Sei sulla pagina 1di 6

CONTRACT SUMMARY

Contract Details

PO No:- 4101903003
PO issue date:- 25th Sep 2019
Po Version No:- 0
Scope of value:- 229,320,006.72 INR (excl. GST)
270,597,607.92 INR (incl. GST)

Owner:- NTPC Solapur


Client:- GE POWER INDIA LIMITED
Sub Contractor:- WESTERN INDIA ERECTORS LLP

CONTRACTUAL MILESTONE

Vacuum Pumps, Limesstone &


Area Absorber Ball Mill Booster Fan & Duct Bed Filters, Hydro Gypsum Handling
Cyclones System

Planned work 21-Jul-20 1-Jul-20 21-Jul-20 21-Jul-20 21-Jul-20

Actual work

**Note: All planned date for U # 1 as per contract (NOA+10 month) and +4 month for Unit #2

Summary
EHS SUMMARY
PROGRESS
PHOTOGRAPHIC REPORT
3 MONTHS LOOK AHEAD SCHEDULE
MAN POWER STATUS
T&P STATUS
EHS SUMMARY

OBSERVATION IN LAST MONTH


1
2
3
4
5
6
7
8
9
10
11

OBSERVATION IN THIS MONTH


1 Improper cable route near RC pump
2 D shackels without colour code
3 welding plug shocket inner core exposed near store
4 oxygen cylinder imperper observed near rest room
5 first aid box without inspection
6 wheel observed without expiry date
7 Hydra wire observed without Cardium Compound
8 Acess block in front of 125 panel zone 2
9 Material improper stack near main store
10 Chemical drum observed without secondary containmnet near main store
11 ladder without inspection & colour code near main store
12 No job specific & policy sign boards displyed at site
13 Empty paint drum observed near store ,no hazards west material Identified

Indicates Pending Indicates Cleared


Remark:-
Observation Observation

NO OF OBSERVATION BALANCE CUMILATIVER OF


NO OF OBSERVATION NO OF OBSERVATION
Sl. No. DISCIPLINE CLEARED IN LAST OBSERVATION IN OBSERVATION UPTO
IN LAST MONTH IN THIS MONTH
MONTH LAST MONTH LAST MONTH

