Sei sulla pagina 1di 50

SERIOUS INSPECTION

PLTU AMURANG UNIT 2


2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 21 September 2016
Turbin
1 Disassembly Isolasi Turbin 100% 1
2 Disassembly Front Standard 30% 2
3 Disassembly Turning Gear 30% 3
4 Disassembly Kopling Turbin 0% 4
5 Disassembly Cover Bearing 1, 2, 3, 4 0%
6 Disassembly Stang MSV 100%
1
Aux. Turbin
Disassembly CEP (Pengangkatan Motor
1 100%
CEP)
2 Bongkar Flange Seal 100%
3 Bongkar Baut Discharge 100%
4 Bongkar Pompa 20%
5 Lepas Baut Kopling 100%

Boiler
1 Scafolding di Furnace 10%
2 Disassembly Boiler Steam Drum 25%
3 Melepas Isolasi Steam Drum Man Hole 100%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan Progress
No Tag No. Keterangan No Tag No.
(Work Has Been Done)
Tanggal : 21 September 2016
4 Drain Bunker Boiler 10%

Keterangan

Koordinator Bidang Willy Pratama


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbin
Disassembly Front Standard
Disassembly Turning Gear
Disassembly Kopling Turbin
Disassembly Cover Bearing 1, 2, 3, 4

Aux. Turbin
Bongkar Pompa

Inspeksi MOT
Drain ESP
Drain Pasir di Furnace
Cleaning Steam Drum
PAF System
SAF System
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 22 September 2016
1 Turbin
SE0116013 Turbine Casing Progress 10%
Melepas baut dan pin casing turbin 50%

SE0116013 Turbine Bolt and Nut Progress 10%


Melepas Baut inlet steam turbin 100%

2 Aux. Turbin
Inspeksi MOT Progress 25%
SE0116064 Inspection HE pada Vacuum Pump Progress 20%
Bongkar HE No. 1 & 2 100%

Cleaning HE No. 1 30%

Bongkar Filter Inlet Cooling HE no. 1 & 2 100%

Buka Penekan Gland Packing No. 1 dan No. 2 80%

Inspection Saparator Tank Vacuum Pump Progress 10%


Membuka Manhole Sparator tank 1 & 2 100%

3 Aux Boiler
PAF System Progress 10%
Pelepasan Kopling PA Fan dan Data Alignment 50%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 22 September 2016
SAF System Progress 1%

4 Boiler
Inspection Steam Drum Progress 2%
Cleaning Steam Drum 10%
SE0116124 Inspeksi Air Heater Progress 30%
Test Air Heater (Tidak ada kebocoran) 50%

Pembuatan Akses Manhole Air Heater 50%

Drain Pasir di Furnace Progress 90%


Pelepasan Lance Cube & Inner Cube di Sootblower
No. 5 dan No. 7 Progress 50%
Pekerjaan Pemasangan Scafolding di furnace Progress 10%

Keterangan

Koordinator Bidang Willy Pratama


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbine Casing
Melepas baut dan pin casing turbin
Turbine Bolt and Nut

Aux. Turbin
Inspeksi MOT
Inspection HE pada Vacuum Pump
Cleaning HE No. 1
Buka Penekan Gland Packing No. 1 dan No. 2
Inspection Saparator Tank

Aux Boiler
PAF System
Pelepasan Kopling PA Fan dan Data Alignment
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

SAF System

Boiler
Inspection Steam Drum
Cleaning Steam Drum
Inspeksi Air Heater
Test Air Heater (Hasil Baik)
Pembuatan Akses Manhole Air Heater
Drain Pasir di Furnace
Pelepasan Lance Cube & Inner Cube di
Sootblower No. 5 dan No. 7

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 23 September 2016
Turbin
Turbine Casing Progress 40%
Melepas baut dan pin casing turbin Finished 100%
Pengangkatan Casing Turbin Progress 10%

Aux. Turbin
Inspeksi MOT Progress 30%
Inspection HE pada Vacuum Pump Progress 50%
Cleaning HE No. 1 Finished 100%

Cleaning HE No. 2 Finished 100%

Buka Penekan Gland Packing No. 1 dan No. 2 Progress 80%

Pelepasan Bearing Vacuum Pump No.1 Progress 50%

Inspection Saparator Tank Finished 100%

Aux Boiler Progress


PAF System Progress 20%
Pelepasan Kopling PA Fan dan Data Alignment Progress 100%
SAF System Progress 1%

