Detailed Technical report:

Date: 01/10/2019

Issue: Around 15 Cassette type AC units in the SBC facility; Comprising of the units in NH-1 Housing; NH-2 Offices and OASIS center in Equipment out of order
list. This due to non-availability of the spare PCB of the kind for Mnfr: Samsung with the drain pump in the local market. As a remedy to this long pending issue
the existing units (Mnfr : Samsung ) were replaced with Zamil Air conditioner Cassette type units ( 2 tons).

Action taken: Installation of the Cassette unit 2 ton (Mnfr: Zamil Air conditioners) as a remediation to faulty corridor units at Building NH-1; NH-2 and Oasis
Centre.

List of equipment’s replaced with location details:


S.No Scheduled Day Bldg Floor Unit number Issues Remarks
Date of
installation
1 9-9-2019 Mon NH-1 Third floor 3-D-3 Near room A-332 No power as of now; PCB issue. Installed new AC unit
2 10-9-2019 Tue NH-1 Third floor 3-E-2 Near room A-320 No power as of now; PCB issue. Installed new Ac unit
3 11-9-2019 Wed NH-1 Third floor 3-F-3 Near room A-303 No power as of now; PCB issue. Installed new AC unit
4 15-9-2019 Sun NH-1 Second floor 2-D-3 Near room A-238 Unit to be replaced; Motor / PCB/ Fan Installed new AC unit
issue
5 16-9-2019 Mon NH-1 Second floor AS-213-B Lounge No power as of now; PCB issue. Installed new AC unit
6 17-9-2019 NH-2 First floor I.T room No power as of now; PCB issue. Installed new AC unit
7 17-9-2019 NH-2 Second floor I.T room No power as of now; PCB issue. Installed new AC unit

8 21-9-2019 Sat NH-1 First floor Laundry room Unit recurring breakdown; PCB issue Installed new AC unit

9 22-9-2019 Sun NH-1 First floor 1-A-2 Near meeting PCB issue ; fan motor jam; Installed new AC unit
room A-2
10 28-9-2019 Sat OASIS Third floor Lobby neat lift PCB Issue; Installed new AC unit

11 24-9-2019 Tue NH-2 First floor Corridor A/C Near room PCB issue ; Fan not working Transferred spare from BS108 unit
B-116
12 25-9-2019 Wed NH-2 First floor 1-A-1 PCB issue ; Fan not working Transferred spare from BS208 unit
13 17-9-2019 Tue NH-1 Second floor 2-E-2 Near room A-220 Unit Running (Recurring breakdown) Working now with pcb replacment
14 18-9-2019 Wed NH-1 Second floor 2-F-1 Near room A-215 PCB error ; Motor jam ( Need to Fan motor replaced
replace)
15 19-9-2019 Thu NH-1 First floor Janitor room, near room PCB issue ; Fan not working Fan motor form AS-231
A-114 Replaced the spare from existing
removed unit.
Breakdown cost efficiency:
Item: 11; 12; 13; 14; 15

11 24-9-2019 Tue NH-2 First floor Corridor A/C Near room PCB issue ; Fan not working Transferred spare from BS108 unit
B-116
12 25-9-2019 Wed NH-2 First floor 1-A-1 PCB issue ; Fan not working Transferred spare from BS208 unit
13 17-9-2019 Tue NH-1 Second floor 2-E-2 Near room A-220 Unit Running (Recurring breakdown) Working now with pcb replacment
14 18-9-2019 Wed NH-1 Second floor 2-F-1 Near room A-215 PCB error ; Motor jam ( Need to Fan motor replaced
replace)
15 19-9-2019 Thu NH-1 First floor Janitor room, near room PCB issue ; Fan not working Replaced the spare from existing
A-114 removed unit AS-231

The spare fan motor residual to the one unit failed because of PCB was utilized to clear the work orders as depicted in the above table line items 11
12 13 14 and 15.

Thus, unit cost of Cassette unit: 4500 SAR.

Total cost saved: 4500* 5 = 22500 SAR.