1 Observation 0 13 0 0 0

Sl. No. DISCIPLINE TILL LAST MONTH DURING THIS MONTH CUMULATIVE
1 Safe man hours 5960 13950 19910
2 Pep / Tool box talks 0 30 30
3 Induction training 19 22 41
4 Incident / Accident 0 0 0
5 Minor First Aid 0 0 0
6 Major Accidents 0 0 0
PROGRESS
PLANNED UPTO DATE AS %
TOTAL ACHIVED FOR %TAGE UPTO DATE UPTO DATE %TAGE
S.NO ITEM / DESCRIPTION UNIT FOR THE OF FINAL Reasons for incompletion
Qty THE MONTH COMPLETED PLANNED ACHIVED COMPLETED
MONTH QUANTITY
Absorber-1
1) Foundation CTO not yet received.
1 Erection MT 265.0 30.39 8.86 29% 30.39 8.86 29.17% 3.34%
2) Welding Electrode for C276 not available
2 Alignment 0% 0.00% 0.00% 3) Bottom Plate SPB2 excess in Length
4) Back filing not done near to absorber for scaffolding
3 Welding & NDT 0% 0.00% 0.00% purpose.
Absorber-2
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
Process Water Tank-1
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
Process Water Tank-2
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
AUXI
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
PRIMARY HC FEED TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
REAGENT TANK -1
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
REAGENT TANK -2
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
FILTER WATER TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
WASTE WATER TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
SECONDARY HC FEED TANK
1 Erection 0% 0.00% 0.00%
2 Alignment 0% 0.00% 0.00%
3 Welding & NDT 0% 0.00% 0.00%
Area Wise Photographs - Visual Progress
Last Month Photgraph This Month Photograph
Absorber # 1 Absorber # 1
3 MONTH LOOK-AHEAD SCHEDULE
January-19 February-19 March-19
Weekl Wee Wee Wee Weekl
Week-1 Week-2 Week-3 Week-4 Week-5 MONTH-2 MONTH-3
SI. PLAN y plan kly kly kly y plan
WORK ACTIVITY UOM SCOPE COMPL QTY BAL QYT START DATE END DATE 1-Jan-20 8-Jan-19 13-Jan-19 20-Jan-19 27-Jan-19
No DAY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su % COMPLETE NOTES
A ABSORBER - 1
Welding of Bottom Shell (1st Shell) MT 0 01-Jan-20 03-Jan-20 3 - - - - - 1) Welding Electrode for
Erection & Fitup of Shell from 1.2 mtr to 2.4 mtr (2nd C276 not available
MT 9.366 9.366 04-Jan-20 06-Jan-20 3 3.12 3.12 6.24 3.12 3.12 - - - 2) CTO & FQP for Welding
Shell)
Erection Joint weld of Bottom Shell (1st Shell) & 2nd not yet received
07-Jan-20 09-Jan-20 3
Shell
Shell Welding from 1.2 mtr to 2.4 mtr (2nd Shell) MT 0 10-Jan-20 12-Jan-20 3 - - - - -
Erection & Fitup of Shell from 2.4 mtr to 3.6 mtr (3rd
MT 9.366 9.366 13-Jan-20 15-Jan-20 3 - - 3.12 3.12 3.12 9.37 - -
Shell)
Erection Joint weld of 2nd Shell & 3rd Shell 16-Jan-20 18-Jan-20 3
Shell Welding from 2.4 mtr to 3.6 mtr (3rd Shell) MT 0 19-Jan-20 21-Jan-20 3 - - - - -
Erection & Fitup of Shell from 3.6 mtr to 4.8 mtr (4th
MT 8.253 8.253 22-Jan-20 24-Jan-20 3 - - - 2.75 2.75 2.75 8.25 -
Shell)
Erection Joint weld of 3rd Shell & 4th Shell MT 25-Jan-20 27-Jan-20 3
Shell Welding from 3.6 mtr to 4.8 mtr (4th Shell) MT 0 28-Jan-20 30-Jan-20 3 - - - - -
Erection & Fitup of Shell from 4.8 mtr to 6.0 mtr (5th
MT 8.253 8.253 31-Jan-20 02-Feb-20 3 - - - - 2.751 2.75 5.502
Shell)
Erection Joint weld of 4th Shell & 5th Shell MT 03-Feb-20 05-Feb-20 3
Shell Welding from 4.8 mtr to 6.0 mtr MT 0 06-Feb-20 08-Feb-20 3 - - - - -
Erection & Fitup of Bottom Plate MT 19.479 19.479 09-Feb-20 13-Feb-20 5 19.479
Welding of Bottol plate, and bottom plate with bottom
MT 0 13-Feb-20 17-Feb-20 5
shell
Erection & Fitup of Shell from 6.0 mtr to 7.2 mtr (6th
MT 8.253 8.253 18-Feb-20 20-Feb-20 3 8.253
Shell)
Erection Joint weld of 5th Shell & 6th Shell 21-Feb-20 23-Feb-20 3
Shell Welding from 6.0 mtr to 7.2 mtr (6th Shell) MT 0 24-Feb-20 26-Feb-20 3
Erection & Fitup of Shell from 7.2 mtr to 8.4 mtr (7th
MT 8.253 8.253 27-Feb-20 29-Feb-20 3 8.253
Shell)
Erection Joint weld of 6th Shell & 7th Shell 01-Mar-20 03-Mar-20 3
Shell Welding from 7.2 mtr to 8.4 mtr (7th Shell) MT 8.253 8.253 04-Mar-20 06-Mar-20 3 8.253
Erection & Fitup of Shell from 8.4 mtr to 9.6 mtr (8th
MT 6.006 6.006 07-Mar-20 09-Mar-20 3 6.006
Shell)
Erection Joint weld of 7th Shell & 8th Shell 10-Mar-20 12-Mar-20 3
Shell Welding from 8.4 mtr to 9.6 mtr (8th Shell) 13-Mar-20 15-Mar-20 3
Erection & Fitup of Shell from 9.6 mtr to 10.8 mtr (9th
MT 5.151 5.151 16-Mar-20 18-Mar-20 3 5.151
Shell)
Erection Joint weld of 8th Shell & 9th Shell 19-Mar-20 21-Mar-20 3
Shell Welding from 9.6 mtr to 10.8 mtr (9th Shell) 22-Mar-20 24-Mar-20 3
Erection & Fitup of Shell from 10.8 mtr to 12 mtr (10th
MT 4.551 4.551 25-Mar-20 27-Mar-20 3 4.551
Shell)
Erection Joint weld of 9th Shell & 10th Shell 28-Mar-20 30-Mar-20 3
Shell Welding from 10.8 mtr to 12 mtr (10th Shell) 31-Mar-20 02-Apr-20 3
- - - - -

