Sei sulla pagina 1di 13

THE RED SEA DEVELOPMENT COMPANY (TRSDC)

DESIGN & BUILD


5,000 WORKERS ACCOMMODATION VILLA
CONSTRUCTION

METHOD STATEMENT FOR LIFTING OF


ACCOMMODATION UNITS SINGLE & DOBLE STORY

CODE DESCRIPTION

1 WORK MAY PROCEED


REVISE AND RESUBMIT WORK MAY PROCEED SUBJECT
2
TO INCORPORATION OF CHANGES INDICATED
3 REVISE AND RESUBMIT. WORK MAY NOT PROCEED
4 REVIEW NOT REQUIRED FOR INFO ONLY
5 CANCELLED / DELETED

Name:
Date:
Signature:

A 28 Oct 2019 DE AR PR Issued for Approval

REV. DATE ORIGINATOR REVIEWED APPROVED DESCRIPTION


THIS DOCUMENT IS INTENDED FOR USE BY ARCCO/SPEEDHOUSE JV AND ITS NOMINATED CONSULTANTS, CONTRACTORS, MANUFACTURERS AND
SUPPLIERS.

ORIGINATOR:

ARCCO / SPEEDHOUSE JV REV 1 Discipline

DOC No:R11-T02B02-ASH-MTS-CI-0020 00 Civil


Revision Description

Rev. No. Section Revision Description


A All Issued for Approval

HOLDS
Rev. No. Section Description

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 2OF 13
Table of Contents

1.0 PURPOSE ....................................................................................................................................................4


2.0 SCOPE .........................................................................................................................................................4
3.0 DEFINITIONS .............................................................................................................................................4
4.0 EQUIPMENTS.............................................................................................................................................4
5.0 RESPONSIBILITY ......................................................................................................................................4
6.0 COMPETENT RIGGER ..............................................................................................................................5
7.0 PRE LIFT CHECK .......................................................................................................................................5
8.0 PROCEDURE AND METHOD...................................................................................................................6
9.0 ATTACHMENTS ........................................................................................................................................7
9.1 SITE EXECUTION PLAN. .....................................................................................................................7

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 3OF 13
1.0 PURPOSE
This procedure details the control measure to be applied when using mobile
cranes to lift, load and install modular accommodation units.

2.0 SCOPE
This procedure applies to the use of mobile cranes which normally lift loads
independently. This procedure applies to lift.

3.0 DEFINITIONS

3.1 COMPANY The Red Sea Development Company

3.2 CONTRACTOR ARCCO / SPEEDHOUSE JV


4.0 EQUIPMENT

4.1 CRANE & LIFTING ACCESSORIES


 For the purpose of this procedure, a crane is defined as the equipment
or machinery used to lift materials and units into place, and such
equipment and its operator must have third party certifications.
 All lifting accessories like slings, D-shackles must be proof load tested
and have third party inspected certificates prior to enter the site.
 All lifting gear shall be inspected daily by Riggers and log sheet shall be
maintained. Color code for the month shall be wrapped around the lifting gear.
Any damaged lifting gear shall be marked "Not fit for use" and then removed
from site.

5.0 RESPONSIBILITY

5.1 Contractor Site Engineer in conjunction with the HSE Officer, Supervisor /
Foreman shall be responsible for overall execution of the works carried out
during the lifting operations.

5.2 The Certified competent lifting operations supervisor is directly responsible for
the lifting activities carried out on site.

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 4OF 13
5.3 Contractor Civil Engineer is responsible for verifying the soil condition and the
underground services.

5.4 Contractor HSE officer shall be responsible for verifying the crane, operator and
rigger valid certificates before lifting commence.

5.5 Crane operators with valid certification authorized to operate the class of
equipment as noted on the certification.

5.6 Only Crane operators with valid certification will be authorized to operate cranes
on site.

5.7 The crane operator is responsible for Complying with all applicable regulations
and codes of practice including customer restrictions and TRSDC job site-
specific requirements.

5.8 Operating cranes and heavy lift equipment within the specifications provided by
the manufacturer, operator manuals, load charts, and operator notes.

5.9 This includes pre-start and post-start inspection, maneuvering skills, shutdown
and Securing procedure.
6.0 COMPETENT RIGGER
The competent rigger is responsible for completing the pre-lift safety checklist
and performing rigging in accordance with TRSDC Procedure and applicable
regulations, including customer restrictions and job-site specific requirements, as
necessary. He shall identify and predict hazards in the surroundings or working
conditions and take prompt corrective measures to eliminate or correct them.

7.0 PRE LIFT CHECK

7.1 For all lifting made with the crane the competent lifting operations supervisor,
Rigger and Crane Operators shall follow the pre lift safety checklist prior to job
execution.

