus
Fitup & Erection of Roof Structure MT 7.01 7.01 22-Jan-20 24-Jan-20 3 - - - 2.34 2.34 2.34 7.01 -
Welding of Roof Structure 25-Jan-20 27-Jan-20 3
Welding of Roof Structure, Shell S8 28-Jan-20 30-Jan-20 3
Erection & Fitup (L seam fitup) - S6 (Shell S6) MT 2.532 2.532 31-Jan-20 02-Feb-20 3 0.84 1.69
Shell welding (L seam welding) - S6 (Shell S6) 03-Feb-20 05-Feb-20 3
Fitup & Welding of S6 & S7 06-Feb-20 08-Feb-20 3
Erection & Fitup (L seam fitup) - S5 (Shell S5) MT 2.532 2.532 09-Feb-20 11-Feb-20 3 2.532
Shell welding (L seam welding) - S5 (Shell S5) 12-Feb-20 14-Feb-20 3
Fitup & Welding of S5 & S6 15-Feb-20 17-Feb-20 3
Erection & Fitup (L seam fitup) - S4 (Shell S4) MT 2.532 2.532 18-Feb-20 20-Feb-20 3 2.532
Shell welding (L seam welding) - S4 (Shell S4) 21-Feb-20 23-Feb-20 3
Fitup & Welding of S4 & S5 24-Feb-20 26-Feb-20 3
Erection & Fitup (L seam fitup) - S3 (Shell S3) MT 3.375 3.375 27-Feb-20 29-Feb-20 3 3.375
Shell welding (L seam welding) - S3 (Shell S3) 01-Mar-20 03-Mar-20 3
Fitup & Welding of S3 & S4 04-Mar-20 06-Mar-20 3
Erection & Fitup (L seam fitup) - S2 (Shell S2) MT 3.375 3.375 07-Mar-20 09-Mar-20 3 3.375
Shell welding (L seam welding) - S2 (Shell S2) 10-Mar-20 12-Mar-20 3
Fitup & Welding of S2 & S3 13-Mar-20 15-Mar-20 3
Erection & Fitup (L seam fitup) - S1 (Shell S1) MT 6.566 6.566 16-Mar-20 18-Mar-20 3 6.566
Shell welding (L seam welding) - S1 (Shell S1) 19-Mar-20 21-Mar-20 3
Fitup & Welding of S1 & S2 22-Mar-20 24-Mar-20 3
Bottom Plate to Shell S1 Fitup & Welding 25-Mar-20 31-Mar-20 7
Fitup & Erection of Roof Structure MT 2.951 2.951 22-Jan-20 24-Jan-20 3 - - - 0.98 0.98 0.98 2.95 -
Welding of Roof Structure 25-Jan-20 27-Jan-20 3
Welding of Roof Structure, Shell S8 28-Jan-20 30-Jan-20 3
Erection & Fitup (L seam fitup) - S4 (Shell S4) MT 1.644 1.644 31-Jan-20 02-Feb-20 3 0.55 1.096
Shell welding (L seam welding) - S4 (Shell S4) 03-Feb-20 05-Feb-20 3
Fitup & Welding of S4 & S5 06-Feb-20 08-Feb-20 3
Erection & Fitup (L seam fitup) - S3 (Shell S3) MT 1.644 1.644 09-Feb-20 11-Feb-20 3 1.644
Shell welding (L seam welding) - S3 (Shell S3) 12-Feb-20 14-Feb-20 3
Fitup & Welding of S3 & S4 15-Feb-20 17-Feb-20 3
Erection & Fitup (L seam fitup) - S2 (Shell S2) MT 1.644 1.644 18-Feb-20 20-Feb-20 3 1.644
Shell welding (L seam welding) - S2 (Shell S2) 21-Feb-20 23-Feb-20 3
Fitup & Welding of S2 & S3 24-Feb-20 26-Feb-20 3
Erection & Fitup (L seam fitup) - S1 (Shell S1) MT 1.475 1.475 27-Feb-20 29-Feb-20 3 1.475
Shell welding (L seam welding) - S1 (Shell S1) 01-Mar-20 03-Mar-20 3
Fitup & Welding of S1 & S2 04-Mar-20 06-Mar-20 3
Bottom Plate to Shell S1 Fitup & Welding 07-Mar-20 13-Mar-20 7
Platform & Stairs Fitup & Welding MT 2.783 2.783 14-Mar-20 20-Mar-20 7 2.783
Scaffolding for Ducct and Damper During Shutdown job 01-Jan-20 31-Jan-20