B AUXILIARY ABSORBENT TANK


Base plate erection & fitup MT 10.536 10.536 01-Jan-20 03-Jan-20 3 3.51 3.51 3.51 10.54 - - - - 1) Foundation CTO not yet
done
Base plate welding MT 0 04-Jan-20 06-Jan-20 3 - - - - -
2) Confirmation required
Shell erection & fitup (L seam fitup) S7 (Shell S7) MT 4.292 4.292 07-Jan-20 09-Jan-20 3 - 1.43 1.43 1.43 4.29 - - - for Curb angle, Roof
Structure material &
Shell welding (L seam welding) S7 (Shell S7) MT 0 10-Jan-20 12-Jan-20 3 - - - - - Nozzle, Appratus
Top Ring Erection & fitup (L seam fitup) S8 (Shell S8) MT 4.262 4.262 13-Jan-20 15-Jan-20 3 - - 1.42 1.42 1.42 4.26 - -

Fitup & Welding of S7 & S8 22-Jan-20 25-Jan-20 4 - - - - -

Top Ring welding (L seam welding) S8 (Shell S8) MT 0 26-Jan-20 28-Jan-20 3 - - - - -

Fitup & Erection of Roof Structure MT 11.555 11.555 29-Jan-20 31-Jan-20 3 - - - - 3.85 3.85 3.85 11.56
Welding of Roof Structure 01-Feb-20 03-Feb-20 3
Welding of Roof Structure, Shell S8 04-Feb-20 06-Feb-20 3
Erection & Fitup (L seam fitup) - S6 (Shell S6) MT 4.292 4.292 07-Feb-20 09-Feb-20 3 4.292
Shell welding (L seam welding) - S6 (Shell S6) 10-Feb-20 12-Feb-20 3
Fitup & Welding of S6 & S7 13-Feb-20 15-Feb-20 3
Erection & Fitup (L seam fitup) - S5 (Shell S5) MT 4.292 4.292 16-Feb-20 18-Feb-20 3 4.292
Shell welding (L seam welding) - S5 (Shell S5) 19-Feb-20 21-Feb-20 3
Fitup & Welding of S5 & S6 22-Feb-20 24-Feb-20 3
Erection & Fitup (L seam fitup) - S4 (Shell S4) MT 4.292 4.292 25-Feb-20 27-Feb-20 3 4.292
Shell welding (L seam welding) - S4 (Shell S4) 28-Feb-20 01-Mar-20 3
Fitup & Welding of S4 & S5 02-Mar-20 04-Mar-20 3
Erection & Fitup (L seam fitup) - S3 (Shell S3) MT 8.948 8.948 05-Mar-20 07-Mar-20 3 8.948
Shell welding (L seam welding) - S3 (Shell S3) 08-Mar-20 10-Mar-20 3
Fitup & Welding of S3 & S4 11-Mar-20 13-Mar-20 3
Erection & Fitup (L seam fitup) - S2 (Shell S2) MT 10.737 10.737 14-Mar-20 16-Mar-20 3 10.737
Shell welding (L seam welding) - S2 (Shell S2) 17-Mar-20 19-Mar-20 3
Fitup & Welding of S2 & S3 20-Mar-20 22-Mar-20 3
Erection & Fitup (L seam fitup) - S1 (Shell S1) MT 10.172 10.172 23-Mar-20 25-Mar-20 3 10.172
Shell welding (L seam welding) - S1 (Shell S1) 26-Mar-20 28-Mar-20 3
Fitup & Welding of S1 & S2 29-Mar-20 31-Mar-20 3