7.2 Site HSE officer shall complete the pre lift safety check list prior to starting of
the lifting activities.

7.3 The Site HSE officer shall examine the records to establish that the crane is
certified thorough a TRSDC approved agency and examination issued within the
last 12 months with current boom certification.

7.4 The crane operators shall perform a daily Crane inspection in accordance with
crane manufacturers recommendations to ensure the lifting equipment and

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 5OF 13
systems are in good condition and do not require repair, adjustment, or
lubrication prior to use.

7.5 The crane operator shall also ensure that the outriggers of the crane are fully
extended and that displacement pads are in place.

7.6 A pre-lift discussion shall take place between Erection Supervisor, the rigging
crew and equipment operators prior to making the lifting. Clear communication
between the crane operators and the rigging crew shall be emphasized.

7.7 Lifting operations supervisor shall ensure that tag lines are attached to the load,
ensure that temporary barricades are placed around the work area and that
adjacent work crews are notified of the rigging work operations.

8.0 PROCEDURE AND METHOD

8.1 PLANNING
 Lifting operations should always be planned and a written work plan
should be produced in advance by a competent lifting operations
supervisor who is conversant with this procedure.
 Operators of cranes being used to carry out the Lifting must be trained,
assessed and certified from a third party agencies acknowledged by
TRSDC and conversant with the contents of this procedure.
 During the operation of crane lifting, Safe Working Load and radius
should not be exceeded at any time.
 The individual lifting plans must show the weight capacity of the
slings and shackles, how far the boom will be extended and the radius
it will be operated at in order to confirm a safe lift according to the
load chart prior to the lifting operation.
 Initially the load should only be lifted 1 meter off the ground to ensure
proper slinging and balance prior to allowing lifting to continue. The
1 meter lift will be a hold point for verification.

8.2 SITE WORK

 The competent lifting operations supervisor and rigger must be


trained, assessed and certified as competent in Lifting by TRSDC

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 6OF 13
approved certificate issuing agency.
 One more Rigger shall be engaged in case of any obstruction of direct
vision between Crane operator and Rigger.
 Before any Lifting commences the operation controller must ensure
that the operators have a clear understanding about the work to be
undertaken and the communications to be used, as well as the
procedures being adopted. Banks man /signal man / competent riggers
shall be identified for lifting operation and tool box talks to be
conducted prior to lift, discussing the lift plan and risk associated with
the lifts.
 If any Ladders are used to rich the lifting points in order to secure the
straps, 3- point contact must be maintained at all times.
 Any tools that might be used when working at heights must be secured
by lanyard.

9.0 ATTACHMENTS

9.1 LIFTING EQUPMENT TEST CERTIVICATES

9.2 DRAWINGS OF LIFTING DETIAL.

9.3 CRANE OPERATOR DAILY CHECK LIST.

9.1 SITE EXECUTION PLAN FOR PLACEMENT & INSTALATION OF


ACCOMMODATION UNITS.

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 7OF 13
Following the step by step site execution plan for the Accommodation units.

 Check dimensions and level of prefabricated foundation pears set out on site.
 Position crane next to foundation setup within rich of offloading area.
 Move truck with the building into position.
 With the use of a certified spreader bar, lifting hook extensions and lifting equipment,
lift the unit from the truck with guide lines on opposing corners.
 Swing the unit into position over the foundations controlling it with the guide lines.
 Slowly lower the unit onto the foundations insuring it is in the right position.
 If it is a building consisting of multiple units, proceed in the same manner with the
second, third and fourth ground floor units.
 Position each unit next to the previously placed one and lower into position.
 With all the ground floor units in place and leveled.
 Proceed in the same manner lifting the first floor units into place one by one and placing
them on top of the ground floor units as per the building layout.

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 8OF 13
METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020
FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 9OF 13
METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020
FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 10OF 13
METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020
FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 11OF 13
METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020
FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 12OF 13
LIFTING & VERTICAL TRANSPORTATION EQUIPMENT - CHECKLIST

LOCATION / AREA:

Sl.
Activities / Items to be Inspected Remarks by Safety staff
No.

1 Condition of carnage and hoisting


equipment
2 Valid certification of carnage and
hoisting equipment
3 Competency of crane and hoist
operators
4
Effective use of trained banks men

5
Use of outriggers and floats

6 Equipment storage, issuing and


receiving.
7
Colour Code

General / specific observations:

CONTRACTOR– SAFETY ENGR. APPROVAL


SIGNATURE

NAME

DESIGNATION

DATE

METHOD STATEMENT DOC. NO. R11-T02B02-ASH-MTS-CI-0020


FOR LIFTING OF
ACCOMMODATION REV. 00 DATE: 28 Oct 2019
UNITS PAGE 13OF 13

Potrebbero piacerti anche