12 mm dia bar
For Post = 5
x 3.30 x 4 = 66.00 Rm
For Tie Beam = 1
x 10.00x 4 = 40.00 Rm
Total = 106.00 Rm
@ 0.89 Kg/Rm………………………………… = 94.34 Kg
10 mm dia bar
For Jali = 5 x 20.90 =
x 7 x 63.00 Rm
Total = 63.00 Rm
@ 0.62 Kg/Rm………………………………… = 39.06 Kg
1 2 3 4 5 6
6 mm dia MS bar for stirrup
Col, Upto PL = 5 x 9 x =
0.90 40.50 Rm
Above PL = 5 x 14 x =
0.65 45.50 Rm
T.B.(@125 c/c) = 1 x 80 x =
0.95 76.00 Rm
=
Total 162.00 Rm
@ 0.22 Kg/m…………… = 35.64 Kg
Grand Total = 169.04 Qtl Kg 169.04 16.904
5 53.3.1.1.3.a.ii Providing form work of ordinary timber planking so as to give a rough
finish including centering, shuttering, strutting and propping etc., height of
propping and centering below supporting floor to ceiling not exceeding
4.0M and removal of the same for in-situ reinforced concrete and plain
concrete work in:Columns, Pillars, Posts & Strut. Square, Rectangular,
polygonal in plan or any shape like Tee/L etc. having plane vertical face.
Using 25 mm thick plank.
A) In Sub-structure
Col. Footing = 5 x 0.90 x 0.90 x 0.10 = 0.41 m³
5 x 0.90² + 0.20² x 0.15 = 0.32 m³
2
Col. Below PL = 5 x 0.225 x 0.20 x 0.90 = 0.20 m³
Tie Beam = 1 x 10.00 x 0.25 x 0.20 = 0.50 m³
Total = 1.43 m³
Deduct for Joints 5 x 0.20 x 0.20 x 0.25 = 0.05 m³
Total = 1.38 m³
(B) In super structure from plinth level up to 1st floor level.
Column = 5 x 0.125 x 0.125 x 1.50 = 0.12 m³
Grand Total = 1.49 m³ m³ 1.49 0.149
7 53.4.1.4.I.a Brick work in cement morter with 1st class brick including racking out
joints and curing complete as directed in structure.In Sub-structure upto
plinth level including dewatering if necessary.In proportion 1:3.