qty
Sl No. Item Description Unit Scope Start Date End Date Man power Required Remarks
pending
11 KV Line Switchgear Erection &
2 Set 1 1 20.01.2020 31.01.2020 Fitter -4 Nos, welder -2 Nos Erection Completed, Testing is not started
Comissioning
2.02.2020 Fitter
-3 Nos ,welder - 2 Nos.
3 Earthing works Km 9 1 20.01.2020
Supervisor - 1 No. under progress
12.1 kV 5.8 MVAR capacitor bank Civil
4 Set 2 2 20.01.2020 05.02.2020 Fitter -4 Nos and welder -2 Nos
foundation.
LC required from kptcl, latest request letter issued to EE KPTCL Ref:
5 66 KV CTT Tower Erection Nos. 2 1 22.01.2020 22.01.2020 Fitter - 18 Nos letter KEC/ KPTCL/ITI on 13.01.2020
Relay testing completed & 2 No Bays will be charged after 1.No CTT
6 66 KV GIS Line Bays Comissioning Bay 6 3 22.01.2020 22.01.2020 Erection and remaining 1 no. bay will be charged after exist 31.5 MVA
Transformer cahrged with the New GIS Bay.