Hasang Hydropower Project

Code Item Description Unit Rate


Main Sub. [USD]
100 EARTH & ROCK WORKS
Preparation of construction area by clearing, grubbing and m2 1.5
Preparation of construction stripping. Usable tree trunks to be piled up for loading on
101
area accessible roads. Unuseable bushes, shrubs etc. to be burned or
disposed off.
Excavation and transport of soil including loading and dumping. m3 4.5
102 Transport distance 1,000 m
Excavation of soil
Location : weir, channels, portals, headpond, penstock

Excavation and transport of rock including drilling, blasting, m3 18


loading and dumping.
103 Excavation of rock Transport distance : 1,000 m
Location : Foundation of weir, tunnel portals, channels, penstock,
powerhouse, etc.

Excavation of rock surface layers by using carefully methods like m3 65


scrapping, ripping, hammering, breaking including loading,
transport, dumping and surface cleaning
104 Excavation of rock in layers Transport distance : 1,000 m
Location : Foundation of weir

Dumped rock and soil to be loaded and transported to deposit. m3 1.5


Transport of dumped rock and Distance of transport : 1,000 m
105
soil

Rock bolting of open slopes. Rock bolts fully mortared including m 31.5
drilling, flushing of hole and placing of anchor.
Length: 6.0 m
106 Rockbolting Diameter: 28 mm
Steel Bars, Grade 75 (ASTM) Similar BST 500/550 (DIN)
Location : Any open excavation for tunnel portal, access roads,
powerhouse, etc.

Drainage holes in open excavations, including drilling, flushing, m 2.5


installation of PVC pipe
107 Drainage holes Diameter : 75 mm
Length: 6.0 m
Loaction: Any open excavation

Reinforced steel wire mesh to be delivered, cut and placed T 800


including fastening materials for gunite.
108 Reinforced steel wire mesh Grade 60 (ASTM) similar BST 500/550 (DIN) (100*100*8 mm)

Shotcrete for slope stabilization at open excavation. Concrete m3 240


Class : C25 including all auxiliary materials and works
109 Shotcrete Thickness : as required

Grading and finishing of any type of permanent excavation surface m2 1.5


110 Slope Treatment
in slopes.

200 ROADS & PAVEMENT


Base-Course laid, spread and compacted to form a layer of m3 18
201 approved and specified materials.
Base course layer
Thickness: 35 cm

Binder-Course bituminous, laid, spread and compacted to form a m2 35


202 layer of approved and specified materials.
Binder course bituminous
Thickness : 5.0 cm

Copy of annex 16-2 - BoQ and Cost Estimate2.xlsx - rates 1 of 5


Hasang Hydropower Project

Code Item Description Unit Rate


Main Sub. [USD]
Drainage, side ditches, cross drains, culverts, guard rails and 35
203 Road finishing
lighting

UNDERGROUND EXCAVATION
300
Underground excavation in rock, 0-10° inclined, Including all m3 65
Underground excavation in required material and provisions of power, air, water, draining
301 and light. Removal of muck to a deposit up to 200 m from the
rock
tunnel portal.

Gunite type as required for underground works. m2 25


302 Shotcrete Thickness of gunite: min 10 cm

Rock bolts fully mortared, including drilling, flushing of hole and No. 85
placing of anchor.
303 Rock anchor Steel bars: Grade 75 (ASTM) similar BST 500/550 (DIN)
Diameter: 28 mm
Length: 3.0 m

Reinforced steel wire mesh for gunite to be delivered, cut and T 1,700
304 placed including fastening materials.
Reinforced steel wire mesh
Grade: 60 (ASTM) similar BST 500/550 (DIN)

305 Steel ribs support Steel rib supports T 800


306 Steel lagging Install at the crown above steel ribs T 800
Spot location for type IV support (Estimated 2 NO. every 5 m of No. 105
307 Fore polling, L = 4.0 m
advancing)

400 EMBANKMENT
Cofferdam: Impervious Fill m3 10
With excavated soil material out of required foundation
excavations from deposit area, including loading, transporting,
401 Impervious Fill dumping, processing, spreading in layers and compacting to a
specified density.
Material classification : Impervious cohesionless silt

Backfill to structures m3 8
With excavated soil material out of required foundation
excavations from deposit area, including loading, transporting,
402 Random Fill dumping, spreading in layers and compacting.
Material classification : Random earthfill

Cofferdam: Filter m3 22
With quarried material out of quarries, including drilling, blasting,
loading, processing, transporting, dumping, spreading in layers
and compacting.
403 Filter Distance of transport : Up to 2,000 m
Material classification : Quarried and processed filter material
Grain size : As per gradation curve

Cofferdam: Transition m3 18
With quarried material out of quarries, including drilling, blasting,
loading, eventually processing, transporting, dumping, spreading
404 Transition in layers and compacting.
Distance of transport : Up to 2,000 m
Material classification : Quarried and eventually processed coarse
transition material

Copy of annex 16-2 - BoQ and Cost Estimate2.xlsx - rates 2 of 5


Hasang Hydropower Project

Code Item Description Unit Rate


Main Sub. [USD]
Rip-Rap Cofferdamdam: Rip-Rap m3 10
With boulders from quarries and/or colluvium material, including
405 loding, transporting, and placing
Size of boulders for Rip-Rap: approx. 1m

Gabbions Gabions of broken stones m3 8


Consisting of plastic coated galvanized wire-mesh up to 4 m3, to
406 be supplied, set in place, filled with rock
Placement area: Dam crest

500 DRILLING & GROUTING


Grout-hole, vertical down in confined space with each direction m 14.5
and inclination from vertical up to 30°. To be drilled and flushed
501 Boreholes, vertical for all types of grouting without core recovery
Diameter : 48 mm

Core drilling, vertical down, with each direction and inclination m 150
from vertical up to 30°, with a minimum of 95% core recovery in
rock, including provision of core boxes, core logging.
For testing permeability of grout curtain and determination of
502 Core drilling, vertical final depth of grout-curtain
Diameter : 76 mm
Location : Plinth And Tunnel

Water pressure testing time including mounting and dismounting No. 300
of single packers for water pressure testing from top to bottom,
provision of watermeter pressure gauge, rotary pump, max. 150
503 Water pressure testing L/min, max. 25 bar, and evaluation

Cement injected for curtain grouting in any depth. In stages T 250


provision of grouting equipment including setting up and
removing on site, setting of single packer for each boreholes in
504 Cement grouting steps of 5.0 m
Scope of Application : Curtain grouting and consolidation grouting

600 CONCRETE WORKS


Concrete Works in Open Areas

Concrete for blinding layer, strength class C15. m3 47


601 Blinding Concrete, C15 Surface finish grade: U2

Structural concrete, strength class C25 m3 75


Including construction/contraction joints, waterstops, all auxiliary
works, equipment and materials for transport, placing,
602 Structural Concrete, C25 compaction and surface treatment of the concrete.
Location : All concrete works in open areas, e.g. plinth, intake and
outfall structures, etc.

Copy of annex 16-2 - BoQ and Cost Estimate2.xlsx - rates 3 of 5


Hasang Hydropower Project

Code Item Description Unit Rate


Main Sub. [USD]
Structural concrete, strength class C35 m3 85
Including construction/contraction joints, waterstops, all auxiliary
works, equipment and materials for transport, placing,
603 Structural Concrete, C35 compaction and surface treatment of the concrete.
Location : All concrete works in open areas, e.g. plinth, intake and
outfall structures, etc.

610 Formwork
Formwork F1 m2 10
611 Consisting of sawn boards of even thickness, neatly arranged,
Formwork F1
including all bracings, supports, stripping

Formwork F2 m3 35
Consisting of plain boards, uniformly arranged, permanently
612 Formwork F2 exposed to view, including all bracings, supports, stripping

Formwork F3 m2 55
System formwork consisting of smooth plywood or equipment
613 Formwork F3 material surfaces or tongue-and-groove boards of uniform size
and arrangement, including all bracing, supports, stripping

Extra-over for formwork F2, curved in one direction m2 15


614 Formwork F2 curved
620 Reinforcement
Reinforcement Steel Steel bars as reinforcement steel to be delivered, cut, bent and T 1,750
621 placed, including all supports and spacers
Grade of steel bars: 60 (ASTM) similar BST 500/550 (DIN)

630 Embedded Parts


Supply and installation of embedded parts in first stage concrete T 1,500
631 Embedded Parts

640 Anchors
Anchor holes to be drilled, flushed and grouted, including all m 18
required equipment, auxiliary materials and cement mortar
641 Anchor holes Location : Rock base of plinth
Diameter of borehole : 45 mm

Anchor steel bars as reinforcement steel to be delivered, cut, bent T 1,800


and placed in anchor holes.
642 Anchor steel bars Location: Rock base of plinth
Grade : 60 (ASTM) Similar BST 500/550 (DIN)
Diameter : 28 mm

650 Concrete Works in Tunnels


Concrete for blinding layer in tunnels, strength class C15 m3 47
Blinding Concrete in Tunnels, Lean concrete in all dimensions, surface smoothed, including
651 transporting, placing and compacting of concrete.
C15

Substructural concrete in tunnels, strength class C25 in all m3 75


dimensions. For any structural component or part, including
652 Concrete in Tunnels, C25 transporting, placing and compacting of concrete.

Copy of annex 16-2 - BoQ and Cost Estimate2.xlsx - rates 4 of 5


Hasang Hydropower Project

Code Item Description Unit Rate


Main Sub. [USD]
Backfill Concrete in Tunnels, Backfill concrete in tunnels, strength class C25. m3 75
653
C25
660 Reinforcement
Delivery and placement of steel bars in tunnels, grade 60 (ASTM) T 1,750
661 similar BST 500/550 (DIN).
Reinforcement Steel in Tunnels
As reinforcement steel to be cut, bent and placed, including all
supports and spacers.

Delivery and placement of reinforcement steel wire mesh in T 1,700


Reinforcement Steel Mesh in tunnels and shafts, Grade 60 (ASTM) similar BST 500/550 (DIN).
662 To be cut to size and installed in formwork.
Tunnels

Supply and installation of embedded parts in first stage concrete T 1,500


663 Embedded Parts

680 Formwork in Tunnels


Formwork F2 in Tunnels Formwork F2 in tunnels m2 45
681 Consisting of plain boards, uniformly arranged, permanently
exposed to view, including all bracings, supports. Including all
curvature
Formwork F3 m2 65
System formwork consisting of smooth plywood or equipment
682 Formwork F3 material surfaces or tongue-and-groove boards of uniform size
and arrangement, including all bracing, supports, stripping

Formwork F3 No. 60,000


683 Steel shutter formwork Consisting of steel formwork attached on the movable gantry.
Total length of 12 m long
690 Grouting in Tunnels
Groutholes Grout-hole, to be drilled and flushed for all types of grouting m 6
691 Diameter : 48 mm

Cement injection for contact Cement injected for contact grouting between rock and concrete T 250
grouting lining in tunnel, including flushing of holes, mounting and
694 dismounting of packer and sealing of grout hole after completion.

Copy of annex 16-2 - BoQ and Cost Estimate2.xlsx - rates 5 of 5