SERIOUS INSPECTION

PLTU AMURANG UNIT 2


2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 21 September 2016
Generator 1
1 Disassembly Exciter Set 100% 2
2 Pelepasan Brush 30% 3
3 Pengukuran Gap 30% 4
4 Megger dan Pelepasan NGR 50%

Motor 380 V 1
1 Dissasembly Motor CEP 10% 2
2 Cleaning Motor CEP 50% 3
3 Insulated Resistance Tester (Megger) 50%
1

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Generator
Pelepasan Brush
Pengukuran Gap
Megger dan Pelepasan NGR

Motor 380 V
Dissasembly Motor CEP
Cleaning Motor CEP
Insulated Resistance Tester (Megger)

Motor 6 kV
Motor PA Fan

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 22 September 2016
Motor 6 kV 1
1 SE0116113 Motor PA Fan Progress 10% 2
2 3
3 Motor 380 V 4
4 Insulated Resistance Tester (Megger) Finished 100%
Motor CEP Finished 100%

1 SE0116007 Transformator 5% 1
2 Pasang Scafolding Progress 40% 2
3 Pelepasan Fan Progress 30% 3

Pemasangan Power Bolt Heater Finished 100% 1

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Motor 6 kV
Motor PA Fan Lanjutan

Motor 380 V
Cleaning dan IR Test Lanjutan

Transformator Lanjutan
Pasang Scafolding Lanjutan
Pelepasan Fan

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 23 September 2016
Motor 6 kV
Motor PA Fan Progress 30%
Disassembly Pipa Cooling PA Fan Finished 100%
Disassembly Baut Pondasi Finished 100%
Disassembly Cooler Finished 100%
Mengangkat Motor Ke area Finished 100%

Motor 380 V
Cleaning dan IR Test Progress 10%

Main Transformator 10%


Pasang Scafolding Finished 100%
Pelepasan Fan Finished 100%
Pengambilan Sampling Bearing Fan Trafo Finished 100%
Pemasangan Stick Grounding Finished 100%

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal
Semua: 23Bidang
September 2016 PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Motor 6 kV
Motor PA Fan
Melepaskan Coupling
Melepaskan Branket dan Bearing DE

Motor 380 V
Cleaning dan IR Test

Main Transformator
Diassembly Motor Fan Transformator

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 24 September 2016
Motor 6 kV
SE0116113 Motor PA Fan
Melepaskan Coupling Finished 100%
Melepaskan Bracket dan Bearing DE Progress 50%
(terkendala Chain Block PA macet)
Pembongkaran Bearing NDE Finished 100%
Cleaning Bracket Progress 50%

SE0116028 Motor 380 V


Pelepasan Bearing sisi fan HP seal Blower Progress 50%

SE0116007 Main Transformator


Pelepasan Flexibel Kabel Box sisi HV dan LV Finished 100%
Insulated Resistance Tester (Megger) Progress 1%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 24 September 2016

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Melepaskan Branket dan Bearing DE


(terkendala Crane PA macet)

Cleaning Branket

Pelepasan Bearing sisi fan HP seal Boaster fan

Cleaning Motor Fan Trafo


Revarnish
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 25 September 2016
SE0116028 Motor 380 V
Pelepasan Bearing PA Booster fan Finished 100%

SE0116007 Main Transformator


Insulated Resistance Tester (Megger) Finished 100%
Cleaning Motor Fan Trafo Progress 10%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 25 September 2016

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Cleaning Motor Fan Trafo Lanjut


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 26 September 2016
Motor 380 V

SE0116022 Pemasangan Bearing DE dan NDE Motor PA Finished 100% SE0116022


Booster Fan

SE0116007 Main Transformator


Insulated Resistance Tester (Megger) Finished 100%
Cleaning Motor Fan Trafo Progress 50%

Motor 6 kV
SE0116113 Pasang Bearing sisi DE motor PA Fan
Pasang Braket motor PA Fan

