IMPORTANT NOTES
A GENERAL
PARAPET WALL 1. ALL DIMENSIONS ARE IN MILLIMETER UNLESS OTHERWISE SPECIFIED & LEVELS ARE IN METER.
2. DO NOT SCALE THE DRAWING, ONLY WRITTEN DIMENSIONS SHALL BE FOLLOWED.
3. THE DRAWING MUST BE READ IN CONJUNCTION WITH ALL OTHER RELEVANT DRAWING I.E. ARCHITECTURAL, ELECTRICAL &

00 9
T.O.C. STRUCTURAL DRAWING. (GA DRAWING OF MANUFACTURER)
9.45 LVL.
4. ALL THE WORK SHALL BE CARRIED OUT AS PER RELEVANT FIELD QUALITY PLAN APPROVED BY GETCO.
RCC SLAB & BEAM
5. IN CASE OF ANY DOUBT OR DISCREPANCIES, PLEASE CONTACT ENGG. CELL. NO ASSUMPTIONS SHALL BE MADE.
F FALSE CEILING RCC LINTEL F
6. ALL SAFETY PRECAUTIONS AS MENTIONED IN ELECTRICAL LAYOUT, SAFETY MANUAL & RELEVANT STANDARD CODES, SHALL BE
V1 V1 SCRUPULOUSLY FOLLOWED WHILE EXECUTION OF WORK.
LINTEL LVL
7.65 LVL. B CONCRETE
7. THE CEMENT SHALL BE ORDINARY PORTLAND CEMENT WITH C3A CONTENT FROM 5 TO 8 % FOR ALL CIVIL WORK.
CURTAIN CURTAIN

002 4
GLAZING GLAZING
8. ALL THE RCC WORK SHALL BE CARRIED OUT AS PER IS 456-2000, WITH LATEST REVISION.

005 1
9. THE GRADE OF CONCRETE SHALL BE M-30, WITH MINIMUM CEMENT CONTENT OF 400 KG/M³. EXCEPT LEAN CONCRETE MIX DESIGN

008 2
SHALL BE DONE CONSIDERING 'SEVERE ENVIRONMENT' EXPOSURE CONDITIONS.
SUNK SLAB 10. THE GRADE OF LEAN CONCRETE SHALL BE M-20
CONFORENCE ROOM L.TOILET G.TOILET STAFF/OFFICE

009
F.F.L 1
5.25 LVL.
11. CONCRETING OF ALL CIVIL WORKS UNDER BIDDER SCOPE FOR GRADE OF M30 & M20 SHALL BE DONE WITH THE HELP OF DIGITAL
WEIGH BATCHER OR FLORI ( MOBILE CONCRETE BATCHING PLANT) ONLY.
12. ALL CONCRETE SHALL BE MACHINE MIXED, VIBRATED & CURED FOR MINIMUM 10 DAYS.
RECEPTION 13. USE OF NEEDLE VIBRATOR IS COMPULSORY FOR ALL CONCRETE WORKS.
LINTEL LVL.
C REINFORCEMENT
3.40 LVL. 14. TMT (HIGH YIELD STRENGTH DEFORMED STEEL BARS) CRS (CORROSION RESISTANT STEEL) BARS COATED WITH FUSION BONDED
EPOXY PAINT OF GRADE FE-500 D BARS CONFORMING TO IS-1786 SHALL BE USED IN ALL CIVIL WORKS.

0524
W2A W1 W1 W1 W1 W2 W2 W2
15. REINFORCEMENT SHALL BE BENT & FIXED IN ACCORDANCE WITH THE PROCEDURE SPECIFIED IN IS 2502-1963.
16. CLEAR COVER TO THE REINFORCEMENT SHALL BE AS UNDER
TOP BOTTOM SIDES
TRENCH DISCUSSION
LV ROOM ROOM · FOOTING (RAFT & ISOLATED) 50 75 50

009
PLATFORM F.F.L
1.00 LVL. · PILE CAPS 50 100 50
E E
· PILE 75 75 75
· GRADE BEAM - 40 40
F.G.L · COLUMNS & PEDESTALS 50 - 50
0.00 LVL. · BEAMS ABOVE GROUND LEVEL 35 35 35
A B C D E F G
· GRADE SLAB 25 25 25
· LINTEL BEAMS 25 25 25
SECTION - 1 · SLABS & STAIRCASE 25 25 25
· CABLE TRENCHES BASE SLAB 20 35 35
· WALL 20 35 35
17. LAP LENGTH SHOULD BE 50 TIMES OF DIA..
18. LAP AT SUPPORT SECTION, JOINT SECTION & MID SPAN SHALL BE AVOIDED.
19. OVERLAPPING OF REINFORCEMENT SHALL BE STAGGERED.
20. UNLESS OTHERWISE SPECIFIED DISTN., STEEL SHOULD BE 8 MM. TOR @ 200 MM. C/C.
21. IN CASE OF CONTINUOUS SUPPORT, REINFORCEMENTS ARE DEFERENT FOR TWO ADJACENT BEAMS / SLABS, THE HIGHER SUPPORT
REINFORCEMENT OF THE TWO SHALL BE PROVIDED AT THE SUPPORT
PARAPET WALL
D FOUNDATION

00 9
T.O.C. 22. IN THE COURSE OF EXCAVATION, IF, SUB SOIL STRATA DIFFERS IN COMPARE TO SBC REPORT. THE SAME SHALL BE REPORTED TO THE
9.45 LVL. CONCERN FOR NECESSARY STEPS BY THE ENGINEERING CELL.
RCC BEAM BOTTOM
23. LAY-OUT, LINE-OUT & ORIENTATION SHALL BE CHECKED JOINTLY BY E. E. / D. E. - (CIVIL) & E. E. / D. E. - (CONST), ON THE BASIS OF
D APPROVED ELECTRICAL LAY-OUT, GA DRAWING & THIS DRAWING, PRIOR TO START THE WORK. D
· FOR OPEN FOUNDATION ( IF REQUIRED)
LINTEL LVL 24. NO FOUNDATION SHALL REST ON FILLED-UP SOIL / BLACK COTTON SOIL.
7.65 LVL.
· IF FILLED UP SOIL ENCOUNTERED, FOUNDATION SHALL BE TAKEN 300 MM BELOW VIRGIN SOIL.

002 4
CURTAIN · IF FOUNDATION FALLS ON EXCAVATED TRENCHES OF ADJOINING FOUNDATION, THAN FOUNDATION SHALL EXTENDED UP TO THE

OT P U(
GLAZING
D D0 DEPTH OF ADJOINING FOUNDATION.
· IF BLACK COTTON SOIL ENCOUNTERED, AT FOUNDATION DEPTH, THAN FOUNDATION SHALL REST ON COMPACTED SAND BED OF 300MM
ALUMINIUM ALUMINIUM
THICK.

9I NI MUL A
PARTION PARTION

OTT OB MAEB
0U
2000 WIDE PASSAGE

00 9
00 9
F.F.L 1 BRICK/BLOCK 25. BACK FILLING OF FOUNDATION TRENCHES SHALL BE DONE WITH USE OF NON COHESIVE SOIL ONLY.
5.25 LVL.

LL)AMW
MASONARY · THE BACK FILLING AROUND THE FOUNDATION SHALL BE ADEQUATE TO ACHIEVE THE PROCTOR DENSITY OF 95%.
WALL
· FOR PILE FOUNDATION

NO I TI T RAP 0M
26. THE GRADE OF CONCRETE SHALL BE M-30 FOR PILE CAP, COLUMN, BEAM, RAFT, ETC., EXCEPT LEAN CONCRETE.

05 4
RECEPTION

K C OL B/ K CI RB
27. THE GRADE OF CONCRETE FOR PILE SHALL BE M-30, CONFIRMING TO IS 456 WITH MINIMUM CEMENT CONTENT AS 400 kg. / M³. WITH
LINTEL LVL.
3.40 LVL.
TREMIE CONCRETE.
28. CONCRETE SLUMP SHALL BE 120 TO 150MM. (VERY HIGH DEGREE OF WORKABILITY) FOR PILE FOUNDATION WITH TREMIE CONCRETE.

052 4
W2 W2 W2 29. FOR CONSTRUCTION SPECIFICATION OF IS 2911 (PART-III), LATEST REVISION SHALL BE FOLLOWED.
DA RD
30. THE PILE SHOULD PROJECT 100MM. IN TO THE PILE CAP CONCRETE.

000 3
S.S
RAILING
31. INTEGRITY TEST TO BE DONE FOR ALL PILES, PRIOR TO CAST PILE CAP.
TERNCH PLATFORM
32. INITIAL & ROUTINE PILE LOAD TEST SHALL BE CARRIED OUT ON ANY ONE PILE & SHALL BE COMPARE WITH VALUE OF SBC
2000 WIDE PASSAGE

00 9
F.F.L REPORT.PAIOR TO START CONCRETING WORK.

LL A W
1.00 LVL.
C SPECIAL NOTE:- C

I TI T RAP MUI NI MUL A


MOTT OB MAEB OT P U
NO

000 1
· FOR SCADA ROOM AT FIRST FLOOR, CUT OUT TO BE KEPT IN RCC SLAB AND APPROPRIATE ARRANGEMENT FOR HANGING CABLE
F.G.L

K C OL B/ K CI RB
0.00 LVL.
TRENCH BELOW SLAB AND ARRANGEMENT FOR CABLE ROUTE FROM G.L. TO F.F. SHALL BE PROVIDED.
A B C D E F G · CARE TO BE TAKEN TO SEE THAT ALL THE ARRANGEMENT PROVIDED FOR CABLE IN AND OUT SYSTEM SHALL BE AESTHETICALLY
PLEASANT AND STRONG ENOUGH AS PER RELEVANT CODES AND STANDARDS.
· CUT-OUT ARE INDICATIVE. IT SHALL BE DECIDE ON THE BASIS OF ACTUAL REQUIREMENT. AND IT SHOULD BE AS PER REQUIREMENT OF
SECTION - 2 TECHNICAL SPECIFICATION, LAY-OUT,STANDERDS AND I.S. CODE.
· EXHAUST FAN SHALL BE PROVIDED IN EACH TOILET BLOCK.
· ORIENTATION OF CONTROL ROOM BUILDING SHALL BE AS PER APPROVED ELECTRICAL LAYOUT.
T.O.C.

00 6
CAGE 12.00 LVL. · IN CASE, GIS BUILDING IS ADJOINING TO C.R. BUILDING & GIS BUILDING SHALL BE DESIGNED AS PER SITE REQUIREMENT.
LADDER · ALL ELECTRIC WIRING / LINE, WATER SUPPLY LINE AND DRAINAGE LINE SHALL BE CONCEALED.
· ALL THE ELECTRICAL OPENINGS IN THE BUILDING SHALL BE SEALED WITH SEALING COMPOUND AFTER COMPLETION OF CABLING WORK
& TO ENSURE WATER TIGHTNESS & FIRE RETARDANT.
D2
· INSERT PLATES ARE TO BE PROVIDED FOR CABLE TRAY SUPPORT STRUCTURES W.R.T CABLE TRAY ARRANGEMENT DRAWING.
004 2

· ALL ELECTRIC WIRING / LINE, WATER SUPPLY LINE AND DRAINAGE LINE SHALL BE CONCEALED

00 9
T.O.C. GENERAL NOTES.
9.45 LVL. 1. CERTAIN MINIMUM REQUIREMENTS ARE INDICATED IN THIS DRAWING FOR GUIDANCE PURPOSE. HOWEVER BIDDER SHALL QUOTE THE
RATES ACCORDING TO SYSTEM REQUIREMENTS.
2. THIS DRAWING IS GIVEN FOR BID PURPOSE ONLY. HOWEVER, BIDDER HAS TO DEVELOP CONSTRUCTION DRAWINGS AND RELEVANT
B B
STRUCTURE DRAWINGS ON THE BASIS OF THIS DRAWING, APPROVED LAY OUT OF SUB STATION, TENDER SPECIFICATION, SBC REPORT,
LINTEL LVL SITE CONDITION, CONTOUR MAP AND AS PER CODES & STANDARDS.
7.65 LVL.
ALUMINIUM
3. CABLE TRENCH AND CUT-OUT ARE INDICATIVE. IT SHALL BE DECIDE ON THE BASIS OF ACTUAL REQUIREMENT. AND IT SHOULD BE AS
PARTITION PER REQUIREMENT OF TECHNICAL SPECIFICATION, LAY-OUT,STANDARDS AND I.S. CODE.
DB
D1 D3
4. ENTRY OF CABLE TRENCH FROM YARD TO C.R. BLDG & FROM GIS HALL / LCC PANEL ROOM TO C.R. BLDG SHALL BE ADJUSTED /
ARRANGED AS PER APPROVED ELECTRICAL LAY OUT OR SHALL BE DECIDED DURING DETAILED ENGINEERING.
ALUMINIUM
PARTION
TENDER PURPOSE
SCADA ROOM PASSAGE L.TOILET
00 9

F.F.L 1 G
5.25 LVL. GUJARAT ENERGY TRANSMISSION CORPN.LTD.
LEGEND. E
T S.P.VIDYUT BHAVAN, RACE COURSE,
SUNK FGL = FINISHED GROUND LEVEL (LVL. 0.000 mt)
SLAB C
FFL = FINISHED FLOOR LEVEL (LVL. 1.000 mt) O
VADODARA - 390 007
FALSE FALSE LINTEL LVL.
CEILING CEILING 3.40 LVL. TOC = TOP OF CONCRETE
ALUMINIUM BOC = BOTTOM OF CONCRETE.
PARTITION ALUMINIUM W2
DA PARTITION
DA
D3

TRENCH BATTERY ROOM


SECTION OF CONTROL ROOM BUILDING
TESTING LAB PASSAGE L.TOILET

00 9
00 9
F.F.L
AT 400KV DHOLERA (GIS) SUB STATION

LL A W
LL A W
1.00 LVL.
A A
CHECKED: APPD:
F.G.L

K C OL B/ K CI RB
K C OL B/ K CI RB

0.00 LVL. SIZE:


A B C D E F G
DE(CIVIL) EE(CIVIL) EE(ENGG) ACE(ENGG.) A1
SCALE: DATE: DRG. NO: SHEET: REV:
SECTION - 3 R0 FIRST PREPARATION.
GETCO / C /
REV: DESCRIPTION N.T.S. 26.09.19 5 OF 6 R0
4S-410/CR-17