C LIMESTONE SLURRY STORAGE TANK # 1


Base plate erection & fitup MT 6.497 6.497 01-Jan-20 03-Jan-20 3 2.17 2.17 2.17 6.50 - - - - 1) Foundation CTO not yet
done
Base plate welding MT 0 04-Jan-20 06-Jan-20 3 - - - - -
2) Confirmation required
Shell erection & fitup (L seam fitup) S7 (Shell S7) MT 2.532 2.532 07-Jan-20 09-Jan-20 3 - 0.84 0.84 0.84 2.53 - - - for Curb angle, Roof
Structure material &
Shell welding (L seam welding) S7 (Shell S7) MT 0 10-Jan-20 12-Jan-20 3 - - - - - Nozzle, Appratus
Top Ring Erection & fitup (L seam fitup) S8 (Shell S8) MT 1.672 1.672 13-Jan-20 15-Jan-20 3 - - 0.84 0.84 0.84 2.51 - -

Fitup & Welding of S7 & S8 MT 16-Jan-20 18-Jan-20 3 - - - - -

Top Ring welding (L seam welding) S8 (Shell S8) MT 0 19-Jan-20 21-Jan-20 3 - - - - -

Fitup & Erection of Roof Structure MT 7.01 7.01 22-Jan-20 24-Jan-20 3 - - - 2.34 2.34 2.34 7.01 -
Welding of Roof Structure 25-Jan-20 27-Jan-20 3
Welding of Roof Structure, Shell S8 28-Jan-20 30-Jan-20 3
Erection & Fitup (L seam fitup) - S6 (Shell S6) MT 2.532 2.532 31-Jan-20 02-Feb-20 3 0.84 1.69
Structure material &
Nozzle, Appratus

January-19 February-19 March-19


Weekl Wee Wee Wee Weekl
Week-1 Week-2 Week-3 Week-4 Week-5 MONTH-2 MONTH-3
SI. PLAN y plan kly kly kly y plan
WORK ACTIVITY UOM SCOPE COMPL QTY BAL QYT START DATE END DATE 1-Jan-20 8-Jan-19 13-Jan-19 20-Jan-19 27-Jan-19
No DAY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su M T W TH F Sa Su % COMPLETE NOTES
Shell welding (L seam welding) - S6 (Shell S6) 03-Feb-20 05-Feb-20 3
Fitup & Welding of S6 & S7 06-Feb-20 08-Feb-20 3
Erection & Fitup (L seam fitup) - S5 (Shell S5) MT 2.532 2.532 09-Feb-20 11-Feb-20 3 2.532
Shell welding (L seam welding) - S5 (Shell S5) 12-Feb-20 14-Feb-20 3
Fitup & Welding of S5 & S6 15-Feb-20 17-Feb-20 3
Erection & Fitup (L seam fitup) - S4 (Shell S4) MT 2.532 2.532 18-Feb-20 20-Feb-20 3 2.532
Shell welding (L seam welding) - S4 (Shell S4) 21-Feb-20 23-Feb-20 3
Fitup & Welding of S4 & S5 24-Feb-20 26-Feb-20 3
Erection & Fitup (L seam fitup) - S3 (Shell S3) MT 3.375 3.375 27-Feb-20 29-Feb-20 3 3.375
Shell welding (L seam welding) - S3 (Shell S3) 01-Mar-20 03-Mar-20 3
Fitup & Welding of S3 & S4 04-Mar-20 06-Mar-20 3
Erection & Fitup (L seam fitup) - S2 (Shell S2) MT 3.375 3.375 07-Mar-20 09-Mar-20 3 3.375
Shell welding (L seam welding) - S2 (Shell S2) 10-Mar-20 12-Mar-20 3
Fitup & Welding of S2 & S3 13-Mar-20 15-Mar-20 3
Erection & Fitup (L seam fitup) - S1 (Shell S1) MT 6.566 6.566 16-Mar-20 18-Mar-20 3 6.566
Shell welding (L seam welding) - S1 (Shell S1) 19-Mar-20 21-Mar-20 3
Fitup & Welding of S1 & S2 22-Mar-20 24-Mar-20 3
Bottom Plate to Shell S1 Fitup & Welding 25-Mar-20 31-Mar-20 7