Battery Charger & Breaker

SE0116150 Cleaning Breaker 6 kV Progress 20%


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 26 September 2016

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Cleaning dan revarnish PA Booster Fan

Cleaning Motor Fan Trafo Lanjut

Pasang Bearing sisi NDE motor PA Fan

Cleaning Breaker 6 kV
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 28 September 2016
1 SE0116007 Main Transformator 1 SE0116007
Disassembly Bearing Fan Transformator Progress 100%
Pemasangan Bearing Fan Trafo Progress 50%
Cleaning Motor Fan Trafo Progress 50%

2 Motor 6 kV
SE0116113 Pasang Bearing sisi NDE motor PA Fan Finished 100% 2 SE0116113
Pasang Braket motor PA Fan Progress 60%

3 Motor 380 V 3
SE0116122 Revarnish Stator PA Booster Fan Finished 100% SE0116030
Assembly branket DE NDE dan acsesoris Finished 100%
Pengencangan baut pondasi PA booster Fan Finished 100%
SE0116030 Disassembly Gland Steam No. 2 Finished 100%

SE0116060 Mengangkat motor Vacuum Pump B Finished 100%


Pasang Bearing Gland Steam Progress 10%

4 Breaker 6 kV dan 10.5 kV 4


SE0116150 Inspeksi dan Cleaning Breaker 6 kV Progress 80% SE0116150
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 28 September 2016
SE0116152 Inspeksi dan Cleaning Breaker 10,5 kV Finished 100%

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Main Transformator
Disassembly Bearing Fan Transformator Lanjutan
Cleaning Motor Fan Trafo Lanjutan

Motor 6 kV
Pasang Braket motor PA Fan Lanjutan

Motor 380 V
Pasang Bearing Gland Steam Lanjutan

Breaker 6 kV dan 10.5 kV


Inspeksi dan Cleaning Breaker 6 kV Lanjutan
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 29 September 2016
1 SE0116007 Main Transformator 1 SE0116007
Pemasangan Bearing Fan Trafo Fnished 100%
Cleaning Motor Fan Trafo Progress 50%

Pengambilan sampling oil Main transformator Finished 100%

2 Motor 6 kV
SE0116113 Pasang Braket motor PA Fan Progress 70% 2 SE0116113

3 Motor 380 V 3
SE0116030 Pasang Bearing Gland Steam Finished 100%

4 Breaker 6 kV dan 10.5 kV


SE0116150 Inspeksi dan Cleaning Breaker 6 kV Progress 80%

5 ESP
Insulated Resistance Testing (Megger ) Finished 100%
Transformator
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 29 September 2016
Insulated Resistance Testing (Megger) Trafo Finished 100%
sisi Beban
Insulated Megger motor dan isolator Finished 100%

6 Generator
Pengecekan & pengukuran Clearance bearing Finished 100%
generator No. 4

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Main Transformator
Pemasangan Fan Transformator
Cleaning Motor Fan Trafo Lanjutan

Motor 6 kV
Pasang Braket motor PA Fan Lanjutan
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 29 September 2016
1 SE0116007 Main Transformator
Cleaning Bushing Main Transformator sisi HV Fnished 100%
dan LV

Motor 6 kV
SE0116113 Pasang Braket motor PA Fan Finished 100%
2 Melepas Cooler ID Fan Finished 100%
Merubah posisi motor untuk pelepasan Progress 10%
kopling ID Fan

3 Motor 380 V
SE0116030 Disassembly Bearing Vacum Pump Finished 100%

4 MCC
Inspeksi dan Cleaning MCC Progress 40%

5 ESP
Insulated Resistance Testing (Megger )
Transformator (sisi beban 2 Trafo tidak bisa di Finished 100%
megger)
Disassembly motor emiting Finished 10%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 29 September 2016
Cleaning Isolator Trafo Incoming 4,5,6 Finished 10%

