Sei sulla pagina 1di 3

Detail Calculation of Quantity for 1.00 Rm of Brick Boundary wall with RCC Beam and column.

[Items are taken from 53-MGNREGA]


Sl. Specification Qty for Qty for 1.00
No No. Item of works Unit
10.00 Rm Rm
1 2 3 4 5 6
1 53.1.1.A.a Earthwork in excavation for foundation trenches of walls, retaining walls,
footings of column, steps, septic tank etc. including refilling (return filling)
the quantity as necessary after completion of work, breaking clods in
return filling, dressing, watering and ramming etc. and removal of surplus
earth with all lead and lifts as directed and specified in the following
classification of soils including bailing out water where necessary as
directed and specified. Upto a depth of 2m below the existing ground
level. In ordinary Soil.

Col. Footing = 5 x 1.00 x 1.00 x


1.20 = 6.00 m³
Total = 6.00 m³ m³ 6.00 0.600
2 53.4.1.1.a Providing brick soling in foundation and under floor with stone/ best
quality picked jhama brick, sand packed and laid to level and in panel
after preparing the subgrade as directed including all labour and
materials and if necessary dewatering, complete.Brick on flat soling.

Col. Footing = 5 x 1.00 x 1.00 = 5.00 m²


Below T/Beam = 1 x 10.00 x 0.25 = 2.50 m²
Total = 7.50 m² m² 7.50 0.750
3 53.2.1.1.a Plain cement concrete works with coarse aggregate of sizes 13mm to
32mm in foundation bed for footing steps, walls, brick works etc. as
directed and specified including dewatering if necessary, and curing
complete (shuttering where necessary shall be measured and paid
separately).In prop. 1:3: 6 (1 cement:3 coarse sand : 6 coarse agg. by
volume).
(a) In prop 1cement: 3 sand :6 coarse aggregate by volume

For Footing = 5x 1.00 x 1.00 x 0.075 = 0.38 m³


Total = 0.38 m³ m³ 0.38 0.038
4 53.18.1.1.c Supplying, fitting and fixing in position reinforcement bars conforming to
relevant I.S. Code for R.C.C. work/ R.B. walling including straightening,
cleaning, cutting and bending to proper shapes and length as per details,
supplying and binding with 20G annealed black wire and placing in
position with proper blocks, supports, chairs, spacers etc. complete.

12 mm dia bar
For Post = 5
x 3.30 x 4 = 66.00 Rm
For Tie Beam = 1
x 10.00x 4 = 40.00 Rm
Total = 106.00 Rm
@ 0.89 Kg/Rm………………………………… = 94.34 Kg

10 mm dia bar
For Jali = 5 x 20.90 =
x 7 x 63.00 Rm
Total = 63.00 Rm
@ 0.62 Kg/Rm………………………………… = 39.06 Kg
1 2 3 4 5 6
6 mm dia MS bar for stirrup

Col, Upto PL = 5 x 9 x =
0.90 40.50 Rm
Above PL = 5 x 14 x =
0.65 45.50 Rm
T.B.(@125 c/c) = 1 x 80 x =
0.95 76.00 Rm
=
Total 162.00 Rm
@ 0.22 Kg/m…………… = 35.64 Kg
Grand Total = 169.04 Qtl Kg 169.04 16.904
5 53.3.1.1.3.a.ii Providing form work of ordinary timber planking so as to give a rough
finish including centering, shuttering, strutting and propping etc., height of
propping and centering below supporting floor to ceiling not exceeding
4.0M and removal of the same for in-situ reinforced concrete and plain
concrete work in:Columns, Pillars, Posts & Strut. Square, Rectangular,
polygonal in plan or any shape like Tee/L etc. having plane vertical face.
Using 25 mm thick plank.

Footing = 5 x 4 x 0.90 x 0.175 = 3.15 m²


Col. Below PL = 5 x 4 x 0.20 x 0.900 = 3.60 m²
For Tie Beam = 1 x 2 x 10.00 x 0.250 = 5.00 m²
Column = 5x 4 x 0.125 x 1.50 = 3.75 m²
Total = 15.50 m² m² 15.50 1.55
6 53.2.2.1.A.b Providing and laying plain/reinforced cement concrete works cement with
coarse sand & 20mm down graded stone aggregate including dewatering
if necessary, and curing complete but excluding cost of form work and
reinforcement for reinforced cement concrete work (form work and
reinforcement will be measured and paid separately). In sub - structure up
to plinth level.Foundation, footing, columns with base tie and plinth beam,
pile cap, base slab, retaining walls, walls of septic tank, inspection pit and
the like and other works not less than 100mm thick up to plinth level. M20
grade concrete or prop. 1.1.5.3.Without using admixture, plasticiser.

A) In Sub-structure
Col. Footing = 5 x 0.90 x 0.90 x 0.10 = 0.41 m³
5 x 0.90² + 0.20² x 0.15 = 0.32 m³
2
Col. Below PL = 5 x 0.225 x 0.20 x 0.90 = 0.20 m³
Tie Beam = 1 x 10.00 x 0.25 x 0.20 = 0.50 m³
Total = 1.43 m³
Deduct for Joints 5 x 0.20 x 0.20 x 0.25 = 0.05 m³
Total = 1.38 m³
(B) In super structure from plinth level up to 1st floor level.
Column = 5 x 0.125 x 0.125 x 1.50 = 0.12 m³
Grand Total = 1.49 m³ m³ 1.49 0.149
7 53.4.1.4.I.a Brick work in cement morter with 1st class brick including racking out
joints and curing complete as directed in structure.In Sub-structure upto
plinth level including dewatering if necessary.In proportion 1:3.

Wall = 1 x 10.00 x 0.125 x 1.50 = 1.88 m³


Total = 1.88 m³
Deduct for columns
Column = 5 x 1.50 x 0.125 x 0.125 = 0.02 m³
Total = 0.02 m³
Net Total = 1.85 m³ m³ 1.85 0.185
1 2 3 4 5 6
8 53.6.2.2.A.c 15 mm thick Cement plaster in single coat onsingle or half brick wall for
interior plastering up to 1st floor level including arises, internal rounded
angles, not exceeding 80mm girth and finished even and smooth
including curing complete as directed. On rough side.In cement mortar
1:5

Wall with beam


& column
= 1 x 2 x 10.00 x 1.75 = 35.00 m²
Total = 35.00 m² m² 35.00 3.500