Cleaning Gas Duct Progress 50%


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 23 September 2016

Boiler
Inspection Steam Drum Progress 2%
Cleaning Steam Drum Progress 10%
Inspeksi Air Heater Progress 40%

Test Air Heater (Hasil Baik) Progress 50%


Pembuatan Akses Manhole Air Heater Progress 60%

Finished 100%
Drain Pasir di Furnace
Pelepasan Lance Cube & Inner Cube di Sootblower Progress 70%
No. 5 dan No. 7
Pekerjaan Pemasangan Scafolding di furnace Progress 20%

Progress 50%
Lepas Chevron dan Sparator di Steam Drum
Melepas Coupling ID fan dan Pengambilan data Progress 50%
before aligment

Keterangan
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 23 September 2016
Koordinator Bidang Willy Pratama
Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbin
Turbine Casing
Pengangkatan Casing Turbin

Aux. Turbin
Inspeksi MOT
Inspection HE pada Vacuum Pump
Buka Penekan Gland Packing No. 1 dan No. 2
Pelepasan Bearing Vacuum Pump
No.1

Aux Boiler
PAF System
SAF System
Cleaning Gas Duct
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Boiler
Inspection Steam Drum
Cleaning Steam Drum
Inspeksi Air Heater
Test Air Heater (Hasil Baik)
Pembuatan Akses Manhole Air Heater

Pelepasan Lance Cube & Inner Cube di


Sootblower No. 5 dan No. 7

Pekerjaan Pemasangan Scafolding di furnace

Lepas Chevron dan Sparator di Steam Drum

Melepas Coupling ID fan dan Pengambilan


data before aligment
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 24 September 2016
Turbin
SE0116013 Turbine Casing
Pengangkatan Casing Turbin Finished 100%
Pengukuran Clearance Before Progress 10%

Aux. Turbin
SE0116027 Inspeksi MOT Progress 30%
SE0116059 Inspection HE pada Vacuum Pump Progress 60%

Progress 80%
Buka Penekan Gland Packing No. 1 dan No. 2
Pelepasan Bearing Vacuum Pump No.1 Finished 100%

Tes Kebocoran HE No. 2 (Tidak ada Kebocoran Finished 100%

Tes Kebocoran HE No. 1 Progress 50%

Aux Boiler
SE0116112 PAF System Progress 20%
SE0116118 SAF System Progress 1%
Cleaning Gas Duct (Back Pass) Progress 50%

SE0116115 Melepas Coupling ID fan dan Pengambilan data Finished 100%


before aligment

Boiler
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 24 September 2016
SE0116078 Inspection Steam Drum Progress 10%
Disassembly Steam Drum Progress 60%
Lepas Chevron dan Separator di Steam Drum Progress 75%

SE0116124 Test Air Heater Progress 50%

SE0116124 Pembuatan Akses Manhole Air Heater Finished 100%

SE0116100 Pelepasan Lance Cube & Inner Cube di Sootblower Progress 70%
No. 5 dan No. 7
Pekerjaan Pemasangan Scafolding di furnace Progress 50%

Keterangan

Koordinator Bidang Willy Pratama


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Pengukuran Clearance Before Lanjutan

Tes Aligment HE
Tes Kebocoran HE Lanjutan

Cleaning Gas Duct Lanjutan


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Disassembly Steam Drum Lanjutan


Lepas Chevron dan Sparator di Steam Drum Lanjutan
Test Air Heater (Hasil Baik) Lanjutan
Pekerjaan Pemasangan Scafolding di furnace Lanjutan

Pelepasan Lance Cube & Inner Cube di Lanjutan


Sootblower No. 5 dan No. 7
Membuka Isolasi LPH

Membuka Manhole HPH

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 25 September 2016
Turbin
Pengukuran Clearance Before
Double Row Curtis Finished 100%
Pressure Stage P1-P17 Finished 100%
Front Gland Finished 100%
Rear Gland Finished 100%
Nozzle Diaparghm P1-P17 Progress 100%
Clearance Journal Bearing (1,2,3) Finished 100%
Clearance Thrust Finished 100%

Lifting Turbin Progress 1%


Uncoupling Poros Turbin Finished 100%
Melepas Upper Curtis Finished 100%
Melepas Dummy Ring Finished 100%
Contact Check Lower Bearing Progress 50%

Aux. Turbin
SE0116027 Progress 30%
Inspeksi MOT
SE0116059 Inspection HE pada Vacuum Pump Progress 60%
Buka Penekan Gland Packing No. 1 dan No. 2 Progress 80%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 25 September 2016
Tes Kebocoran HE No. 1 (no leak) Finished 100%