6 Generator
Membuka Cover Fan Blade Finished 100%
Pembuatan Spesial Tools Jacking Generator Progress 10%

Keterangan

Koordinator Bidang Herry Santoso


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Motor 6 kV
Merubah posisi motor untuk pelepasan
kopling ID Fan

MCC
Inspeksi dan Cleaning MCC

ESP

Disassembly motor emiting

Cleaning Isolator Trafo Incoming 4,5,6


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Generator
Pembuatan Spesial Tools Jacking Generator

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 02 Okt 2016 (
1 Motor 6 KV 1
SE0116113 Inspeksi PA Fan Progress 80% SE0116113
SE0116122 Inpeksi PA Booster Fan Progress 80% SE0116122
SE0116116 Inspeksi ID Fan Progress 50% SE0116116
Melepaskan Bearing NDE ID Fan Finished 100%
Cleaning Branket dan Aksesoris NDE ID Fan Finished 100%
Memasang Bearing NDE ID Fan Progress 10%
Melepaskan Coupling ID Fan Progress 10%

2 Motor 380 V
SE0116045 Inspeksi Motor AOP Progress 40% SE0116045
Disassembly motor AOP Finished 100%
SE0116028 Inspeksi Motor Jacking Oil Pump Progress 5% SE0116028
Disassembly Jacking il Pump Progress 10%

3 SE0116007 Transformator Progress 60% SE0116007


Pemasangan Fan Trafo Progress 50%

4 SE0116127 ESP SE0116127


Inspeksi Heater Hopper Progress 20%
Cleaning Busbar Isolator Progress 35%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 02 Okt 2016 (
Inspeksi Heater Hopper (No. 2 (Short 2)) Progress 20%

5 SE0116003 Generator SE0116003


Disassembly Casing Winding Finished 100%
Disassembly Oil Deflector Inner Bearing #4 Finished 100%
Assembly Support Jacking rotor Progress 50%
Disassembly Pedestal bearing #4 Progress 50%
Keterangan
Koordinator Bidang Herry Santoso
Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Motor 6 KV
Inspeksi PA Fan Lanjutan
Inpeksi PA Booster Fan Lanjutan
Inspeksi ID Fan Lanjutan
Memasang Bearing NDE ID Fan Lanjutan
Melepaskan Coupling ID Fan Lanjutan

Motor 380 V
Inspeksi Motor AOP Lanjutan
Inspeksi Motor Jacking Oil Pump Lanjutan
Disassembly Jacking il Pump Lanjutan

Transformator
Pemasangan Fan Trafo Lanjutan

ESP
Inspeksi Heater Hopper Lanjutan
Cleaning Busbar Isolator Lanjutan
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Inspeksi Heater Hopper (No. 2 (Short 2)) Lanjutan

Generator
Assembly Support Jacking rotor dengan
balok
Disassembly Pedestal bearing #4

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 03 Okt 2016 (Hari ke-15)
1 Motor 6 KV 1
SE0116113 Inspeksi PA Fan Progress 80% SE0116113
SE0116122 Inpeksi PA Booster Fan Progress 80% SE0116122
SE0116116 Inspeksi ID Fan Progress 50% SE0116116
Memasang Bearing NDE ID Fan Finished 100%
Melepaskan Breket DE Progress 20%
Melepaskan Coupling ID Fan Progress 10%

2 Motor 380 V
SE0116045 Inspeksi Motor AOP Progress 40% SE0116045
SE0116028 Inspeksi Motor Jacking Oil Pump Progress 5%
Disassembly Jacking Oil Pump Progress 25% SE0116028
Melepas Koneksi CWP no. 3 Finished 100%

3 SE0116007 Generator Transformator Progress 70%


Pemasangan Fan Trafo Progress 100%

3 SE0116007 Aux. Transformator Progress 1%


Insulated Resistance (Megger) HV dan LV Progress 1%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 03 Okt 2016 (Hari ke-15)
4 SE0116127 ESP SE0116127
Inspeksi Heater Hopper Progress 40%
Cleaning Busbar Isolator Progress 35%
Inspeksi Heater Hopper Progress 25%

