Parent order costing shows actual costs after goods issue and/or activities confirmation
No costs are updated in original orders for goods issue and confirmations
Target costs are are updated after goods receipt for original orders. Actual costs flow to
the original orders only after settlement of the combined production order.
Actual variable quantity needs to be posted for activities
Yield is confirmed against individual orders where as activities are confirmed against
parent order
Before confirmation
After confirmation
Example
Goods issued and activities confirmed for combined order.
Combined order is settled to original orders. Costs are distributed in planned prduction
order quantity.
Combined order after settlement
Original orders show the actual costs. Production order no 27 is explained below
Variance calculation for 27
27 before settlement
27 after settlement
Configuration settings
http://help.sap.com/bp_fm603/BBLibrary/HTML/372_EN_FR.htm
However, there is no system restriction in regard to the combination of process orders with
different header material or the mix of MTO and MTS orders.
COOIS
Confirmation quantity is updated in combined as well as in original orders in COOIS object
overview
11009 is the allocation cost element linked to activity type 20009 and 41001050 is the
consumption account.