Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ES KOM P P P T R A INI NG
0 1 AUG UST 2 0 1 7
Concluding remarks
Risk factors in PPP projects - Basics
Example: Channel Tunnel Project
1986 - TML (Trans Manche Link), a consortium of construction companies won
50 year concession
Eurotunnel – created as an SPV late in the process
TML put little equity in Eurotunnel – main equity through four public offerings
to small shareholders
Loans financed by consortium of 100 banks
Safety standards evolved as project progressed affecting design – costs
doubled to £10 billion
Revenue forecasts for Eurotunnel were disastrously optimistic!
Revenues of £287 million vs. forecast of £440 million in 1995
4
Example: Ninoy Aquino International's Terminal 3 (Manila, Philippines)
In 2003, Philippine Government stopped work & Supreme Court declared the BOT
contract void
5
Example: El Alto water concession
6
Risk Identification – what happened in the various project examples
In technical parlance,
Not only did ‘risks materialize’
But also their impact could not be contained leading to debilitating effect on
the project outcomes
Relevant risks over the project life cycle
Development Construction Operation
12
Risk Mitigation
Comprises:
• Risk Elimination: If risks are too high, should the project be undertaken?
• Risk Reduction: e.g. clear specifications, high quality feasibility studies
• Risk Transfer through contracts
– Between Government department & private developer
– Between private developer & sub-contractors, suppliers, insurers, users
• Allocating risk to the party best placed to deal with it
– Political Force Majeure / Change in Law - Government
– Land acquisition
9
Contracts reflect allocation &
mitigation of risks - Roads Highways
Authority
JV Partners
Concession Agreement
Escrow Bank
State Government
Lenders
• Design Risks • Pre-construction risks • Risk of debt not being • Risk to lenders of
• Construction Risks • Clearances serviced concessionaire not
performing
• Traffic & Toll rate Risks • Competing Facility Risk • O&M exp.not paid
Project Background
• Government notifies a port site to kick start economic development
• Obtains long tenure multilateral loan for port construction
• Government decides to transfer the project to private sector on PPP basis
• Government appoints a consultant to manage bid process
• Project is structured as a B/-O-M-S-T (Build-Own-Manage-Share-Transfer)
• Existing assets (berths, equipment, sunk costs – dredging) to be transferred
to SPV on OMST basis
• New assets to be constructed and commissioned – (berth, equipment, etc.)
Case Example: Z-PORT
International competitive bidding was undertaken
Financing risk Delay in financial closure due to less robust project viability
Maintenance risk Greater than expected maintenance costs due to poor state of movable assets
Mechanical equipment had significantly depreciated as a result of being unused for several
years
Key to-dos to make projects bankable & attractive for pvt. Sector
Adequate project preparation – for high private interest, getting
competitive bids
Sensible risk allocation between government & private developer
Transparent & balanced framework for tariff setting (including trajectory)
Viability enhancement measures if required
Measures to enhance lender comfort
24
Logical risk allocation is at the heart of PPPs (and bankability)
Risks typically allocated to private sector:
- Design, technology and construction risk
- Demand / traffic risk (PPAs mitigate this in power projs.)
- Operating / performance risk
- Financing risk
Shared risks
- Force majeure
- Demand risk (in some
cases)
25
Logical allocation of risks matters for attracting private investments
Lessons from oil field auctions in Mexico (July and Sept 2015)
2 rounds of oil fled development auctions in Mexico
◦ July’15 auction managed to find buyers for only 2 of
the 14 blocks; Sept’15 round faired better – 3 of 5
blocks on offer found buyers despite lower prices (9
bids received)
Improved response credited to lower risk
perception and rationalized bidding rules
◦ Advance information on minimum production share (below
which bids would be rejected)
◦ Reduced bid guarantee requirements
◦ Clarification on circumstances under which the regulator, the
National Hydrocarbons Commission, could rescind a contract
77-year monopoly of Pemex, the state oil firm, ended in
2015
Managing demand risk
Demand / traffic is a prominent risk faced by private developers – given high investment requirements, returns
are very sensitive to lower than expected demand
27
Measures to enhance lender comfort
In addition to structuring viable projects and mitigating risks – some specific mechanisms
enhance lender comfort:
Taking reasonable securities
◦ Finance guarantees provided by govt. – loan guarantees (govt. guarantees debt in case the project company
fails) and re-financing guarantees [e.g. Loan Guarantee Instrument for Trans-European Transport Network
Projects set up in 2008 to backstop senior debt servicing during initial ‘ramp-up’ periods of transport PPPs]
◦ Possibility to take over movable assets in case of default
◦ Clear procedures for appointment of liquidators
Contingent liabilities matter: accumulation of CLs can have a tangible impact on sovereign ratings
The present fiscal policy environment (in Namibia) not geared up to accommodate PPPsZ
◦ CLs in the case of PPP projects are seen as ‘unlikely’ risks (assuming good contracting), therefore are different from
government guarantees
Impact of CLs on sovereign ratings
Excessive CLs can lead to
adverse impact on sovereign
credit ratings
As per a guidance from S&P
CLs below 30% of GDP are
considered as ‘limited’ / low
31
The work in front of us…
Task definition:
◦ Review of the present mechanism for recognition, accounting and reporting of guarantees / CLs
◦ Recommend an update to the framework for accounting of CLs that is suitable for PPP projects
(high value but low probability CLs)
32
Conclusion
Risks are an integral part of any infrastructure project
It is important to upfront identify all possible risks that would impact the progress of the
project
The consequence and impact of each risk needs to be assessed
Risks then need to be allocated to the entity that is best suited to manage such risks –
through project concession and associated contracts
The objective is not to maximise risk transfer but optimise risk allocation!
Risk allocation is the key step that is used for developing contracts
Thank You Contact: Saurabh Suneja
Director, Public Private Partnerships
Ministry of Finance, Republic of Namibia.
Tel: +264 61 2092083/2557 (O) +264 856331146 (M)
Email: saurabh.suneja@mof.gov.na