5 SE0116003 Generator SE0116003


Assembly Support Jacking rotor Progress 60%
Disassembly Pedestal bearing #4 Finished 100%
Contact Check Stopper Bearing Finished 100%
Inspeksi Stopper Bearing Progress 10%
Keterangan
Koordinator Bidang Herry Santoso
Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Motor 6 KV
Inspeksi PA Fan Lanjutan
Inpeksi PA Booster Fan Lanjutan
Inspeksi ID Fan Lanjutan

Motor 380 V
Inspeksi Motor AOP Lanjutan
Inspeksi Motor Jacking Oil Pump Lanjutan
Disassembly Jacking il Pump Lanjutan
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

ESP
Inspeksi Heater Hopper Lanjutan
Cleaning Busbar Isolator Lanjutan
Inspeksi Heater Hopper Lanjutan

Generator
Inspeksi Stopper Bearing

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 05 Okt 2016 (Hari ke-17)
1 Motor 6 KV 1
SE0116113 Inspeksi PA Fan Progress 80%
SE0116122 Inpeksi PA Booster Fan Progress 80%
SE0116116 Inspeksi ID Fan Progress 50%
Cleaning Breket dan aksesoris Progress 40%

2 Motor 380 V
SE0116045 Inspeksi Motor AOP Progress 40%
SE0116028 Inspeksi Motor Jacking Oil Pump Progress 5%
Disassembly Jacking Oil Pump (pembuatan Progress 25%
Spesial Tools)

3 SE0116007 Generator Transformator Progress 70%

3 SE0116007 Aux. Transformator Progress 5%


Cleaning Bushing sisi Hv dan Lv Progress 10%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 05 Okt 2016 (Hari ke-17)
4 SE0116127 ESP
Inspeksi Heater Hopper Progress 40%
Cleaning Bushing Isolator Progress 50%
Inspeksi Heater Hopper dan emitting Progress 70%
Penggantian Isolator Bushing Progress 50%

5 SE0116003 Generator
Inspeksi Stopper Bearing Progress 40%
Pengaturan Simplate di Stopper Bearing Progress 90%
Lower
Cleaning End Winding Progress 70%

Keterangan
Koordinator Bidang Herry Santoso
Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 06 Okt 2016 (Hari ke-18)
1 Motor 6 KV 1
SE0116113 Inspeksi PA Fan Progress 80%
SE0116122 Inpeksi PA Booster Fan Progress 80%
SE0116116 Inspeksi ID Fan Progress 100%
Pasang Coupling dan Cover Progress 100%

2 Motor 380 V
SE0116045 Inspeksi Motor AOP Progress 40%
SE0116028 Inspeksi Motor Jacking Oil Pump Progress 40%
Inspeksi Turning Gear Progress 40%
Inspeksi Motor Vibrator Progress 40%
Disassembly Motor Vibrator Finished 100%
Disassembly Motor DC Oil Pump Finished 100%

3 SE0116007 Generator Transformator Progress 70%

3 SE0116007 Aux. Transformator Progress 30%


Cleaning Bushing sisi Hv dan Lv Finished 80%
Tightning Progress 50%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG Listrik
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 06 Okt 2016 (Hari ke-18)
4 SE0116127 ESP
Inspeksi Hopper Progress 40%
Cleaning Bushing Isolator Progress 80%
Inspeksi Heater Hopper dan emitting Progress 60%
Penggantian Isolator Bushing 100%
Cleaning Motor Colecting 25%

5 SE0116003 Generator
Inspeksi Stopper Bearing Progress 80%
Pengaturan kontak Stopper Bearing Terhadap Progress 90%
Pedestal
Cleaning End Winding Progress 100%

Keterangan
Koordinator Bidang Herry Santoso
Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto