CICB Mobile Crane Monthly Checklist
Orlando, FL 32862-1388
* (800) 327-1386 (407) 277-0884 Crane ID #: Capacity:
www.cicb.com

Machine Description & Number


Mark the appropriate boxes
S - Satisfactory
Month
U - Unsatisfactory Jan. Feb. Mar. April May June July Aug. Sept. Oct. Nov. Dec.
Reference Standard
N - Not Applicable
Boom B30.5-2
Boom Extensions, Jibs B30.5-2
W Boom Sheaves B30.5-2
A Fire Extinguisher B30.5-3 & 1926.1433
L Fluid Leaks 1926.1412
K Fluid Levels B30.5-2
A Guards B30.5-1 & 1926.1412
B Hoist Drum(s) B30.5-2
O Hooks B30.5-2 & B30.10-1
U Outriggers/Pads B30.5-1 & 1926.1412
T Structural Welds 1926.1412
Tire Condition, pressure B30.5-2
Wire Rope, Beckets, Pins B30.5-1
Anti-two Block 1926.1412
Presurized Line Systems B30.5-2
O
Safety Devices 1926.1415
P
Brakes 1926.1412
E
Controls/Functions B30.5-2
R
Electrical Equipment B30.5-2
A
Power plant 1926.1412
T
Housekeeping B30.5-2
O
Lights, Signals, Horn B30.5-2
R
Load Charts B30.5-1
Operational Aids B30.5-1 & 1926.1412
Operators Manual B30.5-1 & 1926.1412
C
Steering B30.5-2
A
Swing Locks and Brakes B30.5-1 & 1926.1412
B
Warning Labels 1926.1412
Cab Windows 1926.1412

Inspector's Signature ________________________________________________


If this mobile crane is not utilized on a date, draw a vertical line through the column.
Please Note - An inspector/operator is responsible to bring Unsatisfactory items to the attention of his/her supervisor and/or maintenance department. CICB has
put this Monthly Checklist together as a guide and the operator/inspector should always refer to the manufacturer to ensure that all required items are being
inspected at the proper frequency.
© Crane Inspection Certification Bureau, 2018
CICB Monthly Rope & Hook Checklist
**This form shall be used for each piece of rope.**

Rope Description: Mfr. Breaking Strength: Application:

Inspection Points Month


W i r e R o p e Jan. Feb. Mar. April May June July Aug. Sept. Oct. Nov. Dec.
Nominal Diameter B30.5-2
Measured Diameter B30.5-2
Rope Damage B30.5-2
Broken Wires (1) Strand / (1) Lay B30.5-2
Broken Wires (1) Lay B30.5-2
Broken Wires at End Fittings B30.5-2
Wear B30.5-2
Corrosion B30.5-2
H o o k
Safety Latch B30.10-1
Deformation/Twists B30.10-1
Deformation/Throat Opening B30.10-1
Wear - Bowl B30.10-1
Wear - Eye B30.10-1
Cracks, Nicks, Gouges B30.10-1
Attachment Points B30.10-1
Self-Locking Operation B30.10-1

Inspector's Signature ________________________________________________


If this mobile crane is not utilized on a date, draw a vertical line through the column.

Please Note - An inspector/operator is responsible to bring Unsatisfactory items to the attention of his/her supervisor and/or maintenance department. CICB has
put this Monthly Checklist together as a guide and the operator/inspector should always refer to the manufacturer to ensure that all required items are being