D LIMESTONE SLURRY STORAGE TANK # 2


Base plate erection & fitup MT 6.497 6.497 01-Jan-20 03-Jan-20 3 2.17 2.17 2.17 6.50 - - - - 1) Foundation CTO not yet
done
Base plate welding MT 0 04-Jan-20 06-Jan-20 3 - - - - -
2) Confirmation required
Shell erection & fitup (L seam fitup) S7 (Shell S7) MT 2.532 2.532 07-Jan-20 09-Jan-20 3 - 0.84 0.84 0.84 2.53 - - - for Curb angle, Roof
Structure material &
Shell welding (L seam welding) S7 (Shell S7) MT 0 10-Jan-20 12-Jan-20 3 - - - - - Nozzle, Appratus
Top Ring Erection & fitup (L seam fitup) S8 (Shell S8) MT 1.672 1.672 13-Jan-20 15-Jan-20 3 - - 0.84 0.84 0.84 2.51 - -

Fitup & Welding of S7 & S8 MT 16-Jan-20 18-Jan-20 3 - - - - -

Top Ring welding (L seam welding) S8 (Shell S8) MT 0 19-Jan-20 21-Jan-20 3 - - - - -

Fitup & Erection of Roof Structure MT 7.01 7.01 22-Jan-20 24-Jan-20 3 - - - 2.34 2.34 2.34 7.01 -
Welding of Roof Structure 25-Jan-20 27-Jan-20 3
Welding of Roof Structure, Shell S8 28-Jan-20 30-Jan-20 3
Erection & Fitup (L seam fitup) - S6 (Shell S6) MT 2.532 2.532 31-Jan-20 02-Feb-20 3 0.84 1.69
Shell welding (L seam welding) - S6 (Shell S6) 03-Feb-20 05-Feb-20 3
Fitup & Welding of S6 & S7 06-Feb-20 08-Feb-20 3
Erection & Fitup (L seam fitup) - S5 (Shell S5) MT 2.532 2.532 09-Feb-20 11-Feb-20 3 2.532
Shell welding (L seam welding) - S5 (Shell S5) 12-Feb-20 14-Feb-20 3
Fitup & Welding of S5 & S6 15-Feb-20 17-Feb-20 3
Erection & Fitup (L seam fitup) - S4 (Shell S4) MT 2.532 2.532 18-Feb-20 20-Feb-20 3 2.532
Shell welding (L seam welding) - S4 (Shell S4) 21-Feb-20 23-Feb-20 3
Fitup & Welding of S4 & S5 24-Feb-20 26-Feb-20 3
Erection & Fitup (L seam fitup) - S3 (Shell S3) MT 3.375 3.375 27-Feb-20 29-Feb-20 3 3.375
Shell welding (L seam welding) - S3 (Shell S3) 01-Mar-20 03-Mar-20 3
Fitup & Welding of S3 & S4 04-Mar-20 06-Mar-20 3
Erection & Fitup (L seam fitup) - S2 (Shell S2) MT 3.375 3.375 07-Mar-20 09-Mar-20 3 3.375
Shell welding (L seam welding) - S2 (Shell S2) 10-Mar-20 12-Mar-20 3
Fitup & Welding of S2 & S3 13-Mar-20 15-Mar-20 3
Erection & Fitup (L seam fitup) - S1 (Shell S1) MT 6.566 6.566 16-Mar-20 18-Mar-20 3 6.566
Shell welding (L seam welding) - S1 (Shell S1) 19-Mar-20 21-Mar-20 3
Fitup & Welding of S1 & S2 22-Mar-20 24-Mar-20 3
Bottom Plate to Shell S1 Fitup & Welding 25-Mar-20 31-Mar-20 7

