Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
IFI
INVESTAMA (CARGILL)
LOCATION : AIR DEKAKAH , MANIS MATA , KABUPATEN KETAPANG , KALIMANTAN BARAT 78864
IFI 1
TABLE OF CONTENTS
A 2
2 PIPE MATERIAL
The HDPE pipes for POME at the Biogas Plant are used particularly within the area of the Raw
POME Treatment System, Recirculation Pump and Sludge Effluent System. Biogas pipes are
used within the area of the Reactor Gas Ring, Venting Gas, Reactor Outlet, Scrubber, Heat
Exchanger, Blower, Gas Engine and Flare Unit. The pipes that are used to transport Raw POME
from the Palm Oil Mill to the cooling pond is placed underground, and flange is installed to be
used when the underground pipe rises to ground elevation. The selection of HDPE pipes for
POME fluids, and HDPE and Stainless Steel pipes for biogas is so that it can handle the
corrosive properties of POME and biogas. With the fluid pressure at the Biogas Plant reaching
a pressure of around 4 bars, HDPE (PE100) pipes has a maximum design stress of 80 bar to 100
bar and whereas Stainless Steel SCH10 is sufficient to handle the pressure stress.
3 PIPING ARRANGEMENT
Installation of pipes at the Biogas Plant must be arranged in a neat and orderly manner so to
avoid clash between pipes with pipes or pipes with cables. Pipeline arrangements made by
contractors must follow the drawings made by the Piping Designer and reviewed by the
Piping Engineer.
2D and 3D Drawing required includes:
4 PIPE INSTALLATION
The activity that follows after the engineering design are the procurement of materials and
installation of pipes. In order for all pipes, fittings and valves to be purchased to meet technical
specifications, such as type, material, size, dimension and quantity, a material take-out (MTO)
document is used as a document of reference to act as an offer to be made for Vendors.
At the stage of pipe installation, things that must be considered are:
PROCEDURE FOR PIPING WORKS
A 3
a. All required pipes, fittings and valves must match the data on the MTO
b. Pipe spool work can be done at workshops using an isometric drawing as reference
c. Determination of the type, size, location of pipe support must follow the Piping Support
Layout and Pipe Support Detail Drawing provided by the Engineering Team.
d. Installation of penetrate pipes at concrete pond must be carried out simultaneously
when casting concrete by ensuring the correct leveling of position and elevation of the
pipe / nozzle.
e. To ensure that a pipeline is installed correctly and accordingly, each coordinate points
and elevation must be checked using a guideline based on the 3D drawing and
isometric provided by the Engineering Team.
B. CUTTING
A 4
4. Pipes with a large diameter cannot use high speed pipe cutters, so an alternated method
to be used is as follow:
Carbon pipes can be cut automatically or manually be done by acetylene oxygen gas
welding
1. The form of Grooves for welding must be in accordance with the welding process to be
carried out, and the contours formed must be able to accommodate the formation of
a perfect connection. In principle, all grooves must be produced in accordance with
the Welding Procedure Specification (WPS).
2. Carbon steel pipes and low alloy steel that have a wall thickness of less than 4 mm
must have a little chamfer at the ends.
3 . The ends of the piping components to be connected must be parallel and to be as
straight as possible with tolerances of pipe diameter and thickness according to Table
2 and ASME B16.9
Table 1: Factory-Made Wrought Buttwelding Fittings, and appropriate root face and root
gap tolerances made with the WPS and PQR Procedure specifications. If the end of the
piping component has an internal misalignment of more than 1.6 mm, the excess
thickness must then be cured at an angle of 30°, as shown in figure 5.1. The trimming
process must be done as smooth as possible, and the minimum thickness requested
must be maintained even though the trimming process has been done.
6 PIPE TESTING
In order for the pre-commissioning of the Biogas Plant to run accordingly, the installed piping
must first be tested. Testing may either be done by hydrotest or flushing method.
PROCEDURE FOR PIPING WORKS
A 5
The reference code used in the hydrotest follows ASME Section VIII Div. 1 Latest Edition (Rules for
Construction of Pressure Vessels) and ASME V Latest Edition (Non Destructive Examination). This
pressure test uses water to determine if any leakage is present within the pipe.
• Using cleaning fluids available on site, usually water and compressed air
• Prepare the tissue to be cleaned, this determines the volume of water used and the time
needed.
• According to the process function in the system, the POME piping network is cleaned
using water, while the biogas piping network will be cleaned using air.
• If possible the cleaning fluid must flow from top to bottom.
• The main header must be cleaned off before connection of piping network.
• Dead end must be avoided, if it is not possible to clean it separately
• Cleaning fluids may not pass through piping inside a heat transfer instrument unless it has
been cleaned off.
• Cleaning fluids must not pass through pumps and blowers. The network must be
separated first.
• To withstand the weight of a large diameter pipe, a piping support must be installed to
anticipate removal of it from the main line.
A 6