Disassembly Bearing Vacuum Pump no.1 DE side Finished 100%

Assembly bearing vacuum pump no.1 Finished 100%

Penutupan Flange Vacum Pump sisi Barat Finished 100%

Penggantian filter flange sisi timur Finished 100%

Shaft Gland Cooler Exhaust fan


Buka Waterbox LPH 1 Finished 100%

Cleaning LPH No.1 Progress 50%

Membuka Waterbox LPH No. 2 Finished 100%

Cleaning LPH No.2 Progress 50%

Boiler
SE0116078 Inspection Steam Drum Progress 10%
Disassembly Steam Drum Progress 60%
Lepas Chevron dan Separator di Steam Drum Progress 75%

SE0116124 Test Air Heater (3 titik kebocoran) Finished 100%

SE0116100 Pelepasan Lance Cube & Inner Cube di Sootblower Finished 100%
No. 5 dan No. 7
Pekerjaan Pemasangan Scafolding di furnace Progress 80%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 25 September 2016

Aux Boiler
SE0116112 Pembukaan Manhole PA Fan Finished 100%

Pembukaan Manhole ID Fan Finished 100%


SE0116118 Pembukaan Manhole SA Fan Finished 100%
Cleaning Gas Duct (Back Pass) Progress 50%

Keterangan

Koordinator Bidang Willy Pratama


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbin
Pengukuran Clearance Before
Diapgrahm Gland P1-P17
Lifting Turbin

Aux. Turbin
Inspeksi MOT (menunggu pengangkatan
rotor)
Inspection HE pada Vacuum Pump
Buka Penekan Gland Packing No. 1 & 2
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Boiler
Inspection Steam Drum
Disassembly Steam Drum
Lepas Chevron dan Separator di Steam Drum
Pekerjaan Pemasangan Scafolding di furnace
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Aux Boiler
Cleaning Gas Duct (Back Pass)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 26 September 2016
1 Turbin 1

SE011613 Lifting Rotor Turbin Finsihed 100%

Pengangkatan bearing lower no. 1dan no.2 Finsihed 100%


NDT PT Bearing no.1 dan no.2 Finsihed 100%
Melepas Diapraghm Lower Finsihed 100%
Pengangkatan Bearing Upper No. 1 dan No.2 Progress 10%

2 Aux. Turbin 2
SE0116027 Inspeksi MOT Progress 40%
SE0116059 Inspection HE pada Vacuum Pump
Buka Penekan Gland Packing No. 1 & 2 Progress 80%
Disassembly shaft fan gland steam no.1 Finished 100%
Disassembly shaft fan gland steam no.2 Finished 100%
Cleaning tube shaft gland steam Progress 80%
Repair Lubang Baut fan no.1 dan no. 2 Progress 40%

Disassembly Condensate Pump Progress 50%


Membuka Pompa Back Wash pump Progress
3 Boiler 3
SE0116078 Inspection Steam Drum Progress 40%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 26 September 2016
Disassembly Steam Drum Finished 100%
Lepas Chevron dan Separator di Steam Drum Finished 100%
SE0116124 Pekerjaan Pemasangan Scafolding di furnace Progress 90%
Cleaning dinding boiler Progress 10%

4 Aux Boiler 4
SE0116112 Cleaning Gas Duct (Back Pass) Progress 50%

Buka Cover Bearing ID Fan sisi Coupling Finished 100%

Buka Cover bearing PA Fan sisi Free Finished 100%

Buka Kopling dan pengukuran alignment pada SA Finished 100%


Fan
SE0116124 Inspection Air Heater Progress 75%

Keterangan

Koordinator Bidang Willy Pratama


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 26 September 2016
Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbin

Pengangkatan Bearing Upper No. 1 dan


No.2
NDT PT Bearing Upper no.1 dan no.2
Melepas Diapraghm Upper

Aux. turbin
Inspeksi MOT
Buka Penekan Gland Packing No. 1 & 2
Cleaning tube shaft gland steam
Repair Lubang Baut fan no.1 dan no. 2
Disassembly Condensate Pump
Inspeksi Expantion Tank

Boiler
Cleaning dinding boiler
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Inspection Steam Drum

Aux Boiler

Cleaning Gas Duct (Back Pass)


Buka Cover Bearing ID Fan sisi free
Buka Cover bearing PA Fan sisi Coupling

Buka Cover bearing SA Fan sisi Coupling


Inspection Air Heater

Project Manager Sugianto Saeran


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Site Manager Mudjianto


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 01 Oktober 2016 (hari ke-13)
1 Turbin 1
SE011613 Cleaning baut turbin Progress 100%
Rotor Posisi Progress 100%
NDT PT Diapraghm lower Progress 100%
NDT PT Rotor Progress 1%

2 Aux. turbin 2
SE0116027 Inspeksi MOT Progress 40%
SE0116059 Inspeksi Condensate Pump no. 1
Disassembly Condensate Pump no. 1 Finished 100%
Identifikasi & pembahasan temuan Progress 50%
ketidaksesuaian
Cleaning rumah impeller dan Discharge Cover Finished 100%
SE0116027 Disassembly Jacking Oil Pump no. 2 Progress 50%
Disassembly SAC No. 3 Progress 10%
Membuka manhole dan Storage Deaerator Progress 40%
Cleaning shaft impeller dan casing CCWP Progress 50%

Identifikasi & pembahasan temuan Progress 50%


ketidaksesuaian di CCWP
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 01 Oktober 2016 (hari ke-13)
Boiler 3
SE0116078 Inspection & Cleaning Steam Drum Progress 70%
Pengelasan Crack dinding 45%
SE0116124 Cleaning Coal Bunker Progress 70%
Pasang Bearing ID Fan Progress 50%
Melepas Coupling PA Fan (Pemasangan Scafolding) Progress 100%

Melepas Cover atas PA Fan 100%

Melepas Cover bawah sisi DE PA Fan Progress 50%

Retubbing Boiler (Preparation) Progress 10%


Melepas Coupling SA Fan Finshed 100%

4 Aux Boiler 4

SE0116112 Cleaning Gas Duct (Back Pass) Progress 0%

SE0116124 Inspection Air Heater Progress 75%

Keterangan
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 01 Oktober 2016 (hari ke-13)
Keterangan

Koordinator Bidang Willy Pratama


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbin
NDT PT Rotor

Aux. turbin
Inspeksi MOT
Disassembly Condensate Pump
Disassembly Jacking Oil Pump no. 2
Disassembly IAC
Membuka manhole dan Storage Deaerator
Cleaning CCWP
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Boiler
Inspection & Cleaning Steam Drum
Pengelasan Crack dinding
Cleaning Coal Bunker
Pasang Bearing ID Fan
Melepas Cover bawah sisi DE PA Fan

Retubbing Boiler (Preparation)

Aux Boiler

Cleaning Gas Duct (Back Pass)


Inspection Air Heater
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 02 Oktober 2016 (hari ke-14)
1 SE011613 Turbin 1
NDT PT Rotor Progress 1%
Melepas Blade Ring Curtis Upper Finished 100%
Melepas Blade Ring Curtis Lower Finished 100%
Memasang Diapraghm Lower Progress 20%

2 Aux. Turbin 2
SE0116027 Inspeksi MOT Progress 40%
SE0116059 Inspeksi Condensate Pump no. 1 Progress 50%

Identifikasi & pembahasan temuan ketidaksesuaian Progress 50%

SE0116027 Inspeksi Jacking Oil Pump Progress 70%


Inspeksi SAC Progress 20%

Cleaning Inspeksi No. 3 Finished 100%

Disassembly SAC No. 2 & 3 Finished 100%


Inspeksi Deaerator Progress 40%
Membuka Manhole Deaerator Finished 100%

Cleaning Deaerator Progress 70%

Inspeksi CCWP
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 02 Oktober 2016 (hari ke-14)
Cleaning Shaft Impeller dan Casing CCWP Finished 100%
Identifikasi & pembahasan temuan Progress 70%
ketidaksesuaian
Pengukuran Dimensi Shaft dan Impeller Progress 50%
Inspeksi Turning Gear Progress 30%
Disassmbly turning Gear Finished 100%

3 Boiler 3
SE0116078 Inspection & Cleaning Steam Drum Progress 80% SE0116078
Pengelasan Crack dinding Progress 60%
SE0116124 Cleaning Coal Bunker Progress 75% SE0116124

4 Aux Boiler 4
SE0116112 Cleaning Gas Duct (Back Pass) Progress 0% SE0116112
SE0116124 Inspection Air Heater Progress 75% SE0116124
Inspeksi ID Fan Progress 30%

Pasang Bearing ID Fan Progress 50%


Inspeksi PA Fan Progress 40%
Melepas Cover bawah sisi DE PA Fan Finished 100%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 02 Oktober 2016 (hari ke-14)
Melepas Bearing sisi NDE Finished 100%
Melepas Bearing sisi DE Progress 1%

Keterangan

Koordinator Bidang Willy Pratama


Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbin
NDT PT Rotor
Memasang Diapraghm Lower

Aux. turbin
Inspeksi MOT
Inspeksi Condensate Pump no. 1
Identifikasi & pembahasan temuan
ketidaksesuaian
Inspeksi Jacking Oil Pump
Inspeksi SAC
Cleaning Inspeksi No. 4
Inspeksi Deaerator
Cleaning Deaerator
Inspeksi CCWP
Identifikasi & pembahasan temuan
ketidaksesuaian
Pengukuran Dimensi Shaft dan Impeller
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Boiler
Inspection & Cleaning Steam Drum
Pengelasan Crack dinding
Cleaning Coal Bunker

Aux Boiler
Cleaning Gas Duct (Back Pass)
Inspection Air Heater
Inspeksi ID Fan
Pasang Bearing ID Fan
Inspeksi PA Fan
Melepas Bearing sisi DE
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


Site Manager Mudjianto
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 06 Oktober 2016 (hari ke-18)
1 SE011613 Turbin 1
Pengangkatan Lower Casing Blade Ring Curtis Finished 100%
Persiapan Pengambilan data Clearance Labyrinth Finished 100%
seal
Cleaning Area Turbin Finished 100%
Cleaning Rotor Turbin Finished 100%
Pemasangan Upper Labyrinth Progress 45%

2 Aux. Turbin 2
SE0116027 Inspeksi MOT Progress 80%
Disassembly Filter MOT Finished 100%
SE0116059 Inspeksi Condensate Pump no. 1 Progress 50%
SE0116027 Inspeksi Jacking Oil Pump Progress 70%
Inspeksi Deaerator Progress 50%
Inspeksi CCWP Progress 30%
Inspeksi Turning Gear Progress 30%
Inspeksi CWP Progress 30%
Pengambilan data Bushing Finished 100%
Pembuatan Spesial Tools (run Out) Finished 100%
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 06 Oktober 2016 (hari ke-18)
Inspeksi Shaft Gland Cooler Progress 50%
Tes Kebocoran Finished 100%

3 Boiler 3
SE0116078 Cleaning Coal Bunker Progress 80%
SE0116124 Mobilisasi Tools dan Meterial Penggantian (Sparator, Progress 50%
Chevron)
Memasang Gland Manhole Progress 40%
Pelepasan Supporting di steam drum Progress 50%
Retubbing Boiler Progress 35%
Remove tube (20 ea) Progress 60%
Bevel Tube Progress 40%
Install Tube no 3, 13, 16, 18 Finished 100%

4 Aux Boiler 4
SE0116112 Cleaning Gas Duct (Back Pass) Progress 0%

SE0116124 Inspection Air Heater Progress 75%

Inspeksi ID Fan Progress 30%

Pasang Bearing ID Fan Progress 50%


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 06 Oktober 2016 (hari ke-18)
Inspeksi PA Fan Progress 40%
Inspeksi PA Booster Fan Progress 50%
Disassembly Bearing Finished 100%
Inspeksi SA Fan Progress 30%
membuat Spesial Tools SA Fan Finished 100%
Disassembly Bearing DE Finished 100%
Disassembly Bearing NDE Progress 50%
Inspeksi BFP Progress
Pengukuran Clearance Jurnal Progress 100%
Pengecekan Clearance Thrust Progress 100%
Cleaning Bearing Journal Finished 100%

Pengambilan data Clearance After Cleaning Progress 70%


Penetrant Test Progress 10%
Expantion Joint Progress 15%

Keterangan

Koordinator Bidang Willy Pratama


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN
BIDANG MEKANIK
Pekerjaan Yang Telah Dilaksanakan (Work Has Progress
No Tag No. Keterangan No Tag No.
Been Done)
Tanggal : 06 Oktober 2016 (hari ke-18)
Semua Bidang PPC Derry Ferdiansyah PT PJB SERVICES
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Turbin

Aux. Turbin
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Boiler

Aux Boiler
SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Project Manager Sugianto Saeran


SERIOUS INSPECTION
PLTU AMURANG UNIT 2
2016
LAPORAN HARIAN

Pekerjaan Yang Akan Dilaksanakan Besok Keterangan


(Work To Do)

Site Manager Mudjianto

Potrebbero piacerti anche