E PRIMARY HYDROCYCLONE FEED TANK


Base plate erection & fitup MT 2.62 2.62 01-Jan-20 03-Jan-20 3 0.87 0.87 0.87 2.62 - - - - 1) Foundation CTO not yet
done
Base plate welding MT 0 04-Jan-20 06-Jan-20 3 - - - - -
2) Confirmation required
Shell erection & fitup (L seam fitup) S5 (Shell S5) MT 1.644 1.644 07-Jan-20 09-Jan-20 3 - 0.55 0.55 0.55 1.64 - - - for Curb angle, Roof
Structure material &
Shell welding (L seam welding) S5 (Shell S5) MT 0 10-Jan-20 12-Jan-20 3 - - - - - Nozzle, Appratus
Top Ring Erection & fitup (L seam fitup) S6 (Shell S6) MT 1.086 1.086 13-Jan-20 15-Jan-20 3 - - 0.36 0.36 0.36 1.09 - -

Fitup & Welding of S6 & S5 MT 16-Jan-20 18-Jan-20 3 - - - - -

Top Ring welding (L seam welding) S6 (Shell S6) MT 0 19-Jan-20 21-Jan-20 3 - - - - -

Fitup & Erection of Roof Structure MT 2.951 2.951 22-Jan-20 24-Jan-20 3 - - - 0.98 0.98 0.98 2.95 -
Welding of Roof Structure 25-Jan-20 27-Jan-20 3
Welding of Roof Structure, Shell S8 28-Jan-20 30-Jan-20 3
Erection & Fitup (L seam fitup) - S4 (Shell S4) MT 1.644 1.644 31-Jan-20 02-Feb-20 3 0.55 1.096
Shell welding (L seam welding) - S4 (Shell S4) 03-Feb-20 05-Feb-20 3
Fitup & Welding of S4 & S5 06-Feb-20 08-Feb-20 3
Erection & Fitup (L seam fitup) - S3 (Shell S3) MT 1.644 1.644 09-Feb-20 11-Feb-20 3 1.644
Shell welding (L seam welding) - S3 (Shell S3) 12-Feb-20 14-Feb-20 3
Fitup & Welding of S3 & S4 15-Feb-20 17-Feb-20 3
Erection & Fitup (L seam fitup) - S2 (Shell S2) MT 1.644 1.644 18-Feb-20 20-Feb-20 3 1.644
Shell welding (L seam welding) - S2 (Shell S2) 21-Feb-20 23-Feb-20 3
Fitup & Welding of S2 & S3 24-Feb-20 26-Feb-20 3
Erection & Fitup (L seam fitup) - S1 (Shell S1) MT 1.475 1.475 27-Feb-20 29-Feb-20 3 1.475
Shell welding (L seam welding) - S1 (Shell S1) 01-Mar-20 03-Mar-20 3
Fitup & Welding of S1 & S2 04-Mar-20 06-Mar-20 3
Bottom Plate to Shell S1 Fitup & Welding 07-Mar-20 13-Mar-20 7
Platform & Stairs Fitup & Welding MT 2.783 2.783 14-Mar-20 20-Mar-20 7 2.783

Manhole, Clean out door, Suction Pump, Drain Overflow,


Earth Plug, Ultrasonic Level Transmitter, Vent, Gypsum 21-Mar-20 31-Mar-20
Bleed Pump, Agitator Nozzle

F SCAFFOLDING FOR SHUTDOWN JOB

Scaffolding for Ducct and Damper During Shutdown job 01-Jan-20